Malonde, Palghar

Deedo IDDL-PAL-MALONDE

6 in 10 MahaRERA registrations here have pushed their completion date back.

RERA projects7
Registrations7
Completion still due61 past their date
Median extension4 months57% of registrations extended
Regulatory cases0none on MahaRERA's lists
Malonde market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

7 in 10 registrations run late here

7 MahaRERA registrations in Malonde

2 not yet due4 extended, not yet due1 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Malonde

7 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
AarambhVartak Lifespaces LLPDue May 2029——
Abdul Hakeem Heights A WingYash LifespacesDue Jul 2029, extended 4 mo——
Lotus HarmonyShree Ekveera ConstructionDue Jul 2031, extended 4 mo——
AvanindraOjas VenturesDue Aug 2029, extended 4 mo——
Dream NestM/s. Clement Regency DevelopersDue Jun 2027—33%
HeavensKeyatorsDue Apr 2029, extended 4 mo—37%
Solitaire CastlePam InfrastructureDue Dec 2029——

Most active promoters

  1. Keyators1 project
  2. M/s. Clement Regency Developers1 project
  3. Ojas Ventures1 project
  4. Pam Infrastructure1 project
  5. Shree Ekveera Construction1 project
  6. Vartak Lifespaces LLP1 project
  7. Yash Lifespaces1 project
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology