RERA projects in Rotegaon

1 project under 1 MahaRERA registration, registered 2017–2017. 100% have a completion date extended beyond the one promised.

Locality
1RERA projects
1Registrations
0Completion still due1 past their completion date
18 monthsMedian extension beyond promised date100% of registrations extended
0Regulatory casesnone on MahaRERA's lists
5Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20171

Projects in Rotegaon

1 project registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Sara Samruddhi - Phase 1Sara PropertiesP5150001378325 Oct 201731 Mar 201930 Sep 2020Extended 18 mo0

Other localities in Aurangabad

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Sara Properties1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology