RERA projects in Paratwada
2 projects under 3 MahaRERA registrations, registered 2018–2018. None has an extended completion date on record.
2RERA projects
3Registrationssome projects hold several
0Completion still due3 past their completion date, 3 marked completed
—Median extension beyond promised date0% of registrations extended
0Regulatory casesnone on MahaRERA's lists
3Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2018 | 3 |
Projects in Paratwada
2 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Vijay PlazaSiddhivinayak Developers | P50300017857, P50300017927 | 24 Sep 2018 | 30 Oct 2022 | — | Completed | 0 |
| Vijay Plaza - CAmit Arvind Deshmukh | P50300017783 | 17 Sep 2018 | 30 Oct 2022 | — | Completed | 0 |
Most active promoters
By projects registered here, as named on MahaRERA.
- Amit Arvind Deshmukh1 project
- Siddhivinayak Developers1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology