Deedo IDDL-AUR-AURANGABAD6 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
6 in 10 registrations run late here
1,507 MahaRERA registrations in Aurangabad and the places within it
181 completed143 not yet due265 extended, not yet due621 past even the latest date297 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Aurangabad
1,480 projects registered with MahaRERA in this district and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Morya Residency - 1Morya Builders | Due Jul 2027, extended 4 mo | — | — |
| Wadkar NakshatraLaxmiraman Mahantappa Wadkar | Due Jul 2030, extended 4 mo | — | — |
| Shivamrut ResidencyBalu Punjaram Agale | Due Dec 2032 | — | — |
| Vivaan ElitesBCD Reality | Due Dec 2030 | — | — |
| Adinath HeightsThe Oriens Corporation | Due Dec 2029 | — | — |
| Omkara City -02Shankara Builders | Due Oct 2029 | — | — |
| Construction of 1056 EWS Tenements on Gut No 9 Part at Nakshtrawadi, Chhatrapati SambhajinagarAurangabad Housing And Area Development Board ( A Regional Unit Of MHADA) | Due Mar 2029 | — | — |
| Krushnakunj Business HubKvg Builders | Due Dec 2030 | — | — |
| Aradhya ResidencyAdiyogi Constructions | Due Dec 2029 | — | — |
| PMAY U Tisgaon 225 BSahakar JV | Due Apr 2031, extended 5 yrs 4 mo | — | — |
| Vithai Residency Phase IShrinivasa Infra | Due Dec 2029 | — | — |
| PMAY U TisgaonUnity Developers | 11 mo late | — | — |
| PMAY U Tisgaon 225 ASahakar JV | 11 mo late | — | — |
| PMAY U Sundarwadi 9Aurathrone Infra | 11 mo late | — | — |
| A V TowersAarav Construction And Developers | Due Apr 2030, extended 4 mo | — | — |
| Bhumi Aditi VastuVvg Landmarks Private Limited | Due Jul 2028, extended 4 mo | — | — |
| Onkar Aakar ValleyAakar Construction | Due Apr 2028, extended 4 mo | — | — |
| PMAY U Sundarwadi 10Aurathrone Infra | Due Apr 2031, extended 4 mo | — | — |
| Shilp Gaurav HeightsShilp Constructions | Due Apr 2028, extended 4 mo | — | — |
| PMAY U PadegaonLaxmi JV | Due Apr 2031, extended 4 mo | — | — |
| Navkar WoodsNavkar Enterprises | Due Jul 2029, extended 4 mo | — | — |
| Arti ApartmentShriraj Labh Developers | Due Apr 2030, extended 4 mo | — | — |
| Swami PushpDilip Ramchandra Dandekar | 11 mo late | — | — |
| Bhumiraaj AvenueKakde Ventures | Due Apr 2028, extended 4 mo | — | — |
| Sara Saphire Ph - IApex Properties | Due Apr 2031, extended 4 mo | — | — |
Localities in Aurangabad
- Aurangabad (M Corp.)513 projects
- Aurangabad192 projects
- Tisgaon93 projects
- Satara (Ct)61 projects
- Itkheda38 projects
- Pisadevi35 projects
- Devlai31 projects
- Garkheda31 projects
- Chikalthana25 projects
- Sawangi22 projects
- Shendra Kamangar21 projects
- Aurangabad (Cb)20 projects
All 80 localities
- Nakshatrawadi19
- Wadgaon Kolhati (Ct)19
- Golwadi17
- Sundarwadi15
- Hirapur14
- Kubhephal14
- Harsool12
- Gangapur Jahagir11
- Balapur9
- Gangapur7
- Shendraban7
- Wadgaon Kh.7
- Bidkin6
- Karmad6
- Paithan (M Cl)6
- Sillod (M Cl)6
- Ashrafpur5
- Gandheli5
- Fattepur4
- Kannad4
- Kannad4
- Shahanur Wadi4
- Gangapur3
- Georai3
- Paithan3
- Palshi3
- Shioor3
- Sulibhanjan3
- Apatgaon2
- Babhulgaon2
- Nanakwadi2
- Ohar2
- Satara Tanda2
- Sawangi2
- Sillod2
- Tuljapur2
- Vaijapur (M Cl)2
- Waluj Bk. (Ct)2
- Warud2
- Zalta2
- Aghur1
- Andheri1
- Bendewadi1
- Chartha1
- Farola1
- Gangapur (M Cl)1
- Georai Tanda1
- Ghanegaon1
- Jogeshwari1
- Jyoti Nagar1
- Kamlapur1
- Kanchanwadi1
- Karodi1
- Khultabad1
- Ladgaon1
- Nagar Tisgaon1
- Naigaon1
- Narayanpur Kh.1
- Nilajgaon1
- Others1
- Paithan Kheda1
- Pokhari1
- Pune (M Corp.)1
- Ranjangaon (S) (Ct)1
- Rotegaon1
- Shahajapur1
- Soygaon1
- Usmanpura1
Other districts
Most active promoters
- Sajansing Motilal Jarwal11 projects
- Simar Pride Ventures Llp10 projects
- Vikas Laxman Chaudhary10 projects
- Sajansing Motilal Jarwal9 projects
- Bhuvi Landmarks Llp8 projects
- Arch Developers7 projects
- Sara Infrastructures7 projects
- Jagrut Sara Associates6 projects
- Nabhraj Builders And Developers Pvt Ltd6 projects
- Sakshi Builders6 projects
Aurangabad, in questions
How many projects in Aurangabad run late?
6 in 10 MahaRERA registrations (886 of 1,507): their completion date was extended or has passed, data through 20 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Aurangabad by Deedo. Medians on fewer than 3 deeds are not shown.