RERA projects in Satara (Ct)
61 projects under 63 MahaRERA registrations, registered 2017–2026. 14% have a completion date extended beyond the one promised.
61RERA projects
63Registrationssome projects hold several
21Completion still due42 past their completion date, 12 marked completed
18 monthsMedian extension beyond promised date14% of registrations extended
4Regulatory caseson 4 projects
41Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 12 |
| 2018 | 5 |
| 2019 | 4 |
| 2020 | 4 |
| 2021 | 8 |
| 2022 | 9 |
| 2023 | 9 |
| 2024 | 4 |
| 2025 | 4 |
| 2026 | 4 |
Projects in Satara (Ct)
61 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Shlok Tirupati Park Phase 1Shlok Realities | PM1040002601255 | 20 Jul 2026 | 31 Dec 2029 | — | Not yet due | 0 |
| Mahalaxmi Saubhagya 3Moreshwar Ramchandra Kulkarni | PR1040002502931 | 18 Mar 2026 | 31 Dec 2032 | — | Not yet due | 0 |
| KirtibanPiyush Infratech Private Limited | PR1040002502677 | 9 Mar 2026 | 28 Aug 2030 | — | Not yet due | 0 |
| Durga HeightsVarad Developers | PM1040002502584 | 4 Mar 2026 | 31 Mar 2028 | — | Not yet due | 0 |
| Malhar ApartmentMukund Govindrao Kulkarni | PR1040002500753 | 11 Sep 2025 | 31 Dec 2028 | — | Not yet due | 0 |
| Swami PushpDilip Ramchandra Dandekar | P51500079628 | 17 Mar 2025 | 31 Dec 2025 | — | Promised date passed | 0 |
| Pukharaj ResidencyPukhraj Builders And Developers | P51500079269 | 25 Feb 2025 | 28 Feb 2027 | — | Not yet due | 0 |
| Brahma ParkPanchshil Developers | P51500078792 | 13 Jan 2025 | 31 Dec 2029 | — | Not yet due | 0 |
| P-9 VillasPrem Infrastructures | P51500078512 | 19 Dec 2024 | 21 Mar 2028 | — | Not yet due | 0 |
| Belpatra VillasSandesh Bhivsan Wagh | P51500066511 | 11 Jun 2024 | 31 Dec 2026 | — | Not yet due | 0 |
| Signature 27Jagrutsara Realtors LLP | P51500054759 | 12 Feb 2024 | 31 Dec 2028 | — | Completed | 0 |
| Saee Residency Phase IIISaee Infra | P51500054628 | 2 Feb 2024 | 31 Oct 2025 | — | Promised date passed | 0 |
| AnukulRiddhi Viyaan Ventures | P51500052898 | 5 Oct 2023 | 31 Mar 2027 | — | Not yet due | 0 |
| Govind ResidencyGovind Infra | P51500051612 | 27 Jun 2023 | 31 Dec 2027 | — | Not yet due | 0 |
| Govind ResidencyGovind Developer | P51500051451 | 23 Jun 2023 | 31 Dec 2027 | — | Not yet due | 0 |
| Ishanya HeightsVivaan Infra | P51500051507 | 23 Jun 2023 | 25 Oct 2025 | — | Promised date passed | 0 |
| Chintamani Hill View IIVrushabh Builders | P51500051154 | 1 Jun 2023 | 31 Dec 2026 | — | Not yet due | 0 |
| Sai Kamal ResidencyShree Ganesha Builders & Developers | P51500051091 | 29 May 2023 | 2 Dec 2024 | 1 Oct 2025 | Extended 10 mo | 0 |
| Aryan HillsVa Developers | P51500050782 | 3 May 2023 | 19 Feb 2025 | 19 Feb 2026 | Extended 12 mo | 0 |
| Samruddhi ParkLandmark Developers | P51500050745 | 28 Apr 2023 | 31 Dec 2024 | — | Completed | 1 |
| Chandramouli Pinnacle 2Chandramouli Properties | P51500048481 | 3 Jan 2023 | 1 Dec 2026 | — | Not yet due | 0 |
| Saffron LandmarksSaffron Associates | P51500048247 | 22 Dec 2022 | 30 Jun 2027 | — | Not yet due | 0 |
| HorizonSunita Prakashrao Hiwarale | P51500047915 | 1 Dec 2022 | 21 Jul 2026 | — | Promised date passed | 0 |
| Renuka HeightsManish Sheshrao Patil | P51500047909 | 1 Dec 2022 | 31 Dec 2023 | 30 Dec 2024 | Completed | 0 |
| Balaji SolastaCreative Group | P51500047134 | 10 Oct 2022 | 31 Mar 2027 | — | Not yet due | 0 |
| JD VillasJD Villas | P51500034527 | 11 Apr 2022 | 11 May 2022 | — | Promised date passed | 0 |
| Orchid TowersSavali Constructions | P51500033091 | 3 Feb 2022 | 30 Dec 2023 | — | Promised date passed | 0 |
| Gaia Carnival ApartmentZambad Disha Pride Infrastructure LLP | P51500032777, P51500032793 | 29 Jan 2022 | 31 Dec 2028 | — | Not yet due | 0 |
| Viyaan AnantaRiddhi Viyaan Ventures | P51500032300, P51500035035 | 29 Dec 2021 | 31 Mar 2027 | — | Not yet due | 1 |
| Gulmohar Park BGovind Tikaram Chavan And Teajas Govind Chavan | P51500031972 | 29 Nov 2021 | 30 Dec 2023 | — | Promised date passed | 1 |
| Ajinkya ApartmentArihant Enterprises | P51500031801 | 12 Nov 2021 | 31 Mar 2023 | — | Completed | 0 |
| Jay-Shankar TowerSandesh Bhivsan Wagh | P51500031303 | 15 Oct 2021 | 31 Mar 2024 | — | Promised date passed | 0 |
| Saffron Landscape Phase ISaffron Associates | P51500031063 | 5 Oct 2021 | 31 Dec 2026 | — | Not yet due | 0 |
| Gaia Carnival - Row HousesZambad Disha Pride Infrastructure LLP | P51500030703 | 8 Sep 2021 | 31 Dec 2024 | — | Promised date passed | 0 |
| Suryakunj ResidencyGhuge Infrastructure | P51500030654 | 8 Sep 2021 | 31 Mar 2026 | — | Promised date passed | 0 |
| Deogiri PlazaAgraganya Buildcon | P51500027859 | 10 Jan 2021 | 30 Jun 2025 | — | Completed | 0 |
| K P HeritageNavkar Construction | P51500027076 | 13 Nov 2020 | 1 May 2025 | — | Promised date passed | 0 |
| Mahalaxmi SaubhagyaAmruta Swapnil Kulkarni | P51500025445 | 30 May 2020 | 30 Jun 2026 | — | Promised date passed | 0 |
| Sai Sagar AppartmentV K Builders And Developers | P51500025303 | 5 Apr 2020 | 30 Mar 2022 | — | Completed | 0 |
| Anand ParkSaim Saleem Siddiqui , Shaikh Mujtaba Maaz And Shaikh Rameez Ahmed | P51500024935 | 12 Mar 2020 | 30 Mar 2022 | — | Completed | 0 |
| Shri Samarth HeightsAshoka Constructions | P51500021059 | 31 May 2019 | 15 May 2023 | — | Promised date passed | 1 |
| Silver Oaks VillasNavkar Construction | P51500020485 | 15 Apr 2019 | 20 Apr 2022 | — | Completed | 0 |
| Shri Niwas ResidencyShrikant Anatrao Joshi | P51500020303 | 3 Apr 2019 | 30 Dec 2020 | — | Promised date passed | 0 |
| Shashwat KunjA B Infrastructure | P51500020231 | 29 Mar 2019 | 30 Sep 2022 | — | Promised date passed | 0 |
| Silver EstateVishnuprasad Babulalji Karwa | P51500018889 | 10 Dec 2018 | 30 Oct 2021 | — | Completed | 0 |
| anjaneri heightsSakhare Patil Builders And Developers | P51500017879 | 24 Sep 2018 | 30 Dec 2023 | — | Promised date passed | 0 |
| Hrim Ssky City Phase IVAshok Baheti | P51500016766 | 12 Jun 2018 | 28 Apr 2023 | 31 Dec 2027 | Extended 56 mo | 0 |
| Nath TowerD N Developers | P51500016638 | 5 Jun 2018 | 31 Dec 2019 | — | Completed | 0 |
| Navkar HeightsNavkar Construction | P51500015988 | 11 Apr 2018 | 9 Nov 2022 | — | Promised date passed | 0 |
| Omkar ResidencyS N Builders And Developers | P51500013640 | 16 Oct 2017 | 30 Sep 2020 | — | Promised date passed | 0 |
| Renuka CottageChetan Hiralal Sharma | P51500013490 | 7 Oct 2017 | 31 Dec 2017 | — | Promised date passed | 0 |
| Fortune ParkArihant Ventures | P51500010032 | 23 Aug 2017 | 10 Oct 2021 | 9 Apr 2023 | Extended 18 mo | 0 |
| Green Space Residency (Project-1) A BuildingMarathwada Constructions Pvt Ltd | P51500009980 | 23 Aug 2017 | 30 Jun 2023 | 29 Jun 2024 | Extended 12 mo | 0 |
| Biz SquareSam Realties | P51500008228 | 18 Aug 2017 | 31 Dec 2019 | 30 Apr 2025 | Completed | 0 |
| Manomay ResidencyGayatri Developers | P51500008163 | 18 Aug 2017 | 30 Dec 2021 | — | Completed | 0 |
| Om PlatinaPunjab Shivajirao Taur | P51500007102 | 17 Aug 2017 | 31 Dec 2019 | 30 Dec 2021 | Extended 24 mo | 0 |
| Adinath SuvastuAdinath Developers | P51500005255 | 11 Aug 2017 | 31 Dec 2019 | — | Promised date passed | 0 |
| Raghu-Narayana ResidencyD.s Developers & Builders | P51500004562 | 9 Aug 2017 | 31 Jul 2023 | — | Promised date passed | 0 |
| Blue OasisKarimkhan Mohidinkhan Pathan | P51500002808 | 4 Aug 2017 | 18 May 2018 | 9 Jun 2023 | Extended 61 mo | 0 |
| Tirumala RoyalTirumala Builders | P51500002622 | 2 Aug 2017 | 31 Jan 2021 | — | Promised date passed | 0 |
| Disha Vinayak Phase 1Dnk Combines | P51500002345 | 31 Jul 2017 | 31 Mar 2019 | — | Promised date passed | 0 |
Other localities in Aurangabad
- Aurangabad (M Corp.)614 projects
- Tisgaon87 projects
- Pisadevi32 projects
- Devlai29 projects
- Shendra Kamangar21 projects
- Aurangabad (Cb)20 projects
- Wadgaon Kolhati (Ct)19 projects
- Sawangi16 projects
- Golwadi14 projects
- Kubhephal14 projects
- Sundarwadi14 projects
- Gangapur Jahagir11 projects
Most active promoters
By projects registered here, as named on MahaRERA.
- Navkar Construction3 projects
- Riddhi Viyaan Ventures2 projects
- Saffron Associates2 projects
- Sandesh Bhivsan Wagh2 projects
- Zambad Disha Pride Infrastructure LLP2 projects
- A B Infrastructure1 project
- Adinath Developers1 project
- Agraganya Buildcon1 project
- Amruta Swapnil Kulkarni1 project
- Arihant Enterprises1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology