Skip to content

Diwanman, Palghar

Deedo IDDL-PAL-DIWANMAN

8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects11
Registrations11
Completion still due101 past their date
Median extension4 months73% of registrations extended
Regulatory cases0none on MahaRERA's lists

8 in 10 registrations run late here

11 MahaRERA registrations in Diwanman

2 not yet due8 extended, not yet due1 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Diwanman

11 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Kanti Arvat SkyArvat RealtyDue Dec 2028——
Mona TowerTania RealtorsDue Aug 2031, extended 4 mo——
Ruturaj HomesRuturaj HomesDue Apr 2031, extended 4 mo——
Imperial DhanrajImperial Buildcon RealtyDue Nov 2029, extended 4 mo——
Suryoday HeightsSunray RealtyDue Apr 2029, extended 4 mo——
All 11 projects →
Diwanman market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Arvat Realty1 project
  2. Imperial Buildcon Realty1 project
  3. Imperial Builders1 project
  4. R And J Buildline LLP1 project
  5. Ruturaj Homes1 project
  6. Shantee Homes Proprietor Raaz Mohammed Abdul Samad Pathan1 project
  7. Shreeji & Associates1 project
  8. Sunray Realty1 project
  9. Sunrock Constructions LLP1 project
  10. Tania Realtors1 project

Diwanman, in questions

How many projects in Diwanman run late?

8 in 10 MahaRERA registrations (9 of 11): their completion date was extended or has passed, data through 27 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Diwanman by Deedo. Medians on fewer than 3 deeds are not shown.

Data through27 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology