Pelhar, Palghar

9 in 10 MahaRERA registrations here have pushed their completion date back.

RERA projects11
Registrations11
Completion still due110 past their date
Median extension4 months91% of registrations extended
Regulatory cases0none on MahaRERA's lists
Pelhar market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Projects in Pelhar

11 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Diamond Heritage-2Diamond Palm Infrastructure Private LimitedP9900008066623 Jun 202531 Dec 203030 Apr 2031Extended 4 mo0
Hayaat Seven HillM M DevelopersP990000794857 Mar 202531 Dec 202930 Apr 2030Extended 4 mo0
Krishna Industrail HubShreeji InfraP9900007930028 Feb 202531 Dec 202730 Apr 2028Extended 4 mo0
Krishna Industrial HubShreeji BuildconP990000787368 Jan 202531 Dec 202730 Apr 2028Extended 4 mo0
Momin HeightsA-99 DevelopersP9900007769821 Oct 202431 Dec 202631 Dec 2026Not yet due0
Halima HeritageStar Builders And DevelopersP9900005639631 May 202431 Dec 202830 Apr 2029Extended 4 mo0
Zar LandmarkZar Builders & DevelopersP9900005613216 May 202431 Dec 202930 Apr 2030Extended 4 mo0
Dhananjay And Hayaat Industrial EstateM M Infra ProjectP9900005478912 Feb 202431 Dec 202830 Apr 2029Extended 4 mo0
Diamond Heritage 1Diamond Palm Infrastructure Private LimitedP9900005392311 Dec 202331 Dec 202630 Apr 2027Extended 4 mo0
Honest HeightsMetro DevelopersP9900005363921 Nov 202331 Dec 202730 Apr 2028Extended 4 mo0
Tetris Hill ViewAvora RealtyP9900005337727 Oct 202331 Dec 202930 Apr 2030Extended 4 mo0

Most active promoters

  1. Diamond Palm Infrastructure Private Limited2 projects
  2. A-99 Developers1 project
  3. Avora Realty1 project
  4. Metro Developers1 project
  5. M M Developers1 project
  6. M M Infra Project1 project
  7. Shreeji Buildcon1 project
  8. Shreeji Infra1 project
  9. Star Builders And Developers1 project
  10. Zar Builders & Developers1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology