Deedo IDDP-THN-D0WRCompletion was pushed back 1 year to Aug 2024, and that date has passed too; no MahaRERA orders on record; 72% of its units are booked.
Khuntavali, Thane 421501 · by Geetai Foundation
Buying a flat here?
See every deed registered on it.
Completion was pushed back 1 year to Aug 2024, and that date has passed too
- This projectRegistered 14 Dec 2020, completion promised 28 Aug 2023, revised to 31 Aug 2024, and still not shown completed today.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700027507
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700027507 | 14 Dec 2020 | 28 Aug 2023 | 31 Aug 2024 | Geetai Foundation | Project page |
Documents55
3 documents held by Deedo, 52 filings listed on MahaRERA's project page
Show all 55 documentsShow fewer documents
Migrated
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)architect certificate_compressed.pdf · uploaded 2 Dec 2020Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)engineer certificate_compressed.pdf · uploaded 2 Dec 2020Source
- 1 Proforma of Allotment letterSale agreement performa.pdf · uploaded 2 Dec 2020Source
- 1 Details of encumbrancesNo encumbrance.pdf · uploaded 8 Dec 2020Source
- 1 Copy of Layout Approval (in case of layout)Building plan_compressed (1).pdf · uploaded 8 Dec 2020Source
- 1 Building Plan Approval / NA Order for plotted developmentBuilding plan_compressed (1).pdf · uploaded 8 Dec 2020Source
- 1 Declaration in FORM BFORM B-converted.pdf · uploaded 8 Dec 2020Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 8 Dec 2020Source
- 2 Proforma of Allotment letterAllotment letter.pdf · uploaded 8 Dec 2020Source
- 2 Commencement Certificates / NA Order for plotted developmentcommencement certificate Revised_compressed.pdf · uploaded 27 Jun 2022Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architects certificate 31-Mar-22.pdf · uploaded 27 Jun 2022Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer's certificate 29-4-22_compressed.pdf · uploaded 27 Jun 2022Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate 31-7-2022.pdf · uploaded 28 Aug 2022Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer's certificate 13-8-2022_compressed.pdf · uploaded 28 Aug 2022Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)geetai foundation.pdf · uploaded 20 Oct 2022Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer's certificate 13-10-2022.pdf · uploaded 20 Oct 2022Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect's Certificate 31-12-2022.pdf · uploaded 26 Jan 2023Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer's certificate 13-1-2023.pdf · uploaded 26 Jan 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Annual Report 20-21.pdf · uploaded 27 Mar 2023Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect's Certificate 31-03-2023.pdf · uploaded 8 Apr 2023Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer's certificate 31-3-23_compressed.pdf · uploaded 8 Apr 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Annual Report 21-22.pdf · uploaded 28 Apr 2023Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT LETTER.pdf · uploaded 12 Jul 2023Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer certificate.pdf · uploaded 12 Jul 2023Source
- 1 Declaration about Commencement CertificateCommencement Declaration.pdf · uploaded 12 Sep 2023Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)architect certificate.pdf · uploaded 12 Sep 2023Source
- 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)eng certificate.pdf · uploaded 12 Sep 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)2A (21).pdf · uploaded 12 Sep 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)2A (22).pdf · uploaded 12 Sep 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)2A (23).pdf · uploaded 12 Sep 2023Source
- 1 Disclosure of sold/ booked inventory2 Disclosure of sold_ booked inventory.pdf · uploaded 13 Sep 2023Source
- 2 Disclosure of sold/ booked inventorySold Unsold Details.pdf · uploaded 13 Sep 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBank Account Details.pdf · uploaded 13 Sep 2023Source
- 1 Deviation Report with respect to Allotment letterNo Deviation.pdf · uploaded 13 Sep 2023Source
- 1 Deviation Report with respect to model copy of AgreementDeviation Report 1.pdf · uploaded 13 Sep 2023Source
- 1 PAN Cardpan card.pdf · uploaded 18 Sep 2023Source
- 2 Declaration about Commencement CertificateCC declaration.pdf · uploaded 18 Sep 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 8 Sep 2023_compressed.pdf · uploaded 18 Sep 2023Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 8 Sep 2023_compressed.pdf · uploaded 18 Sep 2023Source
- 3 Disclosure of sold/ booked inventorydec of wrong upload.pdf · uploaded 6 Oct 2023View
- 1 Other – Technicaldec of wrong upload.pdf · uploaded 6 Oct 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 (2022 to 2023).pdf · uploaded 29 Apr 2024Source
Technical
Technical (Architect)
- Documentarchitect certificate.pdf · uploaded 12 Sep 2023Source
Technical (Engineer)
- Documenteng certificate.pdf · uploaded 12 Sep 2023Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel Plot bearing S. No.25 H No. 19 CTS No 63 16 At Navare Park
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK, Shop32 units in all
- Address
- Plot bearing S. No.25 H No. 19 CTS No 63 16 At Navare Park Village Kohoj Khuntavali Ambernath west, Kohoj Khuntavali, AmbernathPIN 421501
- Village
- Khuntavali, Ambarnath taluka
- Land area for this project
- 1,060 sq m (11,410 sq ft)
- Permissible built-up area
- 1,060 sq m (11,410 sq ft)
- Sanctioned built-up area
- 1,060 sq m (11,410 sq ft)
- Designated bank account
- 76
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
Plot bearing S. No.25 H No. 19 CTS No 63 16 At Navare Park Village Kohoj Khuntavali Ambernath west
Boundaries
- North
- S No 25 H No 21
- South
- S No 39 H No 3 and Road
- East
- S No 25 H No 4 and S No 25 H No 20
- West
- S No 39 H No 3 and S No 25 H No 21
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking32 units
23 of 32 units booked (72%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 35.66 sq m · 384 sq ft | 1 | 0 |
| 1BHK | 35.66 sq m · 384 sq ft | 1 | 1 |
| 1BHK | 35.66 sq m · 384 sq ft | 1 | 1 |
| 1BHK | 36.07 sq m · 388 sq ft | 1 | 1 |
| 1BHK | 38.26 sq m · 412 sq ft | 1 | 1 |
| 1BHK | 38.26 sq m · 412 sq ft | 1 | 0 |
| 1BHK | 38.56 sq m · 415 sq ft | 1 | 1 |
| 1BHK | 39.17 sq m · 422 sq ft | 1 | 1 |
Show all 32 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 39.67 sq m · 427 sq ft | 1 | 1 |
| 1BHK | 39.67 sq m · 427 sq ft | 1 | 1 |
| 1BHK | 39.8 sq m · 428 sq ft | 1 | 0 |
| 1BHK | 39.8 sq m · 428 sq ft | 1 | 1 |
| 1BHK | 39.8 sq m · 428 sq ft | 1 | 0 |
| 1BHK | 39.85 sq m · 429 sq ft | 1 | 1 |
| 1BHK | 40.62 sq m · 437 sq ft | 1 | 1 |
| 1BHK | 40.62 sq m · 437 sq ft | 1 | 1 |
| 1BHK | 40.62 sq m · 437 sq ft | 1 | 1 |
| 1BHK | 40.62 sq m · 437 sq ft | 1 | 1 |
| 1BHK | 40.62 sq m · 437 sq ft | 1 | 1 |
| 1BHK | 40.62 sq m · 437 sq ft | 1 | 1 |
| 2BHK | 61.29 sq m · 660 sq ft | 1 | 1 |
| 2BHK | 61.29 sq m · 660 sq ft | 1 | 0 |
| 2BHK | 61.78 sq m · 665 sq ft | 1 | 1 |
| 2BHK | 61.84 sq m · 666 sq ft | 1 | 0 |
| 2BHK | 61.84 sq m · 666 sq ft | 1 | 1 |
| 2BHK | 62.26 sq m · 670 sq ft | 1 | 1 |
| 2BHK | 63.95 sq m · 688 sq ft | 1 | 0 |
| 2BHK | 63.95 sq m · 688 sq ft | 1 | 0 |
| 2BHK | 64.33 sq m · 692 sq ft | 1 | 1 |
| 2BHK | 64.33 sq m · 692 sq ft | 1 | 0 |
| Shop | 18.8 sq m · 202 sq ft | 1 | 1 |
| Shop | 20.2 sq m · 217 sq ft | 1 | 1 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Vinod S Navare | — |
| Chartered accountant | Haresh Ranghani | — |
| Engineer | Atul Kudtarkar And Associates | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Khuntavali
- Dave TowersRERA PC1330002600700
- Gajanan PlazaRERA PC1330002600456
- Patels PrimeRERA PC1330002600154
- Girija ChsRERA PM1330002600104
- Swami Samarth Apartment Co.op.hsg.soc.ltd & Ambreshwar HeritageRERA PM1330002500867
- Shankar Heights Phase 6RERA P51700080923
- Nurani Cooperative Housing Society LtdRERA P51700080245
- Hiltron Business ParkRERA P51700080159
All 39 projects in Khuntavali · Compare Swami Darshan with another project