RERA projects in Bhugaon
80 projects under 84 MahaRERA registrations, registered 2017–2026. 62% have a completion date extended beyond the one promised.
Locality
80RERA projects
84Registrationssome projects hold several
51Completion still due33 past their completion date, 3 marked completed
4 monthsMedian extension beyond promised date62% of registrations extended
46Regulatory caseson 6 projects
294Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 21 |
| 2018 | 4 |
| 2019 | 5 |
| 2020 | 3 |
| 2021 | 4 |
| 2022 | 6 |
| 2023 | 15 |
| 2024 | 11 |
| 2025 | 6 |
| 2026 | 9 |
Projects in Bhugaon
80 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Regis -Avian ValleyKakade Estate Developers Private Limited | PR1260002602288 | 14 Oct 2026 | 31 Dec 2032 | — | Not yet due | 0 |
| The Winds Phase-1, Sector 1b At Avian ValleyKolte-Patil Developers Limited | PR1261012600258 | 23 Apr 2026 | 30 Jun 2031 | 30 Oct 2031 | Extended 4 mo | 0 |
| Park Pebbles Phase IM/s Rainbow Purple Construction LLP | PR1261012600124 | 17 Apr 2026 | 30 Jun 2030 | 30 Oct 2030 | Extended 4 mo | 0 |
| R28A Everglades - Phase 2Arys Realtors Private Limited | PM1260002502776 | 13 Mar 2026 | 31 Jan 2031 | 31 Jan 2031 | Not yet due | 0 |
| Westernhills Bhugaon Phase 1Vistaverde Builders LLP | PR1261012502788 | 13 Mar 2026 | 31 Oct 2030 | 28 Feb 2031 | Extended 4 mo | 0 |
| The WillowAryavart Realty | PP1260002502612, PP1260002600424 | 5 Mar 2026 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| PWC Tigers Nest Phase IEnerrgia Skyi Developers | PR1261012502471 | 24 Feb 2026 | 31 Dec 2029 | 30 Apr 2030 | Extended 4 mo | 0 |
| Avian Valley - SolaireKakade Estate Developers Pvt. Ltd. | PR1260002502429 | 23 Feb 2026 | 31 Dec 2029 | 30 Apr 2030 | Extended 4 mo | 0 |
| Kohinoor Woodshire Phase 2Intofinity Promoters Private Limited | PR1261012501461 | 13 Nov 2025 | 31 Dec 2030 | 30 Apr 2031 | Extended 4 mo | 0 |
| BelviewTranquil Infratech LLP | P52100081035 | 3 Nov 2025 | 1 Jul 2030 | 1 Nov 2030 | Extended 4 mo | 0 |
| C P ShineT And P Developers | PM1260002501218 | 13 Oct 2025 | 15 Aug 2029 | 15 Dec 2029 | Extended 4 mo | 0 |
| Kaleidoscope R5 Misty greens Phase 3BKaleidoscope Developers Pvt. Ltd. | P52100080947 | 26 Aug 2025 | 31 Jan 2030 | 31 May 2030 | Extended 4 mo | 0 |
| R48 The CanopyParanjape Spaces And Services Pvt Ltd | P52100079518 | 10 Mar 2025 | 31 Dec 2029 | 30 Apr 2030 | Extended 4 mo | 0 |
| Kohinoor WoodshireIntofinity Promoters Private Limited | P52100078709 | 7 Jan 2025 | 31 Dec 2029 | 31 Dec 2029 | Not yet due | 0 |
| Skyi Songbirds Phase FEnerrgia Skyi Developers | P52100077956 | 14 Nov 2024 | 31 Dec 2027 | 30 Jun 2028 | Extended 6 mo | 0 |
| River CrestARP Developers | P52100077902 | 13 Nov 2024 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Forest Trails Athashri B3Lavim Developers Pvt Ltd | P52100077686 | 21 Oct 2024 | 30 Sep 2029 | 30 Jan 2030 | Extended 4 mo | 0 |
| Rohan Saroha Phase 1Rohan Builders & Developers Private Limited | P52100076652 | 20 Jun 2024 | 30 Sep 2028 | 30 Jan 2029 | Extended 4 mo | 0 |
| Padmavati AvenueJawalkar Realties | P52100076587 | 18 Jun 2024 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
| Kaleidoscope R5 Misty Greens Phase 3AKaleidoscope Developers Pvt. Ltd. | P52100066537 | 11 Jun 2024 | 30 Apr 2029 | 30 Aug 2029 | Extended 4 mo | 0 |
| Serenora Wing ANirmitee Unicons Infra LLP | P52100066561 | 11 Jun 2024 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
| PWC Towers Hill Side Phase IIIEnerrgia Skyi Developers | P52100056325 | 29 May 2024 | 31 Aug 2028 | 31 Dec 2028 | Extended 4 mo | 0 |
| Cloud 28Oree Reality Pvt Ltd | P52100055816 | 22 Apr 2024 | 31 Dec 2029 | 30 Apr 2030 | Extended 4 mo | 0 |
| The Orchard ResidencesParanjape Schemes (Construction) Ltd | P52100055710 | 15 Apr 2024 | 31 Mar 2029 | 31 Jul 2029 | Extended 4 mo | 0 |
| Pre EminenceR K Shinde Developers | P52100055471 | 2 Apr 2024 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 1 |
Other localities in Mulshi
Most active promoters
By projects registered here, as named on MahaRERA.
- Enerrgia Skyi Developers11 projects
- Paranjape Schemes (Construction) Ltd5 projects
- Kaleidoscope Developers Pvt. Ltd.4 projects
- Mont Vert Elegance4 projects
- Sankla Buildcoon3 projects
- Axis Paradigm Infra Properties2 projects
- Intofinity Promoters Private Limited2 projects
- Jaisons Properties LLP2 projects
- Paranjape Schemes (Construction) Limited2 projects
- Paranjape Spaces And Services Pvt Ltd2 projects
Data through15 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology