RERA projects in Revsa

2 projects under 2 MahaRERA registrations, registered 2020–2023. None has an extended completion date on record.

Locality
2RERA projects
2Registrations
0Completion still due2 past their completion date
—Median extension beyond promised date0% of registrations extended
0Regulatory casesnone on MahaRERA's lists
2Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20201
20210
20220
20231

Projects in Revsa

2 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Shri Guru PlazaShree Gajanan InfraP5030004908330 Jan 202331 Dec 2025—Promised date passed0
Shree Guru Anand Dham Phase 2Yogiraj BuildersP5030002427230 Jan 202030 Dec 2023—Promised date passed0

Other localities in Amravati

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Shree Gajanan Infra1 project
  2. Yogiraj Builders1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology