Punawale, Pune

Deedo IDDL-PUN-PUNAWALE

9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects190
Registrations220some projects hold several
Completion still due98122 past their date
Median extension4 months54% of registrations extended
Regulatory cases1on 1 project

0 deeds a month, 0% of them rentals

Registered sales and rentals, the 24 months to November 2026

Registered sales and rentals by month
MonthSalesRentals
December 202400
January 202500
February 202500
March 202500
April 202500
May 202500
June 202500
July 202500
August 202500
September 202500
October 202500
November 202500
December 202500
January 202600
February 202600
March 202600
April 202600
May 202600
June 202600
July 202600
August 202600
September 202600
October 202600
November 202610

1 sale and 0 rentals in the last 12 months · Source: IGR Maharashtra Index II, registered sale and leave-and-licence deeds

9 in 10 registrations run late here

220 MahaRERA registrations in Punawale

17 not yet due81 extended, not yet due122 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Punawale

190 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Celestia HeightsPrapti BuildconDue Dec 2030——
Legacy HighpointInfinitynx Realtors LLPDue Dec 2030——
V Top VELESTAV-Top DevelopersDue Dec 2030——
Anika Piccadilly Phase 4Arun Pitamber ShethDue Dec 2029——
Venkateshwara HeightVenkateshwara HeightDue Dec 2029——
All 190 projects →
Punawale market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Benchmarrk Realty Llp5 projects
  2. Arun Pitamber Sheth4 projects
  3. Sai Samarttha Properties4 projects
  4. Samarth Chintamani Properties4 projects
  5. Samarttha Prisha Properties4 projects
  6. Essen Land Marks, Esvee Dream Homes LLP3 projects
  7. Shiv Constructions3 projects
  8. Tulip Developers3 projects
  9. Vinayak Kishor Garve3 projects
  10. Vinod Premchand Chandwani3 projects

Punawale, in questions

How many projects in Punawale run late?

9 in 10 MahaRERA registrations (203 of 220): their completion date was extended or has passed, data through 22 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Punawale by Deedo. Medians on fewer than 3 deeds are not shown.

Latest deal · Primary sale · Nov 2026

₹50–75 L

Data through12 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology