6 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects1,480in 80 localities
Registrations1,507some projects hold several
Completion still due421789 past their date
Median extension4 months31% of registrations extended
Regulatory cases122on 114 projects

6 in 10 registrations run late here

1,507 MahaRERA registrations in Aurangabad and the places within it

181 completed143 not yet due265 extended, not yet due621 past even the latest date297 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Aurangabad

1,480 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Morya Residency - 1Morya BuildersDue Jul 2027, extended 4 mo——
Wadkar NakshatraLaxmiraman Mahantappa WadkarDue Jul 2030, extended 4 mo——
Shivamrut ResidencyBalu Punjaram AgaleDue Dec 2032——
Vivaan ElitesBCD RealityDue Dec 2030——
Adinath HeightsThe Oriens CorporationDue Dec 2029——
Omkara City -02Shankara BuildersDue Oct 2029——
Construction of 1056 EWS Tenements on Gut No 9 Part at Nakshtrawadi, Chhatrapati SambhajinagarAurangabad Housing And Area Development Board ( A Regional Unit Of MHADA)Due Mar 2029——
Krushnakunj Business HubKvg BuildersDue Dec 2030——
Aradhya ResidencyAdiyogi ConstructionsDue Dec 2029——
PMAY U Tisgaon 225 BSahakar JVDue Apr 2031, extended 5 yrs 4 mo——
Vithai Residency Phase IShrinivasa InfraDue Dec 2029——
PMAY U TisgaonUnity Developers11 mo late——
PMAY U Tisgaon 225 ASahakar JV11 mo late——
PMAY U Sundarwadi 9Aurathrone Infra11 mo late——
A V TowersAarav Construction And DevelopersDue Apr 2030, extended 4 mo——
Bhumi Aditi VastuVvg Landmarks Private LimitedDue Jul 2028, extended 4 mo——
Onkar Aakar ValleyAakar ConstructionDue Apr 2028, extended 4 mo——
PMAY U Sundarwadi 10Aurathrone InfraDue Apr 2031, extended 4 mo——
Shilp Gaurav HeightsShilp ConstructionsDue Apr 2028, extended 4 mo——
PMAY U PadegaonLaxmi JVDue Apr 2031, extended 4 mo——
Navkar WoodsNavkar EnterprisesDue Jul 2029, extended 4 mo——
Arti ApartmentShriraj Labh DevelopersDue Apr 2030, extended 4 mo——
Swami PushpDilip Ramchandra Dandekar11 mo late——
Bhumiraaj AvenueKakde VenturesDue Apr 2028, extended 4 mo——
Sara Saphire Ph - IApex PropertiesDue Apr 2031, extended 4 mo——
Aurangabad market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Sajansing Motilal Jarwal11 projects
  2. Simar Pride Ventures Llp10 projects
  3. Vikas Laxman Chaudhary10 projects
  4. Sajansing Motilal Jarwal9 projects
  5. Bhuvi Landmarks Llp8 projects
  6. Arch Developers7 projects
  7. Sara Infrastructures7 projects
  8. Jagrut Sara Associates6 projects
  9. Nabhraj Builders And Developers Pvt Ltd6 projects
  10. Sakshi Builders6 projects

Aurangabad, in questions

How many projects in Aurangabad run late?

6 in 10 MahaRERA registrations (886 of 1,507): their completion date was extended or has passed, data through 20 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Aurangabad by Deedo. Medians on fewer than 3 deeds are not shown.

Data through20 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology