RERA projects in Sundarwadi
14 projects under 15 MahaRERA registrations, registered 2017–2025. 53% have a completion date extended beyond the one promised.
Locality
14RERA projects
15Registrationssome projects hold several
6Completion still due9 past their completion date
4 monthsMedian extension beyond promised date53% of registrations extended
0Regulatory casesnone on MahaRERA's lists
111Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 4 |
| 2018 | 0 |
| 2019 | 3 |
| 2020 | 0 |
| 2021 | 0 |
| 2022 | 2 |
| 2023 | 2 |
| 2024 | 1 |
| 2025 | 3 |
Projects in Sundarwadi
14 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| PMAY U Sundarwadi 9Aurathrone Infra | P51500079904 | 29 Mar 2025 | 31 Dec 2025 | — | Promised date passed | 0 |
| PMAY U Sundarwadi 10Aurathrone Infra | P51500079887 | 28 Mar 2025 | 31 Dec 2030 | 30 Apr 2031 | Extended 4 mo | 0 |
| Ideal ResidencyIsraruddin Mukhtaruddin Shaikh | P51500078718 | 7 Jan 2025 | 15 Aug 2026 | 15 Dec 2026 | Extended 4 mo | 0 |
| Raje ResidencyRaje Developers | P51500077175 | 29 Jul 2024 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Krushna UltimaPrachiti Developers | P51500053860 | 5 Dec 2023 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
| 55 HappynestRupesh Prakashchand Mutha | P51500052128 | 24 Jul 2023 | 30 Jun 2026 | — | Promised date passed | 0 |
| Rushikesh VillaMalode Builders & Developers | P51500047762 | 28 Nov 2022 | 31 Mar 2025 | 31 Mar 2025 | Promised date passed | 0 |
| Radha Krushna VillaSainaath Builders And Developers | P51500021253, P51500033700 | 14 Jun 2019 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
| Prasanna Suyash TowerPrasana Suyash Builders And Developers | P51500020025 | 19 Mar 2019 | 30 Dec 2021 | 30 Dec 2022 | Extended 12 mo | 0 |
| Prasanna Plan 8 Gold CityS S Builders And Developers | P51500019307 | 23 Jan 2019 | 31 Dec 2019 | 31 Dec 2019 | Promised date passed | 0 |
| SAINATHVILLA Phase IISainath Builders & Developers | P51500011537 | 31 Aug 2017 | 31 May 2018 | 31 May 2018 | Promised date passed | 0 |
| Sai BanBKT Group | P51500010316 | 24 Aug 2017 | 30 Sep 2018 | 31 Mar 2025 | Extended 78 mo | 0 |
| Dhruv GokuldhamDhruv Buildcon | P51500007864 | 18 Aug 2017 | 30 Dec 2023 | 29 Dec 2024 | Extended 12 mo | 0 |
| Prasanna SuyashPrasana Suyash Builders And Developers | P51500007449 | 17 Aug 2017 | 31 Dec 2018 | 31 Dec 2018 | Promised date passed | 0 |
Other localities in Aurangabad
Most active promoters
By projects registered here, as named on MahaRERA.
- Aurathrone Infra2 projects
- Prasana Suyash Builders And Developers2 projects
- BKT Group1 project
- Dhruv Buildcon1 project
- Israruddin Mukhtaruddin Shaikh1 project
- Malode Builders & Developers1 project
- Prachiti Developers1 project
- Raje Developers1 project
- Rupesh Prakashchand Mutha1 project
- Sainaath Builders And Developers1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology