RERA projects in Wakad

298 projects under 316 MahaRERA registrations, registered 2017–2026. 13% have a completion date extended beyond the one promised.

Locality
298RERA projects
316Registrationssome projects hold several
94Completion still due222 past their completion date
18 monthsMedian extension beyond promised date13% of registrations extended
2Regulatory caseson 2 projects
41Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
201796
201832
201933
202024
202127
202223
202331
202415
202515
202620

Projects in Wakad

298 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Wakad New Project- Tower 1Lodha Developers LimitedPR12600026021938 Oct 202631 Dec 2032—Not yet due0
Truspace Prima AltioraTruspace Developments Private LimitedPR12600026020571 Oct 202631 Dec 2031—Not yet due0
Arham PalazzoVedant InfrastructuresPM126000260201323 Sep 202624 Jun 2029—Not yet due0
Austin AurusDivya HeightsPM12600026014385 Aug 202631 Dec 2031—Not yet due0
Jaijinendra NilayJaijinendra ShreekalpPM12600026014174 Aug 202630 Jun 2030—Not yet due0
The Vantage A, B, C & DKuber PropertiesPR12600026010667 Jul 202619 Mar 2031—Not yet due0
Arise CapitalVinode Wakadkar Buildcon LLPPC126000260090623 Jun 202631 Mar 2030—Not yet due0
The Vantage EKuber PropertiesPC126000260082017 Jun 202619 Mar 2031—Not yet due0
MillefioriFuturistic HomesPM12600026003325 May 202630 Jun 2030—Not yet due0
Meridian StudiosAmegh PropertiesPM126000260022921 Apr 202631 Dec 2028—Not yet due0
Sai VilasitaGolden Terrain Infra LLPPR126000260008515 Apr 202630 Jun 2028—Not yet due0
The Raya Phase ISunguard Builders LLPPR126000250274112 Mar 202631 Dec 2029—Not yet due0
Truston AspenVinode Wakadkar BuildconPR126000250243723 Feb 202631 Dec 2029—Not yet due0
Vardhaman SkysymphonyVardhaman PropertiesPR126000250232311 Feb 202631 Dec 2030—Not yet due0
Ganga Asmi Wing 3Shanti Mohan Developers LLPPM12600025022626 Feb 202630 Dec 2030—Not yet due0
Siddhi's Sapphire HomesSiddhis VenturePR126000250222430 Jan 202631 Dec 2027—Not yet due0
HighnessM/s Binary InfrastructuresPR126000250218327 Jan 202631 Dec 2032—Not yet due0
LuxtonNeev Sai DevelopersPM126000250204312 Jan 202630 Jun 2030—Not yet due0
Terminal TwoAvnee Landmarks LLPPC126000250204812 Jan 202631 Dec 2029—Not yet due0
Brahma Tower Phase IIM D ConstructionsPM126000250195731 Dec 202531 Dec 2030—Not yet due0
Prissa PrathamLga Ventures LLPPM126101250193329 Dec 202531 Dec 2030—Not yet due0
Kuber Properties Kuber Antonia BKuber PropertiesPR126000250179716 Dec 202524 Apr 2027—Not yet due0
The EmbercrestChandrarang Developer and Builders Pvt LtdPR126000250176012 Dec 202531 Dec 2031—Not yet due0
Westgate Business ParkBb Square LLPPC126000250160527 Nov 202531 Dec 2029—Not yet due0
P.k.canopusP K GroupPM126000250126416 Oct 202530 Jun 2029—Not yet due0
Runaa SaukhyamRunaa HomesPR126000250059918 Aug 202531 Mar 2029—Not yet due0
Divine Reves, Wing ADivine Homes DevelopersPM126101250039028 Jul 202531 Dec 2028—Not yet due0
Kohinoor Regalia TowersGodiva Buildcon Private LimitedPR126000250027114 Jul 202515 Jun 2030—Not yet due0
Pashankar WavesPashankar BuildconP521000804455 Jun 202531 Dec 2030—Not yet due0
Platinum 9 World TowerPlatinum Associates LLPP521000801785 May 202531 Dec 2031—Not yet due0
Pune Wakad ProjectLodha Developers LimitedP5210007969220 Mar 202529 Jun 2031—Not yet due0
Wakad Central ParkShree Venkateshwara GroupP5210007965518 Mar 202531 Dec 2027—Not yet due0
Sky SanctumMohar Lifespaces LLPP521000794266 Mar 202531 Dec 2028—Not yet due0
A R MiradorAtlas Royal LivingP521000790713 Feb 202530 Oct 2029—Not yet due0
AR AmoraA R LivingP5210007862327 Dec 202431 Dec 2026—Not yet due0
Anshul Casa K BuildingAnshul Siddhi Promoters And Builders LLPP5210007823929 Nov 202430 Apr 2031—Not yet due0
41 CommuneThree Dots RealtyP5210007794513 Nov 202431 Dec 2027—Not yet due0
Prime PinnacleViraj Enterprises Through Proprietor Nilesh Shankar WaghmareP521000778267 Nov 202430 Sep 2027—Not yet due0
Rajveer GarimaWaghere AssociatesP52100077863, PR12610126007027 Nov 202431 Dec 2031—Not yet due0
Top Towers - BRaga DevelopersP5210007716529 Jul 202431 Jul 2027—Not yet due0
Royal AceFive Star Construction CompanyP5210007703616 Jul 202431 Mar 2026—Promised date passed0
Anp BizsquareFive Star Vighnesh Associates (Aop)P521000559956 May 202431 Jul 2026—Promised date passed0
Prime NestPro Prime Build LLPP5210005572716 Apr 202430 Jun 2027—Not yet due0
Kings County Phase - IKing's Marque GroupP521000556355 Apr 202431 Dec 2027—Not yet due0
Shubh Swarovski Wing AShubh DevelopersP521000555052 Apr 202412 Oct 2028—Not yet due0
Weone 153Grd Infraprojects Private LimitedP5210005496321 Feb 202431 Dec 2026—Not yet due0
Anshul Casa J BuildingAnshul Siddhi Promoters & Builders LLPP5210005431115 Jan 202430 Apr 2030—Not yet due0
Zenone B BuildingK & T InfrastructureP5210005335027 Oct 202330 Sep 2027—Not yet due0
Kuber Antonia C WingVikas Vilas BhalgatP5210005314217 Oct 202324 Apr 2027—Not yet due0
Yashwin Urbo CentroVilas Javdekar Infinitee Developers Pvt. Ltd.P52100053194, P5210007767417 Oct 202330 Jun 2029—Not yet due0
Ivana ResidencySiddhidata InfraP5210005306012 Oct 202331 May 2025—Promised date passed0
ParamPrasanna Infracon LLPP521000528165 Oct 202331 Dec 2027—Not yet due0
Siddhi Nisarg C BuildingSiddhi Nisarg AssociatesP521000529105 Oct 202331 Dec 2026—Not yet due0
Treasure TrovesRealcon Homes LLPP5210005258211 Sep 202331 Dec 2030—Not yet due0
InfiniaSai Krishna PropertiesP521000524658 Sep 202331 Dec 2026—Not yet due0
Trinity GraceJethani Landmark LLPP521000525418 Sep 202331 Dec 2025—Promised date passed0
Akshara HarmonyGarve Developers and PromotersP5210005240521 Aug 202331 Dec 2026—Not yet due0
Shiv MalharShiv DevelopersP5210005240121 Aug 202331 Dec 2027—Not yet due0
Laxmi BlissShree Mahalaxmi AssociatesP521000522542 Aug 202331 May 2027—Not yet due1
Sentosa EliteShanti ConstructionsP5210005220831 Jul 202331 Dec 2026—Not yet due0
Future EliteFuture HomesP5210005149123 Jun 202325 Aug 202331 Mar 2025Extended 19 mo0
A G LandmarkA G LandmarksP5210005106322 May 202331 Dec 2026—Not yet due0
Sai PleasureMr Vinod Kishanchand MataniP5210005093015 May 202325 Jun 2027—Not yet due0
7 SquareSai Spacecon India Private LimitedP521000508259 May 202331 Dec 2026—Not yet due0
A R AtlasA R RealtyP5210005058221 Apr 202331 Dec 2025—Promised date passed0
VJ IndiLife WakadVilas Javdekar Lifestyle Developers Pvt. Ltd.P5210005059421 Apr 202330 Jun 2027—Not yet due0
Arbor VistaAtul Kanhaiyalal SuranaP5210005050417 Apr 202331 Dec 2027—Not yet due0
Mihir Amara Phase IIMihir Homes RealtyP5210005045817 Apr 202331 Dec 2026—Not yet due0
Brahma Tower I A and B WingM D ConstructionsP5210005013920 Mar 202331 Mar 2026—Promised date passed0
Varad ResidencyVilas Bhagaji ArekarP5210005011515 Mar 202316 Sep 2026—Promised date passed0
Presidency TowersPresidency Hospitality LimitedP521000500596 Mar 202330 Jun 2026—Promised date passed0
SRK PlatinumS R K BuildconP5210004977824 Feb 202331 Dec 2025—Promised date passed0
172W Inclusive HousingVilas Javdekar Lifestyle Developers Pvt. Ltd.P521000494128 Feb 202330 Jun 2026—Promised date passed0
57 ElevateEssen Venkatesh LLPP521000492937 Feb 202331 Dec 2027—Not yet due0
ElanzaSantosh Mariba BagadiP521000492757 Feb 202331 Dec 2025—Promised date passed0
Navkarshree BuildingNavkar Shree AssociatesP521000492897 Feb 202331 Mar 2026—Promised date passed0
Weone 121Grd Infraprojects Private LimitedP521000493917 Feb 202331 Dec 2026—Not yet due0
Anp UltimusSwadik Trade Private LimitedP5210004783528 Nov 202230 Jun 2027—Not yet due0
Gaikwad NirvanasGaikwad DevelopersP5210004731519 Oct 202231 Mar 2026—Promised date passed0
Millennium EmeraldMillennium PropertiesP5210004733219 Oct 202231 Dec 2026—Not yet due0
Rohan VitiRohan Builders & Developers Private LimitedP521000467191 Sep 202231 Dec 202731 Dec 2027Not yet due0
My Home WakadSamruddhi PropertiesP5210004617520 Jun 202230 Jun 2027—Not yet due0
Anshul Casa I-BuildingSai Siddhi Promoters and BuildersP5210004552524 May 202231 Mar 2027—Not yet due0
Kuber AntoniaVikas Vilas BhalgatP52100035197, P5210005620910 May 202224 Apr 202723 Feb 2026Not yet due0
Stellar RhythmmWakadkar Patil Associates LLPP5210003516110 May 202231 Dec 2024—Promised date passed0
The Camelia Phase - 1Akanksha BuildersP5210004523110 May 202231 Jan 2027—Not yet due0
Top Towers - ARaga DevelopersP5210003492928 Apr 202230 Jun 2026—Promised date passed0
Itrend Life PlusManas Pearl VenturesP5210003472320 Apr 202225 Mar 2025—Promised date passed0
Anp RetreatFive Star Construction CompanyP5210003455711 Apr 202231 Aug 2026—Promised date passed0
Yashwin NuovoCentroVilas Javdekar Lifestyle Developers Pvt. Ltd.P5210003452311 Apr 202230 Jun 2026—Promised date passed0
RGS ForteRGS Realty LLPP521000344435 Apr 202231 Mar 2027—Not yet due0
Legacy AvenueAastha BuildconP521000343414 Apr 202230 Sep 2024—Promised date passed0
Vantagio. Ph2Harmony Shubham AssociatesP5210003431130 Mar 20228 Sep 2025—Promised date passed0
Ashirwad HouseAshirwad EnterprisesP5210003412724 Mar 202230 Jun 2024—Promised date passed0
Ganga Asmi Wing 2Shantimohandevelopers LLPP5210003406824 Mar 202231 Dec 2028—Not yet due0
Abhiaayu HeightsManoj Yeole Ramdas YeoleP521000336822 Mar 202231 Jan 2024—Promised date passed0
Iyana ResidencyM/S Siddhidata BuildconP521000335822 Mar 202231 Dec 2023—Promised date passed0
Mihir Amara Building - A4Mihir SyntheticsP5210003352822 Feb 202231 Dec 2026—Not yet due0
A R ImperiaA R RealtyP521000329422 Feb 202231 Dec 2024—Promised date passed0
M J OperaM/S Shivdan ConstructionsP521000324134 Jan 202228 Feb 2026—Promised date passed0

Other localities in Mulshi

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Vilas Javdekar Eco Shelters Private Limited5 projects
  2. Vilas Javdekar Lifestyle Developers Pvt. Ltd.5 projects
  3. Five Star Construction Company4 projects
  4. Kumar Construction and Properties Pvt Ltd4 projects
  5. Neev Sai Developers4 projects
  6. Paranjape Schemes (Construction) Ltd4 projects
  7. Shiv Developers4 projects
  8. Grd Infraprojects Private Limited3 projects
  9. Kuber Properties3 projects
  10. Samruddhi Properties3 projects
Data through11 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology