Shioor, Aurangabad
3 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects3
Registrations3
Completion still due21 past their date
Median extension4 months33% of registrations extended
Regulatory cases0none on MahaRERA's lists
7 in 10 registrations run late here
3 MahaRERA registrations in Shioor
1 not yet due1 extended, not yet due1 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Shioor
3 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Venugopal ParkYashwant Mukund Kharote | Due Mar 2030 | — | — |
| Ryans Residency Nx - 81Gautam Kachardas Sancheti (Huf) | Due Jul 2027, extended 4 mo | — | 33% |
| Ryans ResidencyG K Sancheti (Huf) | 3 mo late | — | 0% |
Nearby: other localities in Aurangabad
Most active promoters
- Gautam Kachardas Sancheti (Huf)1 project
- G K Sancheti (Huf)1 project
- Yashwant Mukund Kharote1 project
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology