6 in 10 MahaRERA registrations here have pushed their completion date back.

RERA projects83
Registrations88some projects hold several
Completion still due4444 past their date
Median extension4 months55% of registrations extended
Regulatory cases0none on MahaRERA's lists
Bavadhan Bk market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

9 in 10 registrations run late here

88 MahaRERA registrations in Bavadhan Bk

10 not yet due34 extended, not yet due44 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Bavadhan Bk

83 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Giridhar ResidencyDinesh Nemichandra Ganeshwade And Mahesh Nemichandra GaneshwadeDue Jun 2029——
Konbil TrinityKonbil Baner Project LLPDue Oct 2030, extended 4 mo——
Aakar Heights B WingRiya Rahul KatkamwarDue Apr 2028, extended 4 mo——
Vtp Cielo MHADADelas Realcon LLPDue Apr 2030, extended 4 mo——
Puraniks Abitante Fiore Phase 2DPuranik Buildcon Private LimitedDue Apr 2034, extended 4 mo——
K-ConnectShrem Trading LLPDue Oct 2027, extended 4 mo——
Shubham KarotiM/S Sanskruti DevelopersDue Aug 2028, extended 4 mo——
SkyoraGreen Ladder Estates LLPDue Oct 2029, extended 4 mo——
Divyash CapitalLacom Consultancy LLPDue Apr 2029, extended 4 mo——
Eh Sky TowerEh Reality LLPDue Nov 2030, extended 4 mo——
Celestine B WingLotus ConstructionDue Apr 2030, extended 4 mo——
Atharva Bliss Phase II- Residential BuildingM/s. Abhay ConstructionsDue Jul 2029, extended 4 mo—0%
Survi HeritageShree Dagade Patil VenturesDue Apr 2028, extended 4 mo—0%
Atharva Bliss Phase II- Amenity BuildingM/s. Abhay ConstructionsDue Jul 2029, extended 4 mo—0%
Iris ViewChakankar PropertiesDue Apr 2030, extended 4 mo—0%
WYCE ExclucitySaniket Infratech LLPDue Apr 2030, extended 4 mo—6%
7 AnshulM/s KARAN SANRAN ASSOCIATESDue Aug 2031, extended 4 mo—0%
27th Avenue NxtBlue Construction CompanyDue Dec 2026—43%
Ganga Legend Building B7Legends County Landmark Pvt LtdDue Apr 2029, extended 4 mo——
Ganga Legend B5 BuildingLegends County Landmark Pvt LtdDue Dec 2027—29%
Dream DelmontDream Works RealtorsDue Jul 2029, extended 4 mo—26%
Kekarav Sector 4Midori Realty LLPDue Apr 2027, extended 4 mo——
S SquareSandip Madhav Bhadale1 yr 7 mo late—21%
Padmavati Hills A WingSuyog City DevelopersDue Jul 2027, extended 4 mo—68%
Puraniks Abitante Fiore Phase 2C1Puranik Buildcon Private LimitedDue Oct 2028, extended 4 mo—60%

Most active promoters

  1. Puranik Buildcon Private Limited7 projects
  2. Shrem Trading LLP4 projects
  3. Goel Ganga India Pvt Ltd3 projects
  4. Legends County Landmark Pvt Ltd3 projects
  5. M/s. Abhay Constructions3 projects
  6. M/s KARAN SANRAN ASSOCIATES3 projects
  7. Suyog City Developers3 projects
  8. Abhinav Rainbow Developers And Promoters LLP2 projects
  9. Blue Construction Company2 projects
  10. Kolte-Patil Developers Limited2 projects
Data through22 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology