RERA projects in Amravati (M Corp.)
301 projects under 307 MahaRERA registrations, registered 2017–2026. 11% have a completion date extended beyond the one promised.
Locality
301RERA projects
307Registrationssome projects hold several
60Completion still due247 past their completion date, 152 marked completed
18 monthsMedian extension beyond promised date11% of registrations extended
15Regulatory caseson 13 projects
816Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 81 |
| 2018 | 41 |
| 2019 | 28 |
| 2020 | 21 |
| 2021 | 33 |
| 2022 | 27 |
| 2023 | 37 |
| 2024 | 19 |
| 2025 | 19 |
| 2026 | 1 |
Projects in Amravati (M Corp.)
301 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Dream ImperiaVilas Ramrao Gawai | PM1030002601904 | 11 Sep 2026 | 31 Dec 2028 | — | Not yet due | 0 |
| Samra OneSamra Luxury Private Limited | PM1030002501952 | 30 Dec 2025 | 31 Dec 2031 | — | Not yet due | 0 |
| Nitya:shri ApartmentJog Mahajan Infra Private Limited | PR1030002501671 | 3 Dec 2025 | 31 Dec 2030 | — | Not yet due | 0 |
| Shree Shiv Gajanan ResidencyD.S Ganorkar and Company | PR1030002500992 | 29 Sep 2025 | 31 Dec 2028 | — | Not yet due | 0 |
| Crystal PlazaLaxmikant Prabhakar Joshi | PM1030002500937 | 24 Sep 2025 | 31 Dec 2028 | — | Not yet due | 0 |
| Shree Gajanan ResidencySaurabh Construction and Developers | PM1030002500849 | 19 Sep 2025 | 31 Dec 2028 | — | Not yet due | 0 |
| Solaris CubeSolaris Infra | PC1030002500758 | 11 Sep 2025 | 30 Jun 2029 | — | Not yet due | 0 |
| NavodayaJajoo Ventures | PM1030002500560 | 13 Aug 2025 | 30 Jun 2027 | — | Not yet due | 0 |
| Vidhi HeightsVidhi Developers | PR1030002500459 | 1 Aug 2025 | 31 Dec 2028 | — | Not yet due | 0 |
| Sanjoni HeightsAditya Engineers And Contractors | PM1030002500177 | 1 Jul 2025 | 31 May 2028 | — | Not yet due | 0 |
| Advik NestTathey Realty | P50300080486 | 10 Jun 2025 | 1 Apr 2028 | — | Not yet due | 0 |
| Shri RhideshAnant Keshaorao Saurkar | P50300080405 | 2 Jun 2025 | 31 Mar 2029 | — | Not yet due | 0 |
| Krushnayan VillasSanchit Pradip Patil | P50300080311 | 20 May 2025 | 31 Mar 2029 | — | Not yet due | 0 |
| Vyom Phase 1Talda Infinity LLP | P50300080300 | 19 May 2025 | 30 Jun 2030 | — | Not yet due | 0 |
| Sky VueM/S Ark Infraspace | P50300079482 | 7 Mar 2025 | 30 Sep 2029 | — | Not yet due | 0 |
| Varma HeightsDilip Nandkishor Varma | P50300079310 | 28 Feb 2025 | 31 Dec 2029 | — | Not yet due | 0 |
| Aarambh PrideAarambh Infracon LLp | P50300079060 | 3 Feb 2025 | 31 Dec 2027 | — | Not yet due | 0 |
| Aakar RegencyRohit Ashokrao Jiwarkar | P50300078928 | 21 Jan 2025 | 31 Jul 2028 | — | Not yet due | 0 |
| Sankalp PearlSankalp Properties | P50300078913 | 20 Jan 2025 | 31 Mar 2027 | — | Not yet due | 0 |
| Jayu HeightsNitin Mohod | P50300078794 | 13 Jan 2025 | 30 Sep 2026 | — | Promised date passed | 0 |
| Guru Gajanan ResidencyVtld And Builders Group | P50300078319 | 4 Dec 2024 | 31 Mar 2027 | — | Not yet due | 0 |
| Shree Govindjyot ResidencyMangesh Shyamrao Gulhane | P50300077800 | 7 Nov 2024 | 23 Jul 2026 | — | Promised date passed | 0 |
| Harmony PrathameshRadha Shrihari Builders And Developers LLP | P50300077339 | 9 Aug 2024 | 31 Dec 2028 | — | Not yet due | 0 |
| Madhavam HeightsSky Line Infra Vision | P50300077318 | 6 Aug 2024 | 31 Mar 2028 | — | Not yet due | 0 |
| Gajanan TowerKamal Digrilal Malviya | P50300076894 | 3 Jul 2024 | 15 Mar 2028 | — | Not yet due | 0 |
Other localities in Amravati
Most active promoters
By projects registered here, as named on MahaRERA.
- Vijay Nanakram Talda5 projects
- Garden City4 projects
- P S Associates4 projects
- Amber Builders And Developers3 projects
- Kamal Digrilal Malviya3 projects
- Laxmikant Prabhakar Joshi3 projects
- M/S C & D Engineer's & Developers3 projects
- Ravindra Pundlikrao Mahalle3 projects
- Sagar Pandharinath Bankar3 projects
- Sankalp Builders & Developers3 projects
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology