8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects19
Registrations21some projects hold several
Completion still due714 past their date
Median extension12 months43% of registrations extended
Regulatory cases0none on MahaRERA's lists

8 in 10 registrations run late here

21 MahaRERA registrations in Nakshatrawadi

3 completed1 not yet due5 extended, not yet due12 past even the latest date

Extended registrations moved their completion date by a median of 12 months.

Projects in Nakshatrawadi

19 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Shri Samarth ViharShri Samarth DevelopersDue Mar 2031——
Venkatesh HaripriyaBhagyoday BuildersDue Aug 2027, extended 4 mo——
Tuljai ParkTuljai DevelopersDue Apr 2029, extended 4 mo——
Nakshtrangan AnuradhaMalkhare Builders And Developers Pvt LtdCompleted, extended 4 mo——
Sai Residency AnnexNakshatra EnterprisesCompleted——
All 19 projects →
Nakshatrawadi market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Inspira Realty Llp2 projects
  2. Aakash Ganga Developers1 project
  3. Amit Bhaskarrao Sanap And Anirudha Dineshchandra Somani1 project
  4. Arihant Enterprises1 project
  5. Ashish Ashok Kawde1 project
  6. Aurangabad Housing And Area Development Board ( A Regional Unit Of Mhada)1 project
  7. Bhagyoday Builders1 project
  8. Deven Realties Llp1 project
  9. Dnk Vastu Nirman1 project
  10. Malkhare Builders And Developers Pvt Ltd1 project

Nakshatrawadi, in questions

How many projects in Nakshatrawadi run late?

8 in 10 MahaRERA registrations (17 of 21): their completion date was extended or has passed, data through 21 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nakshatrawadi by Deedo. Medians on fewer than 3 deeds are not shown.

Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology