Pelhar, Palghar
9 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects11
Registrations11
Completion still due110 past their date
Median extension4 months91% of registrations extended
Regulatory cases0none on MahaRERA's lists
Projects in Pelhar
11 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Diamond Heritage-2Diamond Palm Infrastructure Private Limited | P99000080666 | 23 Jun 2025 | 31 Dec 2030 | 30 Apr 2031 | Extended 4 mo | 0 |
| Hayaat Seven HillM M Developers | P99000079485 | 7 Mar 2025 | 31 Dec 2029 | 30 Apr 2030 | Extended 4 mo | 0 |
| Krishna Industrail HubShreeji Infra | P99000079300 | 28 Feb 2025 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
| Krishna Industrial HubShreeji Buildcon | P99000078736 | 8 Jan 2025 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
| Momin HeightsA-99 Developers | P99000077698 | 21 Oct 2024 | 31 Dec 2026 | 31 Dec 2026 | Not yet due | 0 |
| Halima HeritageStar Builders And Developers | P99000056396 | 31 May 2024 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Zar LandmarkZar Builders & Developers | P99000056132 | 16 May 2024 | 31 Dec 2029 | 30 Apr 2030 | Extended 4 mo | 0 |
| Dhananjay And Hayaat Industrial EstateM M Infra Project | P99000054789 | 12 Feb 2024 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Diamond Heritage 1Diamond Palm Infrastructure Private Limited | P99000053923 | 11 Dec 2023 | 31 Dec 2026 | 30 Apr 2027 | Extended 4 mo | 0 |
| Honest HeightsMetro Developers | P99000053639 | 21 Nov 2023 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
| Tetris Hill ViewAvora Realty | P99000053377 | 27 Oct 2023 | 31 Dec 2029 | 30 Apr 2030 | Extended 4 mo | 0 |
Nearby: other localities in Vasai
Most active promoters
- Diamond Palm Infrastructure Private Limited2 projects
- A-99 Developers1 project
- Avora Realty1 project
- Metro Developers1 project
- M M Developers1 project
- M M Infra Project1 project
- Shreeji Buildcon1 project
- Shreeji Infra1 project
- Star Builders And Developers1 project
- Zar Builders & Developers1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology