Skip to content
Residential / Group Housing · 3 buildings · 168 unitsRERA P52100028299

Asmi Pride

Deedo IDDP-PUN-NBEG

It is due for completion in Dec 2026, with no extension on record; no MahaRERA orders on record; 98% of its units are booked.

Bhukum, Pune 412115 · Property rates in Bhukum · by Icon Developers

DeliveryDue Dec 2026No extension on recordRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales98% booked164 of 168 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

It is due for completion in Dec 2026, with no extension on record

  • This projectRegistered 18 Feb 2021, completion promised 31 Dec 2026.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

3 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100028299
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210002829918 Feb 202131 Dec 202631 Dec 2026M/S Icon DevelopersProject page
Documents161

1 document held by Deedo, 160 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPan Card-1.pdf · uploaded 8 Feb 2021Source

Legal

  • Legal Title reportAsmi pride title declaration.pdf · uploaded 3 Feb 2021Source
  • Declaration Form BAsmi declaration_compressed.pdf · uploaded 3 Feb 2021Source
  • Legal Title reportTitle and Search Report 1-11.pdf · uploaded 8 Feb 2021Source
  • Legal Title reportTitle and Search Report12-22.pdf · uploaded 8 Feb 2021Source

Migrated

  • 1 Copy of the legal title reportAsmi pride title declaration.pdf · uploaded 3 Feb 2021Source
  • 1 Declaration in FORM BAsmi declaration_compressed.pdf · uploaded 3 Feb 2021Source
Show all 161 documentsShow fewer documents

Migrated

  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Asmi ca form.pdf · uploaded 3 Feb 2021Source
  • 1 PAN CardPan Card-1.pdf · uploaded 8 Feb 2021Source
  • 2 Copy of the legal title reportTitle and Search Report 1-11.pdf · uploaded 8 Feb 2021Source
  • 3 Copy of the legal title reportTitle and Search Report12-22.pdf · uploaded 8 Feb 2021Source
  • 1 Details of encumbrancesAsmi encumbrance.pdf · uploaded 8 Feb 2021Source
  • 1 Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 8 Feb 2021Source
  • 1 Building Plan Approval / NA Order for plotted developmentScan 2019-11-28 (16,12,11)_compressed.pdf · uploaded 8 Feb 2021Source
  • 2 Building Plan Approval / NA Order for plotted developmentScan 2019-11-28 (16,12,56)_compressed.pdf · uploaded 8 Feb 2021Source
  • 3 Building Plan Approval / NA Order for plotted developmentScan 2019-11-28 (16,13,41)_compressed.pdf · uploaded 8 Feb 2021Source
  • 4 Building Plan Approval / NA Order for plotted developmentScan 2019-11-28 (16,14,34)_compressed.pdf · uploaded 8 Feb 2021Source
  • 5 Building Plan Approval / NA Order for plotted developmentScan 2019-11-28 (16,15,26)_compressed.pdf · uploaded 8 Feb 2021Source
  • 6 Building Plan Approval / NA Order for plotted developmentScan 2019-11-28 (16,16,13)_compressed.pdf · uploaded 8 Feb 2021Source
  • 1 Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT CERTIFICATE.pdf · uploaded 8 Feb 2021Source
  • 1 Proforma of Allotment letterDRAFT AGREEMENT COPY_compressed.pdf · uploaded 8 Feb 2021Source
  • 2 Proforma of Allotment letterALLOTMENT LETTER.pdf · uploaded 8 Feb 2021Source
  • 1 Declaration about Commencement CertificateCommencement declaration.pdf · uploaded 15 Aug 2021Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE (3).pdf · uploaded 15 Aug 2021Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER CERTIFICATE (1).pdf · uploaded 15 Aug 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM 2A (2) (1).pdf · uploaded 15 Aug 2021Source
  • 1 Disclosure of sold/ booked inventoryASAMI PRIDE_compressed.pdf · uploaded 15 Aug 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)FORM 5 (1).pdf · uploaded 15 Aug 2021Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Asmi Pride.pdf · uploaded 28 Aug 2021Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Asmi Pride.pdf · uploaded 28 Aug 2021Source
  • 2 Details of encumbrancesAsmi Pride Encumbrances.pdf · uploaded 10 Dec 2021Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 ARCHITECT CERTIFIACTE ASMI PRIDE.pdf · uploaded 15 Aug 2022Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 ENGINEER CERTIFIACTE ASMI PRIDE_compressed.pdf · uploaded 15 Aug 2022Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 CA certificate ASMI PRIDE_compressed.pdf · uploaded 15 Aug 2022Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1.pdf · uploaded 28 Feb 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2 (1).pdf · uploaded 28 Feb 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form-2A.pdf · uploaded 28 Feb 2023Source
  • 2 Disclosure of sold/ booked inventorySold-Unsold.pdf · uploaded 28 Feb 2023Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3.pdf · uploaded 28 Feb 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form-5.pdf · uploaded 28 Feb 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate 11-07-2023.pdf · uploaded 11 Jul 2023Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate Form 2 11-07-2023.pdf · uploaded 11 Jul 2023Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Engineer Certificate Form 2A 11-07-2023.pdf · uploaded 11 Jul 2023Source
  • 3 Disclosure of sold/ booked inventorySOLD - UNSOLD 11-07-2023_compressed.pdf · uploaded 11 Jul 2023Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)ICON DEVELOPERS FORM3 11-07-2023.pdf · uploaded 11 Jul 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Engineer Certificate Form 2A 11-07-2023.pdf · uploaded 9 Sep 2023Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)31-12-2021.pdf · uploaded 1 Nov 2023Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)31-03-2022.pdf · uploaded 1 Nov 2023Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)30-09-2022.pdf · uploaded 1 Nov 2023Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)31-03-2023.pdf · uploaded 1 Nov 2023Source
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)31-03-2023.pdf · uploaded 1 Nov 2023Source
  • 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)30-09-2023.pdf · uploaded 1 Nov 2023Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)31-12-2021.pdf · uploaded 1 Nov 2023Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)31-03-2022.pdf · uploaded 1 Nov 2023Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)30-09-2022.pdf · uploaded 1 Nov 2023Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)31-03-2023.pdf · uploaded 1 Nov 2023Source
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)30-09-2023.pdf · uploaded 1 Nov 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM 5 31-03-2023.pdf · uploaded 1 Nov 2023Source
  • 2 Copy of Layout Approval (in case of layout)1 (9).pdf · uploaded 2 Nov 2023Source
  • 7 Building Plan Approval / NA Order for plotted development2 (4).pdf · uploaded 2 Nov 2023Source
  • 8 Building Plan Approval / NA Order for plotted development3 (4).pdf · uploaded 2 Nov 2023Source
  • 9 Building Plan Approval / NA Order for plotted development4 (2).pdf · uploaded 2 Nov 2023Source
  • 10 Building Plan Approval / NA Order for plotted development5 (14).pdf · uploaded 2 Nov 2023Source
  • 11 Building Plan Approval / NA Order for plotted development6 (4).pdf · uploaded 2 Nov 2023Source
  • 12 Building Plan Approval / NA Order for plotted development7 (1).pdf · uploaded 2 Nov 2023Source
  • 13 Building Plan Approval / NA Order for plotted development8 (1).pdf · uploaded 2 Nov 2023Source
  • 2 Commencement Certificates / NA Order for plotted developmentAsmi pride CC.pdf · uploaded 2 Nov 2023Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A.pdf · uploaded 2 Nov 2023Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)31-12-2021.pdf · uploaded 2 Nov 2023Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)31-03-2022.pdf · uploaded 2 Nov 2023Source
  • 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)30-09-2022.pdf · uploaded 2 Nov 2023Source
  • 4 Disclosure of sold/ booked inventorySOLD UNSOLD 30-09-2023.pdf · uploaded 3 Nov 2023Source
  • 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)31-03-2023-Asmi pride.pdf · uploaded 3 Nov 2023Source
  • 11 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 30-09-2023-ASMI PRIDE.pdf · uploaded 3 Nov 2023Source
  • 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)1 ARCHITECT CERTIFICATE WING 09-05-24.pdf · uploaded 30 May 2024Source
  • 12 CA Certificate on Project Cost & Fund withdrawal (Form 3)3 FORM 3 09-05-24.pdf · uploaded 30 May 2024Source
  • 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER CERTIFICATE FORM 2.pdf · uploaded 25 Jul 2024Source
  • 2 Disclosure of sold/ booked inventorysold and unsold.pdf · uploaded 12 Nov 2024Source
  • 3 Disclosure of sold/ booked inventorysold unsold.pdf · uploaded 12 Nov 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 31 12 2022.pdf · uploaded 11 Dec 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 31 12 2023.pdf · uploaded 11 Dec 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 30 06 2024.pdf · uploaded 11 Dec 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 30 09 2024.pdf · uploaded 11 Dec 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 31 12 2021.pdf · uploaded 11 Dec 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 31 12 2023.pdf · uploaded 11 Dec 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 30 06 2024.pdf · uploaded 11 Dec 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 30 09 2024.pdf · uploaded 11 Dec 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 30 06 2024.pdf · uploaded 11 Dec 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 30 09 2024.pdf · uploaded 11 Dec 2024Source
  • 4 Disclosure of sold/ booked inventorySOLD UNSOLD 31 03 2023.pdf · uploaded 11 Dec 2024Source
  • 5 Disclosure of sold/ booked inventorySOLD UNSOLD 31 12 2023.pdf · uploaded 11 Dec 2024Source
  • 6 Disclosure of sold/ booked inventorySOLD UNSOLD 30 06 2024.pdf · uploaded 11 Dec 2024Source
  • 7 Disclosure of sold/ booked inventorySOLD UNSOLD 30 09 2024.pdf · uploaded 11 Dec 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 31 12 2021.pdf · uploaded 12 Dec 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM 2A 31 03 2024.pdf · uploaded 12 Dec 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)FORM 5 31 03 2024 (2).pdf · uploaded 12 Dec 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 31 12 2024 (2).pdf · uploaded 2 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 31 12 2024 (2).pdf · uploaded 2 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 31 12 2024 (2).pdf · uploaded 2 Jan 2025Source
  • 1 Disclosure of sold/ booked inventorySOLD UNSOLD 31 12 2024 (2).pdf · uploaded 2 Jan 2025Source
  • Form 1FORM 1 01-04-2025.pdf · uploaded 29 May 2025Source
  • Form 2FORM 2 01-04-2025.pdf · uploaded 29 May 2025Source
  • Form 3FORM 3 01-04-2025.pdf · uploaded 29 May 2025Source
  • Disclosure of Sold and Booked InventorySOLD UNSOLD 01-04-2025.pdf · uploaded 29 May 2025Source
  • Form 1FORM 1 ARCHITECT CERTIFICATE 30-06-2025.pdf · uploaded 2 Dec 2025Source
  • Form 2FORM 2 ENGINEER CERTIFICATE 30-06-2025.pdf · uploaded 2 Dec 2025Source
  • Form 3FORM 3 CA CERTIFICATE 30-06-2025.pdf · uploaded 2 Dec 2025Source
  • Disclosure of Sold and Booked InventorySOLD UNSOLD 30-06-2025.pdf · uploaded 2 Dec 2025Source
  • Form 1Form 1.pdf · uploaded 19 Feb 2026Source
  • Form 1Form 1.pdf · uploaded 19 Feb 2026Source
  • Form 1Form 1.pdf · uploaded 19 Feb 2026Source
  • Form 1Form 1.pdf · uploaded 19 Feb 2026Source
  • Form 2Form 2.pdf · uploaded 19 Feb 2026Source
  • Form 2Form 2.pdf · uploaded 19 Feb 2026Source
  • Form 2Form 2.pdf · uploaded 19 Feb 2026Source
  • Form 2Form 2.pdf · uploaded 19 Feb 2026Source
  • Form 3Form 3.pdf · uploaded 19 Feb 2026Source
  • Form 3Form 3.pdf · uploaded 19 Feb 2026Source
  • Form 3Form 3.pdf · uploaded 19 Feb 2026Source
  • Form 3Form 3.pdf · uploaded 19 Feb 2026Source
  • Disclosure of Sold and Booked InventorySold Unsold Inventory.pdf · uploaded 19 Feb 2026Source
  • Disclosure of Sold and Booked InventorySold Unsold Inventoy.pdf · uploaded 19 Feb 2026Source
  • Disclosure of Sold and Booked InventorySold Unsold Inventory.pdf · uploaded 19 Feb 2026Source
  • Disclosure of Sold and Booked InventorySold Unsold Inventory.pdf · uploaded 19 Feb 2026Source
  • Form 1FORM 1.pdf · uploaded 24 Feb 2026Source
  • Form 2FORM 2.pdf · uploaded 24 Feb 2026Source
  • Form 3FORM 3.pdf · uploaded 24 Feb 2026Source
  • Disclosure of Sold and Booked InventorySold Unsold Inventory.pdf · uploaded 24 Feb 2026Source
  • Withdrawal Update Form 1Architect Certificate Ms Icon Developers 30-09-2025.pdf · uploaded 5 Mar 2026Source
  • Withdrawal Update Form 2Engineer Certificate Form 2 Ms Icon Developers 30-09-2025.pdf · uploaded 5 Mar 2026Source
  • Withdrawal Update Form 3icon form 3 April to september 25.pdf · uploaded 5 Mar 2026Source
  • Withdrawal Update Form 1Architect Certificate Ms Icon Developers 31-12-2025.pdf · uploaded 6 Mar 2026Source
  • Withdrawal Update Form 2Engineer Certificate Form 2 Ms Icon Developers 31-12-2025.pdf · uploaded 6 Mar 2026Source
  • Withdrawal Update Form 3Icon Form 3 Dec 25.pdf · uploaded 6 Mar 2026Source

Technical

  • DocumentLayout.pdf · uploaded 8 Feb 2021Source
  • DocumentScan 2019-11-28 (16,12,11)_compressed.pdf · uploaded 8 Feb 2021Source
  • DocumentScan 2019-11-28 (16,12,56)_compressed.pdf · uploaded 8 Feb 2021Source
  • DocumentScan 2019-11-28 (16,13,41)_compressed.pdf · uploaded 8 Feb 2021Source
  • DocumentScan 2019-11-28 (16,14,34)_compressed.pdf · uploaded 8 Feb 2021Source
  • DocumentScan 2019-11-28 (16,15,26)_compressed.pdf · uploaded 8 Feb 2021Source
  • DocumentScan 2019-11-28 (16,16,13)_compressed.pdf · uploaded 8 Feb 2021Source
  • Document1 (9).pdf · uploaded 2 Nov 2023Source
  • Document2 (4).pdf · uploaded 2 Nov 2023Source
  • Document3 (4).pdf · uploaded 2 Nov 2023Source
  • Document4 (2).pdf · uploaded 2 Nov 2023Source
  • Document5 (14).pdf · uploaded 2 Nov 2023Source
  • Document6 (4).pdf · uploaded 2 Nov 2023Source
  • Document7 (1).pdf · uploaded 2 Nov 2023Source
  • Document8 (1).pdf · uploaded 2 Nov 2023Source

Technical (Architect)

  • DocumentFORM 1 31 12 2022.pdf · uploaded 11 Dec 2024Source
  • DocumentFORM 1 31 12 2023.pdf · uploaded 11 Dec 2024Source
  • DocumentFORM 1 30 06 2024.pdf · uploaded 11 Dec 2024Source
  • DocumentFORM 1 30 09 2024.pdf · uploaded 11 Dec 2024Source
  • DocumentFORM 1 31 12 2024 (2).pdf · uploaded 2 Jan 2025Source
  • DocumentArchitect Certificate Ms Icon Developers 31-12-2025.pdf · uploaded 6 Mar 2026Source

Technical (Engineer)

  • DocumentFORM 2 30 06 2024.pdf · uploaded 11 Dec 2024Source
  • DocumentFORM 2 30 09 2024.pdf · uploaded 11 Dec 2024Source
  • DocumentFORM 2 31 12 2021.pdf · uploaded 12 Dec 2024Source
  • DocumentFORM 2 31 12 2024 (2).pdf · uploaded 2 Jan 2025Source
  • DocumentEngineer Certificate Form 2 Ms Icon Developers 31-12-2025.pdf · uploaded 6 Mar 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 64, 65

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
101 landowner, 102, 103, 104, 105, 106, 107 landowner, 108, 109 landowner, 110, 201, 202, 203, 204 landowner, 205 landowner, 206, 207, 208, 209, 210, 301, 302, 303, 304 landowner, 305, 306 landowner, 307, 308, 309, 310, 401, 402, 403, 404, 405, 406 landowner, 407, 408, 409 landowner, 410, 501, 502, 503, 504, 505, 506 landowner, 507, 508, 509, 510, 601, 602, 603, 604 landowner, 605, 606, 607, 608, 609, 610, 102 landowner, 107, 109, 111 landowner, 112, 204, 210 landowner, 211 landowner, 212 landowner, 306, 310 landowner, 311, 312, 403 landowner, 406, 407 landowner, 408 landowner, 409, 410 landowner, 411 landowner, 412 landowner, 504 landowner, 506, 507 landowner, 508 landowner, 509 landowner, 510 landowner, 511 landowner, 512 landowner, 603 landowner, 605 landowner, 606 landowner, 611, 612, 103 landowner, 104 landowner, 202 landowner, 203 landowner, 205, 302 landowner, 303 landowner, 604168 units in all
Address
Gat No. 63 Part, 64, 65 And 68, BhukumPIN 412115
Village
Bhukum, Mulshi taluka
Land area for this project
6,920 sq m (74,486 sq ft)
Permissible built-up area
10,822 sq m (1,16,489 sq ft)
Sanctioned built-up area
8,822 sq m (94,962 sq ft)
Recreational open space
692 sq m (7,449 sq ft)
Designated bank account
85
Developed in phases
Yes

Survey, CTS, gat or plot numbers

646568GAT NO. 63 PART

Land as published on MahaRERA's project page

GAT NO. 63 PART, 64, 65 AND 68

Boundaries

North
By Gat No 63 Part
South
By Adj Gat No 74 Part
East
By 15 Mtr Wide Road
West
By Adj Gat No 66 And 69 Part

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking168 units

164 of 168 units booked (98%), as the promoter reported to MahaRERA

101 landowner · 3 units102 · 1 unit103 · 2 units104 · 2 units105 · 3 units106 · 3 units107 landowner · 1 unit108 · 2 units109 landowner · 1 unit110 · 2 units201 · 3 units202 · 2 units203 · 2 units204 landowner · 2 units205 landowner · 2 units206 · 3 units207 · 2 units208 · 2 units209 · 2 units210 · 1 unit301 · 3 units302 · 2 units303 · 2 units304 landowner · 3 units305 · 3 units306 landowner · 1 unit307 · 2 units308 · 2 units309 · 2 units310 · 1 unit401 · 3 units402 · 3 units403 · 2 units404 · 3 units405 · 3 units406 landowner · 1 unit407 · 1 unit408 · 1 unit409 landowner · 1 unit410 · 1 unit501 · 3 units502 · 3 units503 · 3 units504 · 2 units505 · 3 units506 landowner · 1 unit507 · 1 unit508 · 1 unit509 · 1 unit510 · 1 unit601 · 3 units602 · 3 units603 · 2 units604 landowner · 2 units605 · 2 units606 · 2 units607 · 2 units608 · 2 units609 · 2 units610 · 2 units102 landowner · 2 units107 · 1 unit109 · 1 unit111 landowner · 1 unit112 · 1 unit204 · 1 unit210 landowner · 1 unit211 landowner · 1 unit212 landowner · 1 unit306 · 2 units310 landowner · 1 unit311 · 1 unit312 · 1 unit403 landowner · 1 unit406 · 2 units407 landowner · 1 unit408 landowner · 1 unit409 · 1 unit410 landowner · 1 unit411 landowner · 1 unit412 landowner · 1 unit504 landowner · 1 unit506 · 2 units507 landowner · 1 unit508 landowner · 1 unit509 landowner · 1 unit510 landowner · 1 unit511 landowner · 1 unit512 landowner · 1 unit603 landowner · 1 unit605 landowner · 1 unit606 landowner · 1 unit611 · 1 unit612 · 1 unit103 landowner · 1 unit104 landowner · 1 unit202 landowner · 1 unit203 landowner · 1 unit205 · 1 unit302 landowner · 1 unit303 landowner · 1 unit604 · 1 unit
BuildingTypeCarpet areaUnitsBooked
Wing A101 landowner40.51 sq m · 436 sq ft11
Wing A10240.51 sq m · 436 sq ft11
Wing A10365.23 sq m · 702 sq ft11
Wing A10440.33 sq m · 434 sq ft11
Wing A10540.33 sq m · 434 sq ft11
Wing A10640.33 sq m · 434 sq ft11
Wing A107 landowner40.51 sq m · 436 sq ft11
Wing A10840.2 sq m · 433 sq ft11
Show all 168 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
Wing A109 landowner40.2 sq m · 433 sq ft11
Wing A11040.2 sq m · 433 sq ft11
Wing A20140.51 sq m · 436 sq ft11
Wing A20240.51 sq m · 436 sq ft11
Wing A20365.23 sq m · 702 sq ft11
Wing A204 landowner40.33 sq m · 434 sq ft11
Wing A205 landowner40.33 sq m · 434 sq ft11
Wing A20640.2 sq m · 433 sq ft11
Wing A20740.2 sq m · 433 sq ft11
Wing A20840.2 sq m · 433 sq ft11
Wing A20940.2 sq m · 433 sq ft11
Wing A21040.2 sq m · 433 sq ft11
Wing A30140.51 sq m · 436 sq ft11
Wing A30240.51 sq m · 436 sq ft11
Wing A30365.23 sq m · 702 sq ft11
Wing A304 landowner40.33 sq m · 434 sq ft11
Wing A30540.33 sq m · 434 sq ft11
Wing A306 landowner40.2 sq m · 433 sq ft11
Wing A30740.2 sq m · 433 sq ft11
Wing A30840.2 sq m · 433 sq ft11
Wing A30940.2 sq m · 433 sq ft11
Wing A31040.2 sq m · 433 sq ft11
Wing A40140.51 sq m · 436 sq ft11
Wing A40240.51 sq m · 436 sq ft11
Wing A40365.23 sq m · 702 sq ft11
Wing A40440.33 sq m · 434 sq ft11
Wing A40540.33 sq m · 434 sq ft11
Wing A406 landowner40.2 sq m · 433 sq ft11
Wing A40740.2 sq m · 433 sq ft11
Wing A40840.2 sq m · 433 sq ft11
Wing A409 landowner40.2 sq m · 433 sq ft11
Wing A41040.2 sq m · 433 sq ft11
Wing A50140.51 sq m · 436 sq ft11
Wing A50240.51 sq m · 436 sq ft11
Wing A50365.23 sq m · 702 sq ft11
Wing A50440.33 sq m · 434 sq ft11
Wing A50540.33 sq m · 434 sq ft11
Wing A506 landowner40.2 sq m · 433 sq ft11
Wing A50740.2 sq m · 433 sq ft11
Wing A50840.2 sq m · 433 sq ft11
Wing A50940.2 sq m · 433 sq ft11
Wing A51040.2 sq m · 433 sq ft11
Wing A60140.51 sq m · 436 sq ft11
Wing A60240.51 sq m · 436 sq ft11
Wing A60365.23 sq m · 702 sq ft11
Wing A604 landowner40.33 sq m · 434 sq ft11
Wing A60540.33 sq m · 434 sq ft11
Wing A60640.33 sq m · 434 sq ft11
Wing A60740.2 sq m · 433 sq ft11
Wing A60840.2 sq m · 433 sq ft11
Wing A60940.2 sq m · 433 sq ft11
Wing A61040.2 sq m · 433 sq ft11
Wing B101 landowner63.34 sq m · 682 sq ft11
Wing B102 landowner63.34 sq m · 682 sq ft11
Wing B10363.34 sq m · 682 sq ft11
Wing B10463.34 sq m · 682 sq ft11
Wing B10540.56 sq m · 437 sq ft11
Wing B10640.2 sq m · 433 sq ft11
Wing B10740.2 sq m · 433 sq ft11
Wing B10840.2 sq m · 433 sq ft11
Wing B10940.2 sq m · 433 sq ft10
Wing B11040.2 sq m · 433 sq ft11
Wing B111 landowner40.2 sq m · 433 sq ft11
Wing B11240.56 sq m · 437 sq ft11
Wing B20163.34 sq m · 682 sq ft11
Wing B20263.34 sq m · 682 sq ft11
Wing B20363.34 sq m · 682 sq ft11
Wing B20463.34 sq m · 682 sq ft11
Wing B205 landowner40.56 sq m · 437 sq ft11
Wing B20640.2 sq m · 433 sq ft11
Wing B20740.2 sq m · 433 sq ft11
Wing B20840.2 sq m · 433 sq ft11
Wing B20940.2 sq m · 433 sq ft11
Wing B210 landowner40.2 sq m · 433 sq ft11
Wing B211 landowner40.2 sq m · 433 sq ft11
Wing B212 landowner40.56 sq m · 437 sq ft11
Wing B30163.34 sq m · 682 sq ft11
Wing B30263.34 sq m · 682 sq ft11
Wing B30363.34 sq m · 682 sq ft11
Wing B304 landowner63.34 sq m · 682 sq ft11
Wing B30540.56 sq m · 437 sq ft11
Wing B30640.2 sq m · 433 sq ft11
Wing B30740.2 sq m · 433 sq ft11
Wing B30840.2 sq m · 433 sq ft11
Wing B30940.2 sq m · 433 sq ft11
Wing B310 landowner40.2 sq m · 433 sq ft11
Wing B31140.2 sq m · 433 sq ft11
Wing B31240.2 sq m · 433 sq ft11
Wing B40163.34 sq m · 682 sq ft10
Wing B40263.34 sq m · 682 sq ft11
Wing B403 landowner63.34 sq m · 682 sq ft11
Wing B40463.34 sq m · 682 sq ft11
Wing B40540.56 sq m · 437 sq ft11
Wing B40640.2 sq m · 433 sq ft11
Wing B407 landowner40.2 sq m · 433 sq ft11
Wing B408 landowner40.2 sq m · 433 sq ft11
Wing B40940.2 sq m · 433 sq ft11
Wing B410 landowner40.2 sq m · 433 sq ft11
Wing B411 landowner40.2 sq m · 433 sq ft11
Wing B412 landowner40.56 sq m · 437 sq ft11
Wing B50163.34 sq m · 682 sq ft11
Wing B50263.34 sq m · 682 sq ft11
Wing B50363.34 sq m · 682 sq ft11
Wing B504 landowner63.34 sq m · 682 sq ft11
Wing B50540.56 sq m · 437 sq ft11
Wing B50640.2 sq m · 433 sq ft11
Wing B507 landowner40.2 sq m · 433 sq ft11
Wing B508 landowner40.2 sq m · 433 sq ft11
Wing B509 landowner40.2 sq m · 433 sq ft11
Wing B510 landowner40.2 sq m · 433 sq ft11
Wing B511 landowner40.2 sq m · 433 sq ft11
Wing B512 landowner40.56 sq m · 437 sq ft11
Wing B60163.34 sq m · 682 sq ft11
Wing B60263.34 sq m · 682 sq ft11
Wing B603 landowner63.34 sq m · 682 sq ft11
Wing B604 landowner63.34 sq m · 682 sq ft11
Wing B605 landowner40.56 sq m · 437 sq ft11
Wing B606 landowner40.2 sq m · 433 sq ft11
Wing B60740.2 sq m · 433 sq ft11
Wing B60840.2 sq m · 433 sq ft11
Wing B60940.2 sq m · 433 sq ft11
Wing B61040.2 sq m · 433 sq ft11
Wing B61140.2 sq m · 433 sq ft11
Wing B61240.56 sq m · 437 sq ft11
Wing C101 landowner65.31 sq m · 703 sq ft11
Wing C102 landowner44.62 sq m · 480 sq ft11
Wing C103 landowner44.62 sq m · 480 sq ft11
Wing C104 landowner44.62 sq m · 480 sq ft11
Wing C10564.87 sq m · 698 sq ft11
Wing C10666.03 sq m · 711 sq ft11
Wing C20165.31 sq m · 703 sq ft11
Wing C202 landowner44.62 sq m · 480 sq ft11
Wing C203 landowner44.62 sq m · 480 sq ft11
Wing C204 landowner44.62 sq m · 480 sq ft11
Wing C20564.87 sq m · 698 sq ft11
Wing C20666.03 sq m · 711 sq ft11
Wing C30165.31 sq m · 703 sq ft11
Wing C302 landowner44.62 sq m · 480 sq ft11
Wing C303 landowner44.62 sq m · 480 sq ft11
Wing C304 landowner44.62 sq m · 480 sq ft11
Wing C30564.87 sq m · 698 sq ft11
Wing C30666.03 sq m · 711 sq ft10
Wing C40165.31 sq m · 703 sq ft11
Wing C40244.62 sq m · 480 sq ft11
Wing C40344.62 sq m · 480 sq ft10
Wing C40444.62 sq m · 480 sq ft11
Wing C40564.87 sq m · 698 sq ft11
Wing C40666.03 sq m · 711 sq ft11
Wing C50165.31 sq m · 703 sq ft11
Wing C50244.62 sq m · 480 sq ft11
Wing C50344.62 sq m · 480 sq ft11
Wing C50444.62 sq m · 480 sq ft11
Wing C50564.87 sq m · 698 sq ft11
Wing C50666.03 sq m · 711 sq ft11
Wing C60165.31 sq m · 703 sq ft11
Wing C60244.62 sq m · 480 sq ft11
Wing C60344.62 sq m · 480 sq ft11
Wing C60444.62 sq m · 480 sq ft11
Wing C60564.87 sq m · 698 sq ft11
Wing C60666.03 sq m · 711 sq ft11

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals5

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectShivanand Swami Shivanand Swami—
Chartered accountantAmol C Datar And Associates—
EngineerAijaj Sikandar Nadaf—
EngineerGanesh Wankhede—
OtherSupekar—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Bhukum

All 21 projects in Bhukum · Compare Asmi Pride with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology