Completion was pushed back 4 months, to Oct 2030; no MahaRERA orders on record; 0% of its units are booked.

Man, Pune 411057 · by Hinjawadi Infradevelopment Pvt Ltd · 50% of its projects kept the RERA date

DeliveryExtended 4 moPromised Jun 2030 · now due Oct 2030RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 183 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Oct 2030

  • This projectRegistered 21 May 2025, completion promised 30 Jun 2030, revised to 30 Oct 2030.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

6 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100080318
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210008031821 May 202530 Jun 203030 Oct 2030Hinjawadi Infradevelopment Pvt LtdProject page
Documents82

2 documents held by Deedo, 80 filings listed on MahaRERA's project page

Registration certificate

Other

  • OtherDate not statedView

Finance

  • PAN CardHIPL PAN.pdf · uploaded 9 Jul 2024Source
  • Other – FinanceGetUserDocumentFileContent (13).pdf · uploaded 26 Mar 2025Source

Legal

  • Legal Title reportSearch and Title Report_compressed.pdf · uploaded 4 Mar 2025Source
  • Declaration Form BAffidavit Cum Declaration Form B.pdf · uploaded 4 Mar 2025Source
  • Other – LegalCertificate of Incorporation.pdf · uploaded 12 Mar 2025Source
  • Other – LegalLease Deed.pdf · uploaded 19 Mar 2025Source
Show all 82 documentsShow fewer documents

Migrated

  • 1 PAN CardHIPL PAN.pdf · uploaded 9 Jul 2024Source
  • 2 Copy of Layout Approval (in case of layout)Layout Plan.pdf · uploaded 9 Jul 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architects Certificate.PDF · uploaded 9 Jul 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)B3 form 3.PDF · uploaded 9 Jul 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)B3 Engg Certi_13062024102209 (1).PDF · uploaded 9 Jul 2024Source
  • 3 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 9 Jul 2024Source
  • 5 Building Plan Approval / NA Order for plotted developmentFloor Plan.pdf · uploaded 9 Jul 2024Source
  • 6 Building Plan Approval / NA Order for plotted developmentPlinth , FSI and Floor Plan.pdf · uploaded 9 Jul 2024Source
  • 1 Declaration about Commencement CertificateDeclaration CC.PDF · uploaded 15 Feb 2025Source
  • 1 Deviation Report with respect to Allotment letterNo deviation in Allotment letter.PDF · uploaded 15 Feb 2025Source
  • 1 Deviation Report with respect to model copy of AgreementNo Deviation in Agreement.PDF · uploaded 15 Feb 2025Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure in other organisation Brajesh Gupta pdf.pdf · uploaded 15 Feb 2025Source
  • 1 Copy of the legal title reportSearch and Title Report_compressed.pdf · uploaded 4 Mar 2025Source
  • 1 a Details of encumbrances concerned to Financeilovepdf_merged (8).pdf · uploaded 4 Mar 2025Source
  • 1 Declaration in FORM BAffidavit Cum Declaration Form B.pdf · uploaded 4 Mar 2025Source
  • 1 CERSAI detailsCERSAI Declaration.PDF · uploaded 4 Mar 2025Source
  • 1 b Details of encumbrances concerned to Legalilovepdf_merged (8).pdf · uploaded 4 Mar 2025Source
  • 1 Proforma of Agreement for saleAgreement for sale 4th Feb 2025.pdf · uploaded 4 Mar 2025Source
  • 1 Other – LegalCertificate of Incorporation.pdf · uploaded 12 Mar 2025Source
  • 1 Other – TechnicalCertificate of Incorporation.pdf · uploaded 12 Mar 2025Source
  • 1 Copy of Layout Approval (in case of layout)HIGHLIGHTED BUILDING B3 WITH PLINTH AREA - EON HOMES 11-06-2024_compressed (1).pdf · uploaded 19 Mar 2025Source
  • 2 Other – LegalLease Deed.pdf · uploaded 19 Mar 2025Source
  • 1 Proforma of Allotment letterAllotment letter.pdf · uploaded 26 Mar 2025Source
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)Format A declaration about separate account.pdf · uploaded 26 Mar 2025Source
  • 1 Other – FinanceGetUserDocumentFileContent (13).pdf · uploaded 26 Mar 2025Source
  • 5 Other – TechnicalAnnexure A order 50.pdf · uploaded 26 Mar 2025Source
  • 4 Other – Technical2 Other – Legal.pdf · uploaded 26 Mar 2025Source
  • 3 Other – TechnicalEon Homes MIDC Plinth.pdf · uploaded 26 Mar 2025Source
  • 2 Other – TechnicalClarification of Plinth Area.PDF · uploaded 26 Mar 2025Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsDisclosure in other organisation.pdf · uploaded 26 Mar 2025Source
  • 1 Disclosure for secured/unsecured finance availed for the projectDisclosure of secured unsecured finance.pdf · uploaded 26 Mar 2025Source
  • 2 a Details of encumbrances concerned to FinanceEncumbrance Finance Eon B3.pdf · uploaded 11 Apr 2025Source
  • 2 b Details of encumbrances concerned to LegalEncumbrance Finance Eon B3.pdf · uploaded 11 Apr 2025Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)Hinjawadi .pdf · uploaded 16 Apr 2025Source
  • 1 Commencement Certificates / NA Order for plotted developmentLower Ground Parking Plan.pdf · uploaded 23 Apr 2025Source
  • 2 Commencement Certificates / NA Order for plotted developmentUpper Ground Parking Plan.pdf · uploaded 23 Apr 2025Source
  • 2 Declaration about Commencement Certificateilovepdf_merged (10).pdf · uploaded 23 Apr 2025Source
  • 3 a Details of encumbrances concerned to FinanceEncumbrance Letter Finance.pdf · uploaded 15 May 2025Source
  • 1 Building Plan Approval / NA Order for plotted developmentLower Ground Parking Plan.pdf · uploaded 15 May 2025Source
  • 2 Building Plan Approval / NA Order for plotted developmentUpper Ground Parking Plan.pdf · uploaded 15 May 2025Source
  • 3 Building Plan Approval / NA Order for plotted developmentFloor Plan.pdf · uploaded 15 May 2025Source
  • 4 Building Plan Approval / NA Order for plotted developmentLower Ground Parking Plan.pdf · uploaded 15 May 2025Source
  • 3 b Details of encumbrances concerned to LegalEncumbrance Letter Finance.pdf · uploaded 15 May 2025Source
  • Form 1Tower B3 FORM 1 ARCHITECTS CERTIFICATE.PDF · uploaded 14 Oct 2025Source
  • Form 2EON-B03.PDF · uploaded 14 Oct 2025Source
  • Form 3B3_Form 3.PDF · uploaded 14 Oct 2025Source
  • Disclosure of Sold and Booked InventoryB3 Sold Unsold_13102025124105.PDF · uploaded 14 Oct 2025View
  • Form 1Form 1 Architect Certificate Building B3.PDF · uploaded 9 Jan 2026Source
  • Form 2B3 Form 2.pdf · uploaded 9 Jan 2026Source
  • Form 3EON B3 form 3.PDF · uploaded 9 Jan 2026Source
  • Disclosure of Sold and Booked InventoryB3 RERA inventory_07012026160858.PDF · uploaded 9 Jan 2026View
  • Form 1Form 1 Eon Homes Tower B3.PDF · uploaded 10 Apr 2026Source
  • Form 2EON B3 JAN-MAR 26.PDF · uploaded 10 Apr 2026Source
  • Form 3B3.PDF · uploaded 10 Apr 2026Source
  • Disclosure of Sold and Booked InventoryB3.PDF · uploaded 10 Apr 2026View
  • Form 1Form 1 Tower B3.PDF · uploaded 20 Jul 2026Source
  • Form 2Eon Homes B3.PDF · uploaded 20 Jul 2026Source
  • Form 3Hipl Form3 B3.PDF · uploaded 20 Jul 2026Source
  • Disclosure of Sold and Booked InventoryEON B3 inventory_13072026101914.PDF · uploaded 20 Jul 2026View

Technical

  • DocumentLayout Plan.pdf · uploaded 9 Jul 2024Source
  • DocumentFloor Plan.pdf · uploaded 9 Jul 2024Source
  • DocumentPlinth , FSI and Floor Plan.pdf · uploaded 9 Jul 2024Source
  • Other – TechnicalCertificate of Incorporation.pdf · uploaded 12 Mar 2025Source
  • DocumentHIGHLIGHTED BUILDING B3 WITH PLINTH AREA - EON HOMES 11-06-2024_compressed (1).pdf · uploaded 19 Mar 2025Source
  • Other – TechnicalClarification of Plinth Area.PDF · uploaded 26 Mar 2025Source
  • Other – TechnicalEon Homes MIDC Plinth.pdf · uploaded 26 Mar 2025Source
  • Other – Technical2 Other – Legal.pdf · uploaded 26 Mar 2025Source
  • Other – TechnicalAnnexure A order 50.pdf · uploaded 26 Mar 2025Source
  • DocumentLower Ground Parking Plan.pdf · uploaded 15 May 2025Source
  • DocumentUpper Ground Parking Plan.pdf · uploaded 15 May 2025Source
  • DocumentFloor Plan.pdf · uploaded 15 May 2025Source
  • DocumentLower Ground Parking Plan.pdf · uploaded 15 May 2025Source

Technical (Architect)

  • DocumentArchitects Certificate.PDF · uploaded 9 Jul 2024Source

Technical (Engineer)

  • DocumentB3 Engg Certi_13062024102209 (1).PDF · uploaded 9 Jul 2024Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel Plot R3/1

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
2BHK183 units in all
Address
Plot R-3/1, Adjacent to Tech Mahindra, Hinjawadi Phase IIIPIN 411057
Village
Man, Mulshi taluka
Land area for this project
840 sq m (9,041 sq ft)
Permissible built-up area
16,964 sq m (1,82,603 sq ft)
Sanctioned built-up area
16,964 sq m (1,82,603 sq ft)
Recreational open space
9,086 sq m (97,801 sq ft)
Designated bank account
85
Developed in phases
No

Survey, CTS, gat or plot numbers

Plot R3/1

Land as published on MahaRERA's project page

Plot R-3/1

Boundaries

North
Portion of layout
South
Portion of layout Periphery Road and compound wall
East
Portion of Layout
West
portion of Layout

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking183 units

0 of 183 units booked (0%), as the promoter reported to MahaRERA

2BHK · 183 units
TypeCarpet areaUnitsBooked
2BHK77.65 sq m · 836 sq ft450
2BHK77.98 sq m · 839 sq ft460
2BHK88.99 sq m · 958 sq ft460
2BHK90.42 sq m · 973 sq ft460

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals9

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectMs Sudhir Patil and Associates—
Chartered accountantMantri Maru and company—
EngineerAchyut Watve—
Registered real estate agentAdarsh Vikram Singh—
Registered real estate agentAnand Ajit Gupte—
Registered real estate agentNeeraj Giri—
Registered real estate agentPiyush Shrawan Singh Shekhawat—
Registered real estate agentPrashant Vitthal Arote—
Registered real estate agentSuhail Ahmad—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology