RERA projects in Vasaivirar City (M Corp)
863 projects under 915 MahaRERA registrations, registered 2017–2026. 30% have a completion date extended beyond the one promised.
Locality
863RERA projects
915Registrationssome projects hold several
365Completion still due550 past their completion date
26 monthsMedian extension beyond promised date30% of registrations extended
16Regulatory caseson 14 projects
8Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 397 |
| 2018 | 24 |
| 2019 | 54 |
| 2020 | 38 |
| 2021 | 62 |
| 2022 | 83 |
| 2023 | 81 |
| 2024 | 113 |
| 2025 | 57 |
| 2026 | 5 |
Projects in Vasaivirar City (M Corp)
863 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Yashvi Pride Building No.3 Wing-OYashvi Pride LLP | P99000081100 | 2 Mar 2026 | 31 Dec 2027 | — | Not yet due | 0 |
| Urban HomesUrban Developers | P99000081093 | 9 Feb 2026 | 30 Jun 2027 | — | Not yet due | 0 |
| Tania WillowsTania Realtors | P99000081082 | 7 Jan 2026 | 31 Mar 2028 | — | Not yet due | 0 |
| Shalibhadra HeightsShree Nakoda Developers | P99000081076 | 26 Dec 2025 | 31 Dec 2027 | — | Not yet due | 0 |
| Mukti Narayan Co Op Hsg Soc LtdShiv Sai Builders And Developers | P99000081056 | 2 Dec 2025 | 31 Dec 2029 | — | Not yet due | 0 |
| Marshal HeightsArpan Builder & Developers | P99000081046 | 24 Nov 2025 | 31 Dec 2030 | — | Not yet due | 0 |
| Dhananjay StarlightDhanraj Starlight | P99000081038 | 14 Nov 2025 | 20 Dec 2029 | — | Not yet due | 0 |
| Crystal CrownCrystal Ventures | P99000081027 | 20 Oct 2025 | 31 Dec 2027 | — | Not yet due | 0 |
| Bitcon Paradise ComplexKiran Development Corporation | P99000081018 | 15 Oct 2025 | 31 Dec 2030 | — | Not yet due | 0 |
| Gurmukh Apartments by Amrit DevelopersDivekar And Vanmali Constructions | P99000080985 | 24 Sep 2025 | 31 Dec 2028 | — | Not yet due | 0 |
| Chandansar HeightsJivdaya Infra LLP | P99000080974 | 15 Sep 2025 | 31 Dec 2031 | — | Not yet due | 0 |
| Cosmos Serenity Phase 1Cosmos Prime Projects Ltd | P99000080932 | 22 Aug 2025 | 31 Mar 2030 | — | Not yet due | 0 |
| Yashwant Avenue 3Ajiv Yashwant Patil | P99000080900 | 4 Aug 2025 | 31 Dec 2029 | — | Not yet due | 0 |
| Shah HeightsP.v.associates | P99000080860 | 23 Jul 2025 | 31 Dec 2026 | — | Not yet due | 0 |
| EvaraNeminath Poonam Realty LLP | P99000080818 | 14 Jul 2025 | 31 Dec 2030 | — | Not yet due | 0 |
| Zalawad Nagar Building No 2 Chs LtdShree Mahavir Builders And Developers | P99000080785 | 7 Jul 2025 | 31 Dec 2028 | — | Not yet due | 0 |
| Ashoka IconicShree Ashoka Infra | P99000080634 | 23 Jun 2025 | 31 Dec 2029 | — | Not yet due | 0 |
| Veer AttarV A Housing | P99000080644 | 23 Jun 2025 | 31 Mar 2028 | — | Not yet due | 0 |
| Dhananjay Grand AvenueShree Sai Kiran Builders And Developers | P99000080592 | 16 Jun 2025 | 20 Dec 2030 | — | Not yet due | 0 |
| Ekata ResidencyShantee Homes Proprietor Raaz Mohammed Abdul Samad Pathan | P99000080576 | 16 Jun 2025 | 30 Apr 2029 | — | Not yet due | 0 |
| Radhashyam Co-Operative Housing Society Limitedshree sadguru realty | P99000080401 | 2 Jun 2025 | 1 Apr 2028 | — | Not yet due | 0 |
| Shanta BhavanSanjari Properties LLP | P99000080383 | 29 May 2025 | 31 Dec 2028 | — | Not yet due | 0 |
| Sai Balaji ApartmentShree Swami Samarth Developers | P99000080342 | 26 May 2025 | 31 Dec 2027 | — | Not yet due | 0 |
| The PancharatnaRadhe Builder and Developer | P99000080337 | 22 May 2025 | 31 Dec 2027 | — | Not yet due | 0 |
| Atharv-VedPragati Ventures | P99000080299 | 19 May 2025 | 31 Dec 2028 | — | Not yet due | 0 |
Other localities in Vasai
Most active promoters
By projects registered here, as named on MahaRERA.
- Shantee Realty And Life Space6 projects
- M/s AMEYA BUILDERS & PROPERTY DEVELOPERS5 projects
- Shantee Housing5 projects
- Brijesh Satish Dattani4 projects
- Jsb Homemakers Private Limited4 projects
- Kawali Builders4 projects
- Viva Winner Venture Relators LLP4 projects
- Ajmera Developers3 projects
- Bachraj Developers3 projects
- Cosmos Prime Projects Ltd3 projects
Data through11 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology