Nakshatrawadi, Aurangabad
Deedo IDDL-AUR-NAKSHATRAWADI8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects19
Registrations21some projects hold several
Completion still due714 past their date
Median extension12 months43% of registrations extended
Regulatory cases0none on MahaRERA's lists
8 in 10 registrations run late here
21 MahaRERA registrations in Nakshatrawadi
3 completed1 not yet due5 extended, not yet due12 past even the latest date
Extended registrations moved their completion date by a median of 12 months.
Projects in Nakshatrawadi
19 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Shri Samarth ViharShri Samarth Developers | Due Mar 2031 | — | — |
| Venkatesh HaripriyaBhagyoday Builders | Due Aug 2027, extended 4 mo | — | — |
| Tuljai ParkTuljai Developers | Due Apr 2029, extended 4 mo | — | — |
| Nakshtrangan AnuradhaMalkhare Builders And Developers Pvt Ltd | Completed, extended 4 mo | — | — |
| Sai Residency AnnexNakshatra Enterprises | Completed | — | — |
Nearby: other villages in Aurangabad
Aurangabad (M Corp.) · 513 projectsTisgaon · 93 projectsSatara (Ct) · 61 projectsItkheda · 38 projectsPisadevi · 35 projectsDevlai · 31 projectsGarkheda · 31 projectsChikalthana · 25 projectsSawangi · 22 projectsShendra Kamangar · 21 projectsAurangabad (Cb) · 20 projectsWadgaon Kolhati (Ct) · 19 projects
Most active promoters
- Inspira Realty Llp2 projects
- Aakash Ganga Developers1 project
- Amit Bhaskarrao Sanap And Anirudha Dineshchandra Somani1 project
- Arihant Enterprises1 project
- Ashish Ashok Kawde1 project
- Aurangabad Housing And Area Development Board ( A Regional Unit Of Mhada)1 project
- Bhagyoday Builders1 project
- Deven Realties Llp1 project
- Dnk Vastu Nirman1 project
- Malkhare Builders And Developers Pvt Ltd1 project
Nakshatrawadi, in questions
How many projects in Nakshatrawadi run late?
8 in 10 MahaRERA registrations (17 of 21): their completion date was extended or has passed, data through 21 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nakshatrawadi by Deedo. Medians on fewer than 3 deeds are not shown.
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology