11 projects under 11 MahaRERA registrations, registered 2017–2023. 9% have a completion date extended beyond the one promised.

11RERA projects
11Registrations
2Completion still due9 past their completion date, 2 marked completed
45 monthsMedian extension beyond promised date9% of registrations extended
0Regulatory casesnone on MahaRERA's lists
19Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20173
20181
20192
20201
20211
20221
20232

Projects in Gangapur Jahagir

11 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Auric HomesAshok BahetiP515000499856 Mar 202331 Dec 2027—Not yet due0
Sara Angan Phase-1 A1 -B1 Type BuildingSara InfrastructuresP515000491873 Feb 202331 Dec 2025—Promised date passed0
Sara Angan B2, B3, C1 And C2 Type BuildingSara InfrastructuresP515000328852 Feb 202231 Mar 202331 Dec 2026Extended 45 mo0
Heera CityAgrawal InfraP515000284072 Mar 202128 Aug 2024—Promised date passed0
Akshad Super City Phase- IIVansh InfrastructureP5150002725928 Nov 202013 Apr 2025—Completed0
Shree Sai VrundavanR D Choudhari Builders And DevelopersP5150002003619 Mar 201930 Dec 2022—Promised date passed0
Sara Swapnangan Phase-2, H-1, H-2 And G Type Row HouseSara InfrastructuresP515000195368 Feb 201930 Oct 2021—Promised date passed0
Akshad Super City Phase 1Vansh InfrastructureP515000151977 Feb 201819 Feb 2022—Promised date passed0
Sara Swapnangan - Row HousesSara InfrastructuresP5150000194417 Nov 201731 Dec 2017—Promised date passed0
Akshad PuramVansh BuildconP5150000785318 Aug 201730 Nov 2018—Promised date passed0
Sara Swapnangan - A4, A5, A6 BuildingsSara InfrastructuresP5150000136327 Jul 201731 Dec 2018—Completed0

Other localities in Aurangabad

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Sara Infrastructures5 projects
  2. Vansh Infrastructure2 projects
  3. Agrawal Infra1 project
  4. Ashok Baheti1 project
  5. R D Choudhari Builders And Developers1 project
  6. Vansh Buildcon1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology