RERA projects in Bhukum
19 projects under 27 MahaRERA registrations, registered 2017–2026. 56% have a completion date extended beyond the one promised.
Locality
19RERA projects
27Registrationssome projects hold several
12Completion still due15 past their completion date
4 monthsMedian extension beyond promised date56% of registrations extended
0Regulatory casesnone on MahaRERA's lists
43Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 8 |
| 2018 | 2 |
| 2019 | 4 |
| 2020 | 3 |
| 2021 | 2 |
| 2022 | 0 |
| 2023 | 1 |
| 2024 | 0 |
| 2025 | 5 |
| 2026 | 2 |
Projects in Bhukum
19 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Lotus CrestBalaji Kimaya Homes | PR1260002602114 | 1 Oct 2026 | 31 Dec 2028 | 31 Dec 2028 | Not yet due | 0 |
| Skyi First CommercialEnerrgia Skyi Realty | PC1260002601271 | 21 Jul 2026 | 31 Mar 2027 | 31 Jul 2027 | Extended 4 mo | 0 |
| Pyramid Parkland NxtPyramid Lifestyle Limited | PR1260002501203 | 13 Oct 2025 | 31 Dec 2030 | 31 Dec 2030 | Not yet due | 0 |
| Skyi ParkEnerrgia Skyi Ventures | P52100079680, P52100080267 | 20 Mar 2025 | 31 Jul 2030 | 30 Nov 2030 | Extended 4 mo | 0 |
| Bhukum 45Landmark Realtors | P52100079451 | 6 Mar 2025 | 30 Jun 2029 | 30 Oct 2029 | Extended 4 mo | 0 |
| Asmi PrideM/S Icon Developers | P52100028299 | 18 Feb 2021 | 31 Dec 2026 | 31 Dec 2026 | Not yet due | 0 |
| Skyi Manas LakeEnerrgia Skyi Ventures LLP | P52100026954, P52100030584, P52100052033 +1 | 7 Nov 2020 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
| Pyramid ParklandPyramid Lifestyle Limited | P52100025994 | 7 Aug 2020 | 30 Jun 2028 | 30 Oct 2028 | Extended 4 mo | 0 |
| Shri Datta PuramSamruddhi Properties | P52100025332 | 30 Apr 2020 | 31 Mar 2027 | 31 Jul 2027 | Extended 4 mo | 0 |
| Golden Palms- Phase 2 A WingGeeta Vidhyai Constructions | P52100022609 | 9 Oct 2019 | 30 Sep 2023 | 29 Sep 2024 | Extended 12 mo | 0 |
| Manas Valley Phase IIBalaji Kimaya Associates | P52100021300 | 21 Jun 2019 | 31 Oct 2026 | 28 Feb 2027 | Extended 4 mo | 0 |
| Skyi Star TownEnerrgia Skyi Properties Pvt Ltd | P52100019226, P52100021041 | 14 Jan 2019 | 28 Aug 2023 | 29 Feb 2024 | Extended 6 mo | 0 |
| Shanaya EleganceCk Associates | P52100016627 | 28 May 2018 | 30 Dec 2026 | 30 Apr 2027 | Extended 4 mo | 0 |
| Skyi Star Town CommercialPate Life Melange Developers Pvt Ltd | P52100013211 | 21 Sep 2017 | 28 Feb 2021 | 31 Aug 2023 | Extended 30 mo | 0 |
| Skyi Star TownPate Life Melange Developers Pvt Ltd | P52100012998, P52100014662, P52100016286 | 11 Sep 2017 | 28 Aug 2022 | 28 Aug 2023 | Extended 12 mo | 0 |
| Skysparsh RegencySkysparsh Developers | P52100013012 | 11 Sep 2017 | 31 Jan 2021 | 31 Jul 2022 | Extended 18 mo | 0 |
| Golden Palms- Phase 1 B WingGeeta Vidhyai Constructions | P52100012378 | 1 Sep 2017 | 31 Dec 2018 | 31 Dec 2018 | Promised date passed | 0 |
| Skyi StarEnerrgia Skyi Ventures | P52100000421, P52100000690 | 17 Jul 2017 | 28 Feb 2021 | 28 Feb 2021 | Promised date passed | 0 |
| Pyramid County BhukumPrasad Lifespaces LLP | P52100000387 | 15 Jul 2017 | 30 Mar 2022 | 30 Sep 2023 | Extended 18 mo | 0 |
Other localities in Mulshi
Most active promoters
By projects registered here, as named on MahaRERA.
- Enerrgia Skyi Ventures2 projects
- Geeta Vidhyai Constructions2 projects
- Pate Life Melange Developers Pvt Ltd2 projects
- Pyramid Lifestyle Limited2 projects
- Balaji Kimaya Associates1 project
- Balaji Kimaya Homes1 project
- Ck Associates1 project
- Enerrgia Skyi Properties Pvt Ltd1 project
- Enerrgia Skyi Realty1 project
- Enerrgia Skyi Ventures LLP1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology