Skip to content
Others · 1 building · 107 unitsRERA P99000048740

Heavens

Deedo IDDP-PAL-Y0SX

Completion was pushed back 4 months, to Apr 2029; no MahaRERA orders on record; 37% of its units are booked.

Malonde, Palghar 401201 · Promoter: Keyators

DeliveryExtended 4 moPromised Dec 2028 · now due Apr 2029RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales37% booked40 of 107 units · as the promoter reported to MahaRERA
Heavens project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

Completion was pushed back 4 months, to Apr 2029

  • This projectRegistered 17 Jan 2023, completion promised 31 Dec 2028, revised to 30 Apr 2029.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP99000048740
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P9900004874017 Jan 202331 Dec 202830 Apr 2029KeyatorsProject page
Documents127

1 document held by Deedo, 126 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardKeyator Pan Card.pdf · uploaded 22 Nov 2022Source

Legal

  • Declaration Form BForm B.pdf · uploaded 22 Nov 2022Source
  • Legal Title reportTitle Keyator.pdf · uploaded 15 Dec 2022Source
  • Legal Title reportTitle Report as per RERA.pdf · uploaded 8 Jan 2023Source
  • Declaration Form BConveyance Deed.pdf · uploaded 11 Jul 2026Source
  • Declaration Form BLegal Title Report.pdf · uploaded 18 Jul 2026Source
  • Declaration Form BForm B Keyators.pdf · uploaded 18 Jul 2026Source
Show all 127 documentsShow fewer documents

Migrated

  • 1 PAN CardKeyator Pan Card.pdf · uploaded 22 Nov 2022Source
  • 1 Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 22 Nov 2022Source
  • 1 Building Plan Approval / NA Order for plotted developmentPlan 14 floor.pdf · uploaded 22 Nov 2022Source
  • 2 Building Plan Approval / NA Order for plotted developmentPlan Gr 1 and 2.pdf · uploaded 22 Nov 2022Source
  • 3 Building Plan Approval / NA Order for plotted developmentTypical Plan.pdf · uploaded 22 Nov 2022Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 22 Nov 2022Source
  • 2 Commencement Certificates / NA Order for plotted developmentNA.pdf · uploaded 22 Nov 2022Source
  • 1 Declaration about Commencement CertificateDeclaration Form D.pdf · uploaded 22 Nov 2022Source
  • 1 Declaration in FORM BForm B.pdf · uploaded 22 Nov 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 22 Nov 2022Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 22 Nov 2022Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2A.pdf · uploaded 22 Nov 2022Source
  • 1 CERSAI detailsCERSAI_Search_Report_200252873765_For_Asset_Based_Search_22_11_2022_15_55_49_506.pdf · uploaded 22 Nov 2022Source
  • 1 Proforma of Allotment letterdraft of Allotment letter.pdf · uploaded 22 Nov 2022Source
  • 1 Proforma of Agreement for saleLatest RERA AFS 21 11 2022 Keyators Malonde land.pdf · uploaded 22 Nov 2022Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the samewrite up on details of bank account.pdf · uploaded 22 Nov 2022Source
  • 1 Deviation Report with respect to Allotment letterWrite up on deviation on allotment letter.pdf · uploaded 22 Nov 2022Source
  • 1 Deviation Report with respect to model copy of AgreementWrite up on deviation AFS.pdf · uploaded 22 Nov 2022Source
  • 1 a Details of encumbrances concerned to Financewrite up on other finance.pdf · uploaded 30 Nov 2022Source
  • 1 b Details of encumbrances concerned to Legalwrite up on other finance.pdf · uploaded 30 Nov 2022Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 30 Nov 2022Source
  • 2 CERSAI detailsCERSAI_Search_Report_200253708862_For_Asset_Based_Search_01_12_2022_17_21_53_648.pdf · uploaded 4 Dec 2022Source
  • 1 Copy of the legal title reportTitle Keyator.pdf · uploaded 15 Dec 2022Source
  • 2 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFormat A Declaration Bank Account.pdf · uploaded 22 Dec 2022Source
  • 2 Copy of the legal title reportTitle Report as per RERA.pdf · uploaded 8 Jan 2023Source
  • 2 Proforma of Allotment letterAllotment Letter as per RERA.pdf · uploaded 8 Jan 2023Source
  • 2 Proforma of Agreement for saleFinal RERA AFS 07012023 Keyators Malonde land.pdf · uploaded 8 Jan 2023Source
  • 2 Deviation Report with respect to Allotment letter1 Deviation Report with respect to Allotment letter.pdf · uploaded 8 Jan 2023Source
  • 2 Deviation Report with respect to model copy of AgreementKeyator.pdf · uploaded 10 Jan 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsKeyator Letter-Disclosure on other interest.pdf · uploaded 12 Jan 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form1.pdf · uploaded 17 May 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form2.pdf · uploaded 17 May 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form3.pdf · uploaded 17 May 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 21 Sep 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 21 Sep 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3.pdf · uploaded 16 Nov 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)form 5.pdf · uploaded 8 Apr 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 25 Jun 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 .pdf · uploaded 25 Jun 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A .pdf · uploaded 25 Jun 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 25 Jun 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 14 Oct 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 14 Oct 2024Source
  • 1 Disclosure of sold/ booked inventorySold Unsold .pdf · uploaded 14 Oct 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 14 Oct 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 14 Oct 2024Source
  • 1 Disclosure of sold/ booked inventorySold Unsold .pdf · uploaded 14 Oct 2024Source
  • 1 a Details of encumbrances concerned to FinanceKeyator Letter.pdf · uploaded 27 Dec 2024Source
  • 1 Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 27 Dec 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 27 Dec 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 27 Dec 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 27 Dec 2024Source
  • 1 Building Plan Approval / NA Order for plotted developmentSheet 2.pdf · uploaded 27 Dec 2024Source
  • 2 Building Plan Approval / NA Order for plotted developmentSheet 3.pdf · uploaded 27 Dec 2024Source
  • 3 Building Plan Approval / NA Order for plotted developmentSheet 4.pdf · uploaded 27 Dec 2024Source
  • 1 b Details of encumbrances concerned to LegalKeyator Letter.pdf · uploaded 27 Dec 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5.pdf · uploaded 15 Mar 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form1.pdf · uploaded 26 Apr 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 5.pdf · uploaded 26 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 26 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 26 Apr 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 26 Apr 2025Source
  • 1 Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 5 May 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form1.pdf · uploaded 5 May 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 5 May 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 5 May 2025Source
  • 1 Commencement Certificates / NA Order for plotted developmentRevised CC.pdf · uploaded 5 May 2025Source
  • 1 Disclosure of sold/ booked inventorySold Unsold.pdf · uploaded 5 May 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form1 .pdf · uploaded 3 Jun 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 3 Jun 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A.pdf · uploaded 3 Jun 2025Source
  • 1 Disclosure for secured/unsecured finance availed for the projectKeyator Letter.pdf · uploaded 3 Jun 2025Source
  • Form 1Form 1 Keyator.pdf · uploaded 9 Jun 2026Source
  • Form 2Form 2 Keyator.pdf · uploaded 9 Jun 2026Source
  • Form 3Form 3 Keyator.pdf · uploaded 9 Jun 2026Source
  • Disclosure of Sold and Booked InventoryDisclosure Of Sold Booked Inventory.pdf · uploaded 9 Jun 2026Source
  • Withdrawal Update Form 1Form 1 Keyator.pdf · uploaded 9 Jun 2026Source
  • Withdrawal Update Form 1Form 1 Keyator.pdf · uploaded 9 Jun 2026Source
  • Withdrawal Update Form 1Form 1 Keyator.pdf · uploaded 9 Jun 2026Source
  • Withdrawal Update Form 2Form 2 Keyator.pdf · uploaded 9 Jun 2026Source
  • Withdrawal Update Form 2Form 2 Keyator.pdf · uploaded 9 Jun 2026Source
  • Withdrawal Update Form 2Form 2 Keyator.pdf · uploaded 9 Jun 2026Source
  • Withdrawal Update Form 3Form 3 Keyator.pdf · uploaded 9 Jun 2026Source
  • Withdrawal Update Form 3Form 3 Keyator.pdf · uploaded 9 Jun 2026Source
  • Withdrawal Update Form 3Form 3 Keyator.pdf · uploaded 9 Jun 2026Source
  • Form 2A (FY 2025-2026)Form 2A Keyator.pdf · uploaded 9 Jun 2026Source
  • Form 5 (FY 2024-2025)Form 5 Keyator.pdf · uploaded 9 Jun 2026Source
  • Withdrawal Update Form 1Keyator Form 1 Q1 .pdf · uploaded 31 Jul 2026Source
  • Withdrawal Update Form 2Keyator Form 2 Q1 .pdf · uploaded 31 Jul 2026Source
  • Withdrawal Update Form 3Keyator Form 3 Q1.pdf · uploaded 31 Jul 2026Source

Technical

  • DocumentLayout.pdf · uploaded 22 Nov 2022Source
  • DocumentPlan 14 floor.pdf · uploaded 22 Nov 2022Source
  • DocumentPlan Gr 1 and 2.pdf · uploaded 22 Nov 2022Source
  • DocumentTypical Plan.pdf · uploaded 22 Nov 2022Source
  • DocumentLayout.pdf · uploaded 27 Dec 2024Source
  • DocumentSheet 2.pdf · uploaded 27 Dec 2024Source
  • DocumentSheet 3.pdf · uploaded 27 Dec 2024Source
  • DocumentSheet 4.pdf · uploaded 27 Dec 2024Source
  • DocumentLayout.pdf · uploaded 5 May 2025Source
  • DocumentLayout.pdf · uploaded 9 Jun 2026Source
  • DocumentSheet 2.pdf · uploaded 9 Jun 2026Source
  • DocumentSheet 3.pdf · uploaded 9 Jun 2026Source
  • DocumentSheet 4.pdf · uploaded 9 Jun 2026Source

Technical (Architect)

  • DocumentForm 1.pdf · uploaded 14 Oct 2024Source
  • DocumentForm 1.pdf · uploaded 14 Oct 2024Source
  • DocumentForm 1.pdf · uploaded 27 Dec 2024Source
  • DocumentForm1.pdf · uploaded 26 Apr 2025Source
  • DocumentForm 5.pdf · uploaded 26 Apr 2025Source
  • DocumentForm1.pdf · uploaded 5 May 2025Source
  • DocumentForm1 .pdf · uploaded 3 Jun 2025Source
  • DocumentKeyator Form 1 Q1 .pdf · uploaded 31 Jul 2026Source

Technical (Engineer)

  • DocumentForm 2.pdf · uploaded 14 Oct 2024Source
  • DocumentForm 2.pdf · uploaded 14 Oct 2024Source
  • DocumentForm 2.pdf · uploaded 27 Dec 2024Source
  • DocumentForm 2.pdf · uploaded 26 Apr 2025Source
  • DocumentForm 2.pdf · uploaded 26 Apr 2025Source
  • DocumentForm 2.pdf · uploaded 5 May 2025Source
  • DocumentForm 2.pdf · uploaded 3 Jun 2025Source
  • DocumentKeyator Form 2 Q1 .pdf · uploaded 31 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvals1599A, 1599B

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 1RK, 2BHK, 3BHK, Shop107 units in all
Address
1599A, 1599B, 1601A, 1601B, 1602, 1603, 1604, 1605, Parnaka, ParnakaPIN 401201
Village
Malonde, Vasai taluka
Designated bank account
19
Developed in phases
No

Survey, CTS, gat or plot numbers

1599A1599B1601A1601B1602160316041605

Boundaries

North
Rachana Shopping center
South
VVCMC office
East
Dahiwale store
West
Market

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking107 units

40 of 107 units booked (37%), as the promoter reported to MahaRERA

1BHK · 13 units1RK · 1 unit2BHK · 38 units3BHK · 9 unitsShop · 46 units
TypeCarpet areaUnitsBooked
1BHK34.32 sq m · 369 sq ft11
1BHK38.27 sq m · 412 sq ft11
1BHK38.78 sq m · 417 sq ft21
1BHK39.22 sq m · 422 sq ft11
1BHK42.02 sq m · 452 sq ft11
1BHK45.64 sq m · 491 sq ft73
1RK24.98 sq m · 269 sq ft10
2BHK57.75 sq m · 622 sq ft61
Show all 59 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
2BHK57.91 sq m · 623 sq ft10
2BHK58.31 sq m · 628 sq ft20
2BHK59.62 sq m · 642 sq ft10
2BHK60.82 sq m · 655 sq ft90
2BHK63.39 sq m · 682 sq ft82
2BHK64.22 sq m · 691 sq ft61
2BHK64.71 sq m · 697 sq ft50
3BHK79.22 sq m · 853 sq ft83
3BHK90.95 sq m · 979 sq ft11
Shop6.9 sq m · 74 sq ft10
Shop9.83 sq m · 106 sq ft21
Shop11.25 sq m · 121 sq ft11
Shop11.83 sq m · 127 sq ft10
Shop12.4 sq m · 133 sq ft22
Shop12.77 sq m · 137 sq ft22
Shop12.84 sq m · 138 sq ft11
Shop13.15 sq m · 142 sq ft11
Shop13.24 sq m · 143 sq ft11
Shop13.31 sq m · 143 sq ft10
Shop13.33 sq m · 143 sq ft11
Shop13.4 sq m · 144 sq ft11
Shop14.4 sq m · 155 sq ft10
Shop14.45 sq m · 156 sq ft10
Shop14.54 sq m · 157 sq ft11
Shop14.7 sq m · 158 sq ft11
Shop14.77 sq m · 159 sq ft10
Shop14.8 sq m · 159 sq ft10
Shop15.32 sq m · 165 sq ft21
Shop15.36 sq m · 165 sq ft10
Shop15.57 sq m · 168 sq ft10
Shop16.32 sq m · 176 sq ft11
Shop16.68 sq m · 180 sq ft10
Shop17.02 sq m · 183 sq ft10
Shop17.07 sq m · 184 sq ft10
Shop17.51 sq m · 188 sq ft11
Shop17.58 sq m · 189 sq ft11
Shop17.95 sq m · 193 sq ft11
Shop19.64 sq m · 211 sq ft11
Shop20.35 sq m · 219 sq ft11
Shop20.63 sq m · 222 sq ft10
Shop21.24 sq m · 229 sq ft11
Shop23.65 sq m · 255 sq ft10
Shop24.33 sq m · 262 sq ft10
Shop24.55 sq m · 264 sq ft10
Shop26.49 sq m · 285 sq ft10
Shop29.65 sq m · 319 sq ft10
Shop35.25 sq m · 379 sq ft11
Shop36.16 sq m · 389 sq ft10
Shop44.05 sq m · 474 sq ft11
Shop44.47 sq m · 479 sq ft11
Shop122.38 sq m · 1,317 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectEn Con—
Chartered accountantJ N Kamerkar & Co—
EngineerMussadique Hussain Anwarh Shaikh—
EngineerPragnesh Oza Oza—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology