RERA projects in Mhasala

4 projects under 4 MahaRERA registrations, registered 2017–2026. None has an extended completion date on record.

4RERA projects
4Registrations
1Completion still due3 past their completion date, 3 marked completed
—Median extension beyond promised date0% of registrations extended
0Regulatory casesnone on MahaRERA's lists
4Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20171
20180
20190
20201
20211
20220
20230
20240
20250
20261

Projects in Mhasala

4 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Omkar GalaxyDinesh Ramraoji DolarePR10300025025462 Mar 202630 Nov 2029—Not yet due0
Smahi HeightAditya Engineers And DevelopersP5030002976029 Jun 202130 Jun 2024—Completed0
Govind VillaAnshuman BuildersP5030002681628 Oct 202030 Jun 2024—Completed0
Green SquareUjjwala Satish HawareP5030001438429 Nov 201731 Jul 2019—Completed0

Other localities in Amravati

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Aditya Engineers And Developers1 project
  2. Anshuman Builders1 project
  3. Dinesh Ramraoji Dolare1 project
  4. Ujjwala Satish Haware1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology