Diamond Heritage-2

Deedo IDDP-PAL-26WE

Completion was pushed back 4 months, to Apr 2031; no MahaRERA orders on record; 0% of its units are booked.

Pelhar, Palghar 401208 · by Diamond Palm Infrastructure Private Limited

DeliveryExtended 4 moPromised Dec 2030 · now due Apr 2031RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 234 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2031

  • This projectRegistered 23 Jun 2025, completion promised 31 Dec 2030, revised to 30 Apr 2031.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP99000080666
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P9900008066623 Jun 202531 Dec 203030 Apr 2031Diamond Palm Infrastructure Private LimitedProject page
Documents119

30 documents held by Deedo, 89 filings listed on MahaRERA's project page

Registration certificate

Commencement certificate (3)

  • Commencement certificateDate not statedView
  • Commencement certificateDate not statedView
  • Commencement certificateDate not statedView

Other (16)

  • OtherDate not statedView
  • OtherDate not statedView
  • OtherDate not statedView
  • OtherDate not statedView
Show all 119 documentsShow fewer documents

Other (16)

  • OtherDate not statedView
  • OtherDate not statedView
  • OtherDate not statedView
  • OtherDate not statedView
  • OtherDate not statedView
  • OtherDate not statedView
  • OtherDate not statedView
  • OtherDate not statedView
  • OtherDate not statedView
  • OtherDate not statedView
  • OtherDate not statedView
  • OtherDate not statedView

Form 1 (2)

  • Form 1Date not statedView
  • Form 1Date not statedView

Allotment letter

  • Allotment letterDate not statedView

Form B (3)

  • Form BDate not statedView
  • Form BDate not statedView
  • Form BDate not statedView

Layout plan (2)

  • Layout planDate not statedView
  • Layout planDate not statedView

Building plan

  • Building planDate not statedView

Title report

  • Title reportDate not statedView

Finance

  • PAN CardPAN COMPANY.pdf · uploaded 17 Mar 2025View

Legal

  • Legal Title reporttitle_compressed.pdf · uploaded 18 Mar 2025View
  • Declaration Form BFORM B-DIAMOND OWNER.pdf · uploaded 18 Mar 2025View
  • Other – LegalDEED WITH BIFURCATION OF BUILDING.pdf · uploaded 3 Apr 2025View
  • Other – Legaldeclaration.pdf · uploaded 3 Apr 2025View

Migrated

  • 1 PAN CardPAN COMPANY.pdf · uploaded 17 Mar 2025View
  • 2 a Details of encumbrances concerned to FinanceLOE-LEGAL.pdf · uploaded 17 Mar 2025Source
  • 1 a Details of encumbrances concerned to FinanceLOE-FINANCE.pdf · uploaded 17 Mar 2025Source
  • 1 Proforma of Allotment letterALLOTMENT LETTER.pdf · uploaded 17 Mar 2025View
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 17 Mar 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 17 Mar 2025Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC_compressed.pdf · uploaded 17 Mar 2025Source
  • 1 Building Plan Approval / NA Order for plotted developmentBLUE PRINT_compressed (1)_compressed.pdf · uploaded 17 Mar 2025View
  • 1 Declaration about Commencement CertificateFORMAT-D.pdf · uploaded 17 Mar 2025Source
  • 1 CERSAI detailsCERSAI.pdf · uploaded 17 Mar 2025Source
  • 1 Deviation Report with respect to Allotment letterDEVIATION-ALLOTMENT.pdf · uploaded 17 Mar 2025View
  • 1 b Details of encumbrances concerned to LegalLOE-FINANCE.pdf · uploaded 17 Mar 2025Source
  • 2 b Details of encumbrances concerned to LegalLOE-LEGAL.pdf · uploaded 17 Mar 2025Source
  • 1 Deviation Report with respect to model copy of AgreementDEVIATION-AGREEMENT.pdf · uploaded 17 Mar 2025View
  • 1 Proforma of Agreement for saleAFS.pdf · uploaded 17 Mar 2025View
  • 1 Disclosure of Interest in Other Real Estate Organizationsilovepdf_merged (1).pdf · uploaded 17 Mar 2025View
  • 1 Copy of the legal title reporttitle_compressed.pdf · uploaded 18 Mar 2025View
  • 1 Declaration in FORM BFORM B-DIAMOND OWNER.pdf · uploaded 18 Mar 2025View
  • 1 Disclosure for secured/unsecured finance availed for the projectDISCLOSURE OF FINANCE.pdf · uploaded 18 Mar 2025View
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 REVISED.pdf · uploaded 3 Apr 2025Source
  • 2 Commencement Certificates / NA Order for plotted developmentPLINTH CLARIFICATION.pdf · uploaded 3 Apr 2025View
  • 1 Other – LegalDEED WITH BIFURCATION OF BUILDING.pdf · uploaded 3 Apr 2025View
  • 2 Other – Legaldeclaration.pdf · uploaded 3 Apr 2025View
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)FORMAT A REVISED.pdf · uploaded 3 Apr 2025Source
  • 4 Other – TechnicalPLOT AREA DEC.pdf · uploaded 3 Apr 2025View
  • 3 Other – TechnicalANNEXURE A-PLOT AREA.pdf · uploaded 3 Apr 2025View
  • 2 Other – Technicaldeclaration.pdf · uploaded 3 Apr 2025View
  • 1 Other – TechnicalDEED WITH BIFURCATION OF BUILDING.pdf · uploaded 3 Apr 2025View
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)FORMAT B REVISED.pdf · uploaded 3 Apr 2025View
  • 5 Other – TechnicalCC VERIFICATION MAIL.pdf · uploaded 4 Apr 2025View
  • 2 Declaration about all RERA Designated Bank Accounts (Format A)landowner bank dec.pdf · uploaded 21 Apr 2025Source
  • 1 Copy of Layout Approval (in case of layout)1 Copy of Layout Approval (in case of layout).pdf · uploaded 23 May 2025View
  • 3 Commencement Certificates / NA Order for plotted developmentappendix f of bldg 18.pdf · uploaded 23 May 2025View
  • 6 Other – Technicaldd additional fee.pdf · uploaded 23 May 2025View
  • 8 Other – Technicalappendix f of bldg 18.pdf · uploaded 23 May 2025View
  • 7 Other – Technicalplot area calculation.pdf · uploaded 23 May 2025View
  • 2 Copy of Layout Approval (in case of layout)LAYOUT PLAN_compressed (1).pdf · uploaded 4 Jun 2025View
  • 4 Commencement Certificates / NA Order for plotted developmentVVCMC LETTER LATEST.pdf · uploaded 17 Jun 2025View
  • 9 Other – TechnicalVVCMC LETTER LATEST.pdf · uploaded 17 Jun 2025View
  • 2 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)landowner declaration latest.pdf · uploaded 17 Jun 2025View
  • Withdrawal Update Form 1FORM 1 JUN 25.pdf · uploaded 25 Aug 2025Source
  • Withdrawal Update Form 1FORM 1 JUN 25.pdf · uploaded 25 Aug 2025Source
  • Withdrawal Update Form 2FORM 2 JUN 25.pdf · uploaded 25 Aug 2025Source
  • Withdrawal Update Form 2FORM 2 JUN 25.pdf · uploaded 25 Aug 2025Source
  • Withdrawal Update Form 3FORM 3 JUN 25.pdf · uploaded 25 Aug 2025Source
  • Withdrawal Update Form 3FORM 3 JUN 25.pdf · uploaded 25 Aug 2025Source
  • Withdrawal Update Form 1FORM 1 SEP 25.pdf · uploaded 12 Mar 2026Source
  • Withdrawal Update Form 1FORM 1 SEP 25.pdf · uploaded 12 Mar 2026Source
  • Withdrawal Update Form 2FORM 2 SEP 25.pdf · uploaded 12 Mar 2026Source
  • Withdrawal Update Form 2FORM 2 SEP 25.pdf · uploaded 12 Mar 2026Source
  • Withdrawal Update Form 3FORM 3 SEP 25.pdf · uploaded 12 Mar 2026Source
  • Withdrawal Update Form 3FORM 3 SEP 25.pdf · uploaded 12 Mar 2026Source
  • Withdrawal Update Form 1FORM 1 MAR 2026.pdf · uploaded 11 Aug 2026Source
  • Withdrawal Update Form 1FORM 1 MAR 2026.pdf · uploaded 11 Aug 2026Source
  • Withdrawal Update Form 1FORM 1 JUNE 2026.pdf · uploaded 11 Aug 2026Source
  • Withdrawal Update Form 2FORM 2 MAR 2026.pdf · uploaded 11 Aug 2026Source
  • Withdrawal Update Form 2FORM 2 MAR 2026.pdf · uploaded 11 Aug 2026Source
  • Withdrawal Update Form 2FORM 2 JUNE 2026.pdf · uploaded 11 Aug 2026Source
  • Withdrawal Update Form 3FORM 3 DEC 2025.pdf · uploaded 11 Aug 2026Source
  • Withdrawal Update Form 3FORM 3 MAR 2026.pdf · uploaded 11 Aug 2026Source
  • Withdrawal Update Form 3FORM 3 JUNE 2026.pdf · uploaded 11 Aug 2026Source
  • Withdrawal Update Form 1FORM 1 MAR 2026.pdf · uploaded 27 Aug 2026Source
  • Withdrawal Update Form 1FORM 1 MAR 2026.pdf · uploaded 27 Aug 2026Source
  • Withdrawal Update Form 1FORM 1 JUNE 2026.pdf · uploaded 27 Aug 2026Source
  • Withdrawal Update Form 2FORM 2 MAR 2026.pdf · uploaded 27 Aug 2026Source
  • Withdrawal Update Form 2FORM 2 MAR 2026.pdf · uploaded 27 Aug 2026Source
  • Withdrawal Update Form 2FORM 2 JUNE 2026.pdf · uploaded 27 Aug 2026Source
  • Withdrawal Update Form 3FORM 3 MAR 2026 UPDATED.pdf · uploaded 27 Aug 2026Source
  • Withdrawal Update Form 3FORM 3 MAR 2026 UPDATED.pdf · uploaded 27 Aug 2026Source
  • Withdrawal Update Form 3FORM 3 JUNE 2026 UPDATED.pdf · uploaded 27 Aug 2026Source

Technical

  • DocumentBLUE PRINT_compressed (1)_compressed.pdf · uploaded 17 Mar 2025View
  • Other – TechnicalDEED WITH BIFURCATION OF BUILDING.pdf · uploaded 3 Apr 2025View
  • Other – Technicaldeclaration.pdf · uploaded 3 Apr 2025View
  • Other – TechnicalANNEXURE A-PLOT AREA.pdf · uploaded 3 Apr 2025View
  • Other – TechnicalPLOT AREA DEC.pdf · uploaded 3 Apr 2025View
  • Other – TechnicalCC VERIFICATION MAIL.pdf · uploaded 4 Apr 2025View
  • Document1 Copy of Layout Approval (in case of layout).pdf · uploaded 23 May 2025View
  • Other – Technicaldd additional fee.pdf · uploaded 23 May 2025View
  • Other – Technicalplot area calculation.pdf · uploaded 23 May 2025View
  • Other – Technicalappendix f of bldg 18.pdf · uploaded 23 May 2025View
  • DocumentLAYOUT PLAN_compressed (1).pdf · uploaded 4 Jun 2025View
  • Other – TechnicalVVCMC LETTER LATEST.pdf · uploaded 17 Jun 2025View

Technical (Architect)

  • DocumentFORM 1 JUNE 2026.pdf · uploaded 27 Aug 2026Source

Technical (Engineer)

  • DocumentFORM 2 JUNE 2026.pdf · uploaded 27 Aug 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel SURVEY NO 232B PLOT NO 3

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK234 units in all
Address
Survey No 232b Plot No 3, Pelhar, PelharPIN 401208
Village
Pelhar
Land area for this project
2,247 sq m (24,189 sq ft)
Permissible built-up area
12,675 sq m (1,36,436 sq ft)
Sanctioned built-up area
12,675 sq m (1,36,436 sq ft)
Recreational open space
225 sq m (2,419 sq ft)
Designated bank account
85
Developed in phases
No

Survey, CTS, gat or plot numbers

SURVEY NO 232B PLOT NO 3

Land as published on MahaRERA's project page

SURVEY NO 232B PLOT NO 3

Boundaries

North
Building
South
Road
East
Building
West
Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking234 units

0 of 234 units booked (0%), as the promoter reported to MahaRERA

1BHK · 180 units2BHK · 54 units
TypeCarpet areaUnitsBooked
1BHK27.87 sq m · 300 sq ft280
1BHK31.38 sq m · 338 sq ft280
1BHK35.91 sq m · 387 sq ft140
1BHK37.44 sq m · 403 sq ft140
1BHK37.74 sq m · 406 sq ft820
1BHK38.27 sq m · 412 sq ft140
2BHK49.46 sq m · 532 sq ft140
2BHK53.61 sq m · 577 sq ft140
2BHK53.71 sq m · 578 sq ft260

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectVipl Adhia—
Chartered accountantAshwin Nair—
EngineerArif Rupalwala—
EngineerAsrar Ahmed Jatoo—

Source: MahaRERA project page. Contact details are not shown.