Chandrapada, Palghar
Deedo IDDL-PAL-CHANDRAPADA9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects20
Registrations20
Completion still due128 past their date
Median extension4 months60% of registrations extended
Regulatory cases0none on MahaRERA's lists
9 in 10 registrations run late here
20 MahaRERA registrations in Chandrapada
3 not yet due9 extended, not yet due8 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Chandrapada
20 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Dixit EnclavesShivansh Builders & Developers | Due Dec 2029 | — | — |
| Kalpatru AvenueCrowngoldinfra LLP | Due Apr 2031, extended 4 mo | — | — |
| Mahalaxmi Nagar - Bldg No.5Mahalaxmi Homemakers Private Limited | Due Apr 2029, extended 4 mo | — | — |
| Radha Nilaya Phase 2Kishore Anand Shetty | Due Apr 2031, extended 4 mo | — | — |
| Tivoli TowersKohinoor Enclave | Due Apr 2029, extended 4 mo | — | — |
Nearby: other villages in Vasai
Most active promoters
- Mahalaxmi Homemakers Private Limited3 projects
- Shantee Housing2 projects
- Amrita Sandip Barmera1 project
- Crowngoldinfra Llp1 project
- D K Realtors1 project
- Harsh Tirupati Developers Llp1 project
- Kishore Anand Shetty1 project
- Kohinoor Enclave1 project
- Panchavati Builders And Developers1 project
- Panchratna Developers1 project
Chandrapada, in questions
How many projects in Chandrapada run late?
9 in 10 MahaRERA registrations (17 of 20): their completion date was extended or has passed, data through 3 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Chandrapada by Deedo. Medians on fewer than 3 deeds are not shown.
Data through3 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology