Walgaon, Amravati
Deedo IDDL-AMR-WALGAON3 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects3
Registrations3
Completion still due03 past their date
Median extensionNot on record0% of registrations extended
Regulatory cases0none on MahaRERA's lists
3 in 10 registrations run late here
3 MahaRERA registrations in Walgaon
2 completed1 past even the latest date
Projects in Walgaon
3 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Radha CityRavi sahu, Rupesh sahu And Deepak sahu | Completed | — | — |
| Radha CityKrishnagiri Developers | Completed | — | — |
| Radha CityRahul sharma And Yogesh Gawande | Completed | — | — |
Nearby: other villages in Amravati
Most active promoters
- Krishnagiri Developers1 project
- Rahul Sharma And Yogesh Gawande1 project
- Ravi Sahu, Rupesh Sahu And Deepak Sahu1 project
Walgaon, in questions
How many projects in Walgaon run late?
3 in 10 MahaRERA registrations (1 of 3): their completion date was extended or has passed, data through 7 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Walgaon by Deedo. Medians on fewer than 3 deeds are not shown.
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology