Riddhi Siddhi Apartment

Lapsed

Amravati (M Corp.), Amravati 444602 |Promoter: Dinesh Ramrao Dolare

Residential / Group HousingRERAP50300031472
23 Oct 2021Registered with MahaRERA
20 Sep 2023Promised completion
1Building
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Lapsed
Buildings
1
Land area for this project
379 sq m (4,080 sq ft)
Permissible built-up area
638 sq m (6,867 sq ft)
Sanctioned built-up area
638 sq m (6,867 sq ft)
Address
39, 40, Tapovan Road, Ramanand ResidencyPIN 444602
Designated bank account
The Shamrao Vithal Cooperative Bank
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 0.00000, 0.00000
Riddhi Siddhi Apartment is at latitude 0.00000, longitude 0.00000.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 20 Sep 2023

The latest completion date on record passed 3 years and 1 month ago.

Registered
23 Oct 2021
Promised
20 Sep 2023

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5030003147223 Oct 202120 Sep 2023—Dinesh Ramrao DolareProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Riddhi Siddhi Apartment5—

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 units registered

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00001
Open Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Riddhi Siddhi Apartment

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure60%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water Supplyborehole100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)Tanks & Line will be installed40%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingNot applicable
  • Street LightingParking Area Lights0%
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingWill be Installed0%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationBellow Stairs0%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

11 documents held by Deedo, 15 filings listed on MahaRERA's project page

Encumbrance

Commencement certificates

Form b

Form 2

Title

Allotment letters

Registration certificate

Other

Layout plan

Document library

  • Copy of Layout Approval (in case of layout)Copy of Layout Approval (in case of layout).pdf · uploaded 25 Sep 2021View
  • Building Plan Approval / NA Order for plotted developmentBuilding Plan Approval (IOD).pdf · uploaded 25 Sep 2021View
  • Declaration in FORM BDeclaration in FORM B.pdf · uploaded 25 Sep 2021View
  • Details of encumbrancesDetails of encumbrances.pdf · uploaded 25 Sep 2021View
  • Declaration about Commencement Certificatedeclaration.pdf · uploaded 25 Sep 2021View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)form2.pdf · uploaded 25 Sep 2021View
  • Proforma of Allotment letterProforma of the allotment letter and agreement for sale.pdf · uploaded 25 Sep 2021View
  • Proforma of Allotment letterLetter of Allotment.pdf · uploaded 13 Oct 2021View
  • Copy of the legal title reportLegal Title Report.pdf · uploaded 13 Oct 2021View
  • Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 13 Oct 2021View

Promoter documents

  • Declaration Form BDeclaration in FORM B.pdf · uploaded 25 Sep 2021View
  • Legal Title reportLegal Title Report.pdf · uploaded 13 Oct 2021View

Technical documents

  • Layout ApprovalCopy of Layout Approval (in case of layout).pdfView
  • Building Plan ApprovalBuilding Plan Approval (IOD).pdfView

Proforma allotment letter

  • Proforma allotment letterProforma of the allotment letter and agreement for sale.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

Survey, CTS, gat or plot numbers

3940

As published on MahaRERA's project page

39,40

Boundaries

North
9 Mtr Layout Road
South
Service Lane
East
Other Layout
West
Plot No 38

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectDinesh Dolare—
Chartered accountantVishal Pinjarkar—
EngineerDinesh Dolare—
OtherNilesh Gajle—

Source: MahaRERA project page. Contact details are not shown.

Data through9 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology