RERA projects in Man
67 projects under 85 MahaRERA registrations, registered 2017–2026. 9% have a completion date extended beyond the one promised.
67RERA projects
85Registrationssome projects hold several
28Completion still due57 past their completion date
15 monthsMedian extension beyond promised date9% of registrations extended
0Regulatory casesnone on MahaRERA's lists
3Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 20 |
| 2018 | 12 |
| 2019 | 4 |
| 2020 | 11 |
| 2021 | 7 |
| 2022 | 6 |
| 2023 | 11 |
| 2024 | 7 |
| 2025 | 6 |
| 2026 | 1 |
Projects in Man
67 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| 18 AanganFour Pillars | PR1260002501338 | 28 Oct 2025 | 30 Nov 2028 | — | Not yet due | 0 |
| You57 Tower DSanas Developers Private Limited | PR1264042501139 | 9 Oct 2025 | 29 Feb 2028 | — | Not yet due | 0 |
| Building B3 Eon HomesHinjawadi Infradevelopment Pvt Ltd | P52100080318 | 21 May 2025 | 30 Jun 2030 | — | Not yet due | 0 |
| Legend Aaradhyam Phase IR J Construction | P52100080306 | 19 May 2025 | 31 Dec 2027 | — | Not yet due | 0 |
| Godrej Evergreen SquareGodrej Projects Development Limited | P52100078240 | 29 Nov 2024 | 31 Oct 2030 | — | Not yet due | 0 |
| Kohinoor Satori MahalungeIntofinity Promoters Private Limited | P52100066472 | 11 Jun 2024 | 31 Dec 2029 | — | Not yet due | 0 |
| Kohinoor Central ParkIntofinity Promoters Private Limited | P52100056358, P52100078767 | 29 May 2024 | 15 Oct 2029 | — | Not yet due | 0 |
| Parth KionaEdenic Enterprises Pvt Ltd | P52100055852 | 23 Apr 2024 | 31 Dec 2029 | — | Not yet due | 0 |
| AbharanVedant Developers and Builders | P52100055819 | 22 Apr 2024 | 31 Jul 2028 | — | Not yet due | 0 |
| Building C1 Eon HomesHinjawadi Infradevelopment Pvt Ltd | P52100055358 | 22 Mar 2024 | 31 Jan 2029 | — | Not yet due | 0 |
| Global InspiraGlobal Properties | P52100055014 | 26 Feb 2024 | 26 Dec 2026 | — | Not yet due | 0 |
| Dolphin MatrixM/S. Mahalaxmi Promoters | P52100054157 | 29 Dec 2023 | 30 Jun 2026 | — | Promised date passed | 0 |
| Avishkar RidhimaArun Baban Marathe | P52100052836 | 5 Oct 2023 | 31 Dec 2026 | 31 Dec 2027 | Extended 12 mo | 0 |
| Kohinoor FamvilleYellowstone Skyscrapers LLP | P52100051623 | 27 Jun 2023 | 31 Dec 2028 | — | Not yet due | 0 |
| Ceratec West WindsCeratec Lifespaces LLp | P52100050497 | 17 Apr 2023 | 28 Feb 2029 | — | Not yet due | 0 |
| Aditya EnclaveRakhi Pankaj Chopada | P52100050290 | 1 Apr 2023 | 31 Mar 2027 | — | Not yet due | 0 |
| You57 Amenity BuildingSanas Developers Private Limited | P52100049285 | 7 Feb 2023 | 31 Mar 2024 | 31 Mar 2025 | Extended 12 mo | 0 |
| SkyHigh Towers D3New World Landmark LLP | P52100048413 | 3 Jan 2023 | 31 Dec 2027 | — | Not yet due | 0 |
| SkyHigh Towers D4New World Landmark LLP | P52100048403 | 3 Jan 2023 | 31 Dec 2028 | 30 Dec 2029 | Extended 12 mo | 0 |
| Building B2 Eon HomesHinjawadi Infradevelopment Pvt Ltd | P52100048176 | 15 Dec 2022 | 31 Dec 2027 | — | Not yet due | 0 |
| Swanand ResidencyPalande Associates | P52100047573 | 9 Nov 2022 | 31 Mar 2026 | — | Promised date passed | 0 |
| Building C2 Eon HomesHinjawadi Infradevelopment Pvt Ltd | P52100046679 | 29 Aug 2022 | 31 Dec 2027 | — | Not yet due | 0 |
| Yashone EterniteeVilas Javdekar Infinitee Developers Pvt. Ltd. | P52100046122, P52100052676 | 20 Jun 2022 | 30 Jun 2027 | — | Not yet due | 0 |
| SensoriumJoyville Shapoorji Housing Private Limited | P52100045257, P52100049547 | 10 May 2022 | 31 Dec 2026 | — | Not yet due | 0 |
| Apostrophe HinjawadiHinjawadi Infradevelopment Pvt Ltd | P52100031595, P52100048177, P52100080628 | 31 Oct 2021 | 31 Dec 2028 | — | Not yet due | 0 |
| Building C3 Eon homesHinjawadi Infradevelopment Pvt Ltd | P52100030732 | 13 Sep 2021 | 31 Dec 2025 | — | Promised date passed | 0 |
| Welworth PurnamGrow India Realcon LLP | P52100030356 | 17 Aug 2021 | 30 Jun 2026 | — | Promised date passed | 0 |
| Bappa Towerspradeep manohar kodnani | P52100029777 | 29 Jun 2021 | 31 Dec 2026 | — | Not yet due | 0 |
| The AvenuePrimespace Realty Group | P52100029508 | 4 Jun 2021 | 31 Dec 2024 | — | Promised date passed | 0 |
| Sonchandr ResidencyChandan Ramdas Kate | P52100029069 | 23 Apr 2021 | 30 Sep 2026 | — | Promised date passed | 0 |
| The Cliff Garden-Phase 2AVH Township Private Limited | P52100028926 | 15 Apr 2021 | 31 Dec 2025 | — | Promised date passed | 0 |
| SensoriumJoyville Shapoorji Housing Private Limited | P52100027234, P52100027244 | 25 Nov 2020 | 30 Jun 2025 | — | Promised date passed | 0 |
| Building B1 Eon HomesHinjawadi Infradevelopment Pvt Ltd | P52100026429 | 20 Sep 2020 | 30 Jun 2025 | — | Promised date passed | 0 |
| Yashwin SukhNiwasGrowisa Advisors | P52100025982 | 7 Aug 2020 | 30 Dec 2024 | — | Promised date passed | 0 |
| VJ One AvenueVilas Javdekar Eco Shelters Private Limited | P52100025592 | 1 Jul 2020 | 30 Dec 2023 | — | Promised date passed | 0 |
| SensoriumJoyville Shapoorji Housing Private Limited | P52100024963, P52100024964, P52100024965 | 12 Mar 2020 | 30 May 2025 | — | Promised date passed | 0 |
| Building D1 Eon HomesHinjawadi Infradevelopment Pvt Ltd | P52100024680 | 28 Feb 2020 | 30 Jun 2025 | — | Promised date passed | 0 |
| Shiv SparshVedant Developers And Builders | P52100022463 | 25 Sep 2019 | 30 Dec 2022 | — | Promised date passed | 0 |
| Itrend Homes Phase IIIHighpoint Landmark LLP | P52100022236 | 5 Sep 2019 | 30 Dec 2022 | — | Promised date passed | 0 |
| You57Sanas Developers Private Limited | P52100021770, P52100049250 | 23 Jul 2019 | 31 Mar 2025 | — | Promised date passed | 0 |
| YashONE HinjawadiVilas Javdekar Eco Shelters Private Limited | P52100019468, P52100024108 | 1 Feb 2019 | 30 Mar 2025 | — | Promised date passed | 0 |
| Madhuban ParkAdwik Developers | P52100018383 | 26 Oct 2018 | 30 Dec 2022 | 30 Dec 2023 | Extended 12 mo | 0 |
| Itrend Homes Phase II Wing BHighpoint Landmark LLP | P52100017586 | 28 Aug 2018 | 30 Dec 2022 | — | Promised date passed | 0 |
| Tinsel Town Phase IINew World Realty LLP | P52100017178 | 17 Jul 2018 | 30 Dec 2022 | — | Promised date passed | 0 |
| Building D2 Eon homesHinjawadi Infradevelopment Pvt Ltd | P52100016395 | 10 May 2018 | 30 Dec 2023 | — | Promised date passed | 0 |
| Joyville HinjawadiJoyville Shapoorji Housing Private Limited | P52100016131, P52100016252, P52100016775 +3 | 17 Apr 2018 | 30 Sep 2023 | — | Promised date passed | 0 |
| SkyHigh Towers - D1D2New World Landmark LLP | P52100015918 | 9 Apr 2018 | 31 Mar 2028 | — | Not yet due | 0 |
| Menlo Homes HinjewadiMenlo Homes LLP | P52100014732, P52100026972 | 26 Dec 2017 | 31 Dec 2028 | — | Not yet due | 0 |
| Building A3 Eon homesHinjawadi Infradevelopment Pvt Ltd | P52100013714 | 23 Oct 2017 | 30 Dec 2023 | — | Promised date passed | 0 |
| Shubharambh ResidencyAb Developer | P52100008772 | 19 Aug 2017 | 31 Mar 2018 | — | Promised date passed | 0 |
| Platinum ParkSaffron Properties And Schemes | P52100008065 | 18 Aug 2017 | 30 Jun 2021 | 31 Dec 2024 | Extended 42 mo | 0 |
| ShikharSaksham Housing Development LLP | P52100008221 | 18 Aug 2017 | 31 Dec 2018 | 30 Jun 2024 | Extended 66 mo | 0 |
| Tinsel County Phase IIGrow India Realcon LLP | P52100008206 | 18 Aug 2017 | 28 Feb 2021 | — | Promised date passed | 0 |
| Seetai VillaRaju Baburao Jori | P52100007605 | 17 Aug 2017 | 7 Aug 2019 | — | Promised date passed | 0 |
| Building A2 Eon HomesHinjawadi Infradevelopment Pvt Ltd | P52100006888 | 16 Aug 2017 | 30 Dec 2021 | — | Promised date passed | 0 |
| Fortune ShilpFortune Vastushilpa Buildcon LLP | P52100005846 | 14 Aug 2017 | 30 Sep 2020 | 30 Mar 2022 | Extended 18 mo | 0 |
| The Cliff GardenVH Township Private Limited | P52100004906, P52100015759 | 9 Aug 2017 | 30 Dec 2023 | — | Promised date passed | 0 |
| Building D3 Eon HomesHinjawadi Infradevelopment Pvt Ltd | P52100001860 | 29 Jul 2017 | 30 Dec 2021 | — | Promised date passed | 0 |
| Geras Imperium RiseGera Developments Private Limited | P52100001786 | 29 Jul 2017 | 30 May 2022 | 30 May 2022 | Promised date passed | 0 |
| Pebbles-HighMont Phase-1New World Landmark LLP | P52100001895 | 29 Jul 2017 | 30 Dec 2021 | — | Promised date passed | 0 |
| The Crown GreensInternational Biotech Park Limited, International Biotech Park Limited | P52100001864, PR1261012600220 | 29 Jul 2017 | 31 Dec 2028 | — | Not yet due | 0 |
| Apple AromaApple Buildcon | P52100001186 | 27 Jul 2017 | 30 Jun 2019 | — | Promised date passed | 0 |
| Itrend Homes Phase-IHighpoint Landmark LLP | P52100001119 | 26 Jul 2017 | 30 Dec 2022 | — | Promised date passed | 0 |
| Geras AdaraGera Realty Estates | P52100000889 | 23 Jul 2017 | 30 Oct 2023 | — | Promised date passed | 0 |
| Tinsel Town Phase INew World Realty LLP | P52100000392 | 15 Jul 2017 | 31 Dec 2019 | 31 Dec 2019 | Promised date passed | 0 |
| Ace AugustaAceaugusta | P52100000080 | 28 Jun 2017 | 30 Mar 2021 | 30 Sep 2022 | Extended 18 mo | 0 |
| Yashwin HinjawadiVilas Javdekar Eco Shelters Private Limited | P52100000037 | 16 Jun 2017 | 30 Jun 2025 | — | Promised date passed | 0 |
Other localities in Mulshi
- Wakad296 projects
- Punawale183 projects
- Tathwade163 projects
- Bavadhan Bk83 projects
- Hinjavadi (Ct)82 projects
- Sus80 projects
- Bhugaon77 projects
- Mahalunge68 projects
- Thergaon56 projects
- Pirangut49 projects
- Kasar Amboli43 projects
- Dasave27 projects
Most active promoters
By projects registered here, as named on MahaRERA.
- Hinjawadi Infradevelopment Pvt Ltd12 projects
- Joyville Shapoorji Housing Private Limited4 projects
- New World Landmark LLP4 projects
- Highpoint Landmark LLP3 projects
- Sanas Developers Private Limited3 projects
- Vilas Javdekar Eco Shelters Private Limited3 projects
- Grow India Realcon LLP2 projects
- Intofinity Promoters Private Limited2 projects
- New World Realty LLP2 projects
- Vedant Developers and Builders2 projects
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology