RERA projects in Sawangi
16 projects under 16 MahaRERA registrations, registered 2017–2026. 13% have a completion date extended beyond the one promised.
Locality
16RERA projects
16Registrations
8Completion still due8 past their completion date, 1 marked completed
12 monthsMedian extension beyond promised date13% of registrations extended
0Regulatory casesnone on MahaRERA's lists
35Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 2 |
| 2018 | 1 |
| 2019 | 1 |
| 2020 | 1 |
| 2021 | 3 |
| 2022 | 1 |
| 2023 | 2 |
| 2024 | 1 |
| 2025 | 3 |
| 2026 | 1 |
Projects in Sawangi
16 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Sawangi City Phase-2Aryaman Infra | PR1040002600927 | 24 Jun 2026 | 31 Mar 2031 | — | Not yet due | 0 |
| Samruddhi TowerSamruddhi Infra | PM1040002500301 | 17 Jul 2025 | 31 Dec 2029 | — | Not yet due | 0 |
| Jagdale ResidencyVaibhav Arun Jagdale | P51500080757 | 3 Jul 2025 | 31 Dec 2028 | — | Not yet due | 0 |
| PushpanagariShreechatrapati Developers | P51500079119 | 6 Feb 2025 | 31 Dec 2028 | — | Not yet due | 0 |
| Dwarka ParkVenkatesh Land Developers | P51500076705 | 21 Jun 2024 | 31 Oct 2028 | — | Not yet due | 0 |
| Sawangi CityJayesh Infra | P51500050204 | 21 Mar 2023 | 31 Dec 2027 | — | Not yet due | 0 |
| Dar-Ul-AmanSquare-A Develpoers LLP | P51500050046 | 6 Mar 2023 | 15 Dec 2026 | — | Not yet due | 0 |
| Sara Parivartan-Amenity Building-ASara Properties | P51500034773 | 28 Apr 2022 | 31 Dec 2024 | — | Promised date passed | 0 |
| Madhura Sai SamrudhiLandmark Infra | P51500031625 | 3 Nov 2021 | 31 Mar 2025 | — | Promised date passed | 0 |
| SARA PARIVARTAN G - 12, 13, 14 type buildingSara Properties | P51500029499 | 4 Jun 2021 | 31 Mar 2023 | 30 Mar 2024 | Extended 12 mo | 0 |
| Siddhi Vinayak ParkEkdant Construction | P51500028159 | 10 Feb 2021 | 30 Jun 2024 | — | Promised date passed | 0 |
| Darussalam Harmony HomeAster Infra | P51500024404 | 11 Feb 2020 | 27 Jan 2027 | — | Not yet due | 0 |
| Krushnasundar Residency Phase 2Sanjay Baliram Jadhav | P51500022196 | 5 Sep 2019 | 28 Aug 2022 | — | Promised date passed | 0 |
| Sara Parivartan Sector B - Ph 2Sara Properties | P51500016122 | 17 Apr 2018 | 21 Apr 2022 | 20 Apr 2023 | Extended 12 mo | 0 |
| Sara Parivartan - Sector EJagrutsara Structures LLP | P51500001935 | 29 Jul 2017 | 31 Dec 2017 | — | Promised date passed | 0 |
| Sara Parivartan - Sector B - Phase 1Sara Properties | P51500001468 | 28 Jul 2017 | 15 Aug 2019 | — | Completed | 0 |
Other localities in Aurangabad
- Aurangabad (M Corp.)614 projects
- Tisgaon87 projects
- Satara (Ct)61 projects
- Pisadevi32 projects
- Devlai29 projects
- Shendra Kamangar21 projects
- Aurangabad (Cb)20 projects
- Wadgaon Kolhati (Ct)19 projects
- Golwadi14 projects
- Kubhephal14 projects
- Sundarwadi14 projects
- Gangapur Jahagir11 projects
Most active promoters
By projects registered here, as named on MahaRERA.
- Sara Properties4 projects
- Aryaman Infra1 project
- Aster Infra1 project
- Ekdant Construction1 project
- Jagrutsara Structures LLP1 project
- Jayesh Infra1 project
- Landmark Infra1 project
- Samruddhi Infra1 project
- Sanjay Baliram Jadhav1 project
- Shreechatrapati Developers1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology