RERA projects in Borgaon
3 projects under 5 MahaRERA registrations, registered 2017–2024. 20% have a completion date extended beyond the one promised.
Locality
3RERA projects
5Registrationssome projects hold several
1Completion still due4 past their completion date, 2 marked completed
4 monthsMedian extension beyond promised date20% of registrations extended
0Regulatory casesnone on MahaRERA's lists
22Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 4 |
| 2018 | 0 |
| 2019 | 0 |
| 2020 | 0 |
| 2021 | 0 |
| 2022 | 0 |
| 2023 | 0 |
| 2024 | 1 |
Projects in Borgaon
3 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Cityland EmpireCityland Empire | P50300076994 | 16 Jul 2024 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
| Dreamzland Business ParkM/S Dreamz Infrastructure | P50300004385, P50300004849, P50300004985 | 9 Aug 2017 | 31 Mar 2020 | — | Completed | 0 |
| Dreamaland Business Park Phase No IVM/S Dreamz Infrastructure | P50300004109 | 8 Aug 2017 | 31 Mar 2021 | — | Promised date passed | 0 |
Other localities in Amravati
Most active promoters
By projects registered here, as named on MahaRERA.
- M/S Dreamz Infrastructure2 projects
- Cityland Empire1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology