4 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects447in 29 localities
Registrations458some projects hold several
Completion still due97285 past their date
Median extension4 months23% of registrations extended
Regulatory cases38on 36 projects

4 in 10 registrations run late here

458 MahaRERA registrations in Amravati and the places within it

170 completed41 not yet due45 extended, not yet due126 past even the latest date76 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Amravati

447 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Rama EnclaveMajestic InfravisionDue Sep 2031——
Mauli HeightsGurumauli Infra Private LimitedDue Sep 2029——
One NorthD-RealtyDue Mar 2031——
Vitthal HeightsShri Govinda LifespacesDue Dec 2029——
Jannat ComplexMohammad Aamir AhmadDue May 2030——
All 447 projects →
Amravati market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Localities in Amravati

All 29 localities

Most active promoters

  1. Vijay Nanakram Talda6 projects
  2. Garden City4 projects
  3. Sagar Prakashrao Bute4 projects
  4. Amber Builders And Developers3 projects
  5. C & D Engineer's & Developers3 projects
  6. Dreamz Infrastructure3 projects
  7. Kamal Digrilal Malviya3 projects
  8. Nitin Bhatkar3 projects
  9. P. S. Associates3 projects
  10. Ravindra Pundlikrao Mahalle3 projects

Amravati, in questions

How many projects in Amravati run late?

4 in 10 MahaRERA registrations (171 of 458): their completion date was extended or has passed, data through 22 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Amravati by Deedo. Medians on fewer than 3 deeds are not shown.

Data through22 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology