9 projects under 9 MahaRERA registrations, registered 2017–2026. 11% have a completion date extended beyond the one promised.
Locality
9RERA projects
9Registrations
4Completion still due5 past their completion date, 1 marked completed
60 monthsMedian extension beyond promised date11% of registrations extended
0Regulatory casesnone on MahaRERA's lists
2Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 1 |
| 2018 | 1 |
| 2019 | 1 |
| 2020 | 0 |
| 2021 | 0 |
| 2022 | 3 |
| 2023 | 1 |
| 2024 | 0 |
| 2025 | 1 |
| 2026 | 1 |
Projects in Garkheda
9 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Khinvasara August HighStreet MarketChampalal Kanhaiyalal Khinvasara | PC1041012600056 | 9 Apr 2026 | 31 Dec 2031 | — | Not yet due | 0 |
| Bhumiraaj AvenueKakde Ventures | P51500079507 | 10 Mar 2025 | 31 Dec 2027 | — | Not yet due | 0 |
| Ambika ApartmentMukund Govindrao Kulkarni | P51500048648 | 10 Jan 2023 | 31 Dec 2025 | — | Promised date passed | 0 |
| Renuka PrideParth Developers | P51500047868 | 1 Dec 2022 | 30 Sep 2025 | — | Promised date passed | 0 |
| Sadguru ResidencyTechnobuilds | P51500034224 | 25 Mar 2022 | 31 Oct 2023 | — | Promised date passed | 0 |
| Chintamani Highland SquareRrk Buildcon | P51500033939 | 14 Mar 2022 | 21 Feb 2028 | — | Not yet due | 0 |
| Tirumala Hill AppartmentMukund Govindrao Kulkarni | P51500022166 | 4 Sep 2019 | 30 Dec 2024 | — | Promised date passed | 0 |
| Riddhi Siddhi PlazaGopal Trilokchand Agrawal | P51500014798 | 2 Jan 2018 | 30 Dec 2017 | — | Completed | 0 |
| The AuraconAuracon Ventures | P51500011621 | 31 Aug 2017 | 30 Dec 2021 | 31 Dec 2026 | Extended 60 mo | 0 |
Other localities in Aurangabad
Most active promoters
By projects registered here, as named on MahaRERA.
- Mukund Govindrao Kulkarni2 projects
- Auracon Ventures1 project
- Champalal Kanhaiyalal Khinvasara1 project
- Gopal Trilokchand Agrawal1 project
- Kakde Ventures1 project
- Parth Developers1 project
- Rrk Buildcon1 project
- Technobuilds1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology