RERA projects in Pisadevi
32 projects under 33 MahaRERA registrations, registered 2017–2026. 12% have a completion date extended beyond the one promised.
32RERA projects
33Registrationssome projects hold several
22Completion still due11 past their completion date, 2 marked completed
18 monthsMedian extension beyond promised date12% of registrations extended
0Regulatory casesnone on MahaRERA's lists
39Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 2 |
| 2018 | 2 |
| 2019 | 2 |
| 2020 | 1 |
| 2021 | 4 |
| 2022 | 2 |
| 2023 | 7 |
| 2024 | 8 |
| 2025 | 4 |
| 2026 | 1 |
Projects in Pisadevi
32 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Madhura Angan Phase 2Madhura Ventures LLP | PM1040002601068 | 8 Jul 2026 | 31 Dec 2032 | — | Not yet due | 0 |
| Madhura AnganMadhura Estate | PR1040002500545 | 11 Aug 2025 | 31 Dec 2031 | — | Not yet due | 0 |
| Vithai Residency Phase IShrinivasa Infra | P51500079973 | 9 Apr 2025 | 31 Dec 2029 | — | Not yet due | 0 |
| Devansh ParkAmol Fakirchand Kale | P51500078923 | 21 Jan 2025 | 31 Dec 2029 | — | Not yet due | 0 |
| Shantai ResidencyShree Ganesha Group | P51500078089 | 25 Nov 2024 | 31 Dec 2029 | — | Not yet due | 0 |
| Rutuja ResidencyRutuja Developers | P51500077524 | 20 Aug 2024 | 31 Dec 2030 | — | Not yet due | 0 |
| Omkara City-01Kartik Builders | P51500076584 | 18 Jun 2024 | 31 Dec 2027 | — | Not yet due | 0 |
| Rukhmini ParkShree Balaji Infra | P51500076586 | 18 Jun 2024 | 31 Dec 2027 | — | Not yet due | 0 |
| Vyankatesh ParkVyankatesh Park | P51500055961 | 2 May 2024 | 28 Feb 2026 | — | Promised date passed | 0 |
| Shubharambh Residency Phase 1Sudip Infrastructure AOP | P51500055873 | 29 Apr 2024 | 31 Dec 2028 | — | Not yet due | 0 |
| Gokuldham ResidencyGokuldham Residency | P51500055530 | 2 Apr 2024 | 31 Dec 2028 | — | Not yet due | 0 |
| Samarth ParkSamarth Park | P51500055342 | 18 Mar 2024 | 31 Mar 2030 | — | Not yet due | 0 |
| Sahyadri Park Phase 2Sahyadri Builders & Developers | P51500053809 | 1 Dec 2023 | 31 Mar 2028 | — | Not yet due | 0 |
| Laxmi ParkOmraj Infra | P51500053734 | 28 Nov 2023 | 31 Mar 2027 | — | Not yet due | 0 |
| Sahyadri Park Phase 1Sahyadri Builders & Developers | P51500053593 | 10 Nov 2023 | 31 Dec 2027 | — | Not yet due | 0 |
| Bhavana Residency Phase IINew Trimurti Developers | P51500053426 | 31 Oct 2023 | 31 Dec 2028 | — | Not yet due | 0 |
| Shri ParkShri Buildcon | P51500051351 | 8 Jun 2023 | 31 Dec 2025 | — | Promised date passed | 0 |
| Group Housing SchemeVakratund Developers | P51500051044 | 22 May 2023 | 31 Mar 2026 | — | Promised date passed | 0 |
| Tirumala ResidencyTirumala Residency | P51500051039 | 22 May 2023 | 31 Dec 2028 | — | Not yet due | 0 |
| Swastik TowersHari Om Developers | P51500047135 | 10 Oct 2022 | 31 Aug 2027 | — | Not yet due | 0 |
| Vighnaharta TowersVighnaharta Constrcutions | P51500033129 | 9 Feb 2022 | 31 Dec 2025 | — | Promised date passed | 0 |
| Shree Ram ResidencyBhaskar Ramanath Kale Prop Shree Ram Developers | P51500031971 | 29 Nov 2021 | 31 Dec 2026 | — | Not yet due | 0 |
| Seeta ParkLaxman Kondia Kale | P51500031373, P51500080978 | 23 Oct 2021 | 31 Dec 2030 | — | Not yet due | 0 |
| Kalyani Park Phase IIBharat Janardhan Kale | P51500029516 | 4 Jun 2021 | 1 Apr 2026 | — | Promised date passed | 0 |
| Samruddhi Residency 2Tejal Realty | P51500028391 | 23 Feb 2021 | 30 Jun 2027 | — | Not yet due | 0 |
| Yuvraj ResidencyYeshwant Vithalrao Tidke | P51500026163 | 25 Aug 2020 | 31 Jan 2023 | 31 Jan 2024 | Extended 12 mo | 0 |
| Vithu Mauli ParkShri Vithumauli Constructions Builders and Developers | P51500022833 | 30 Oct 2019 | 7 Oct 2024 | — | Promised date passed | 0 |
| Madhura ParkMadhura Land Developers | P51500021024 | 27 May 2019 | 25 Sep 2020 | — | Completed | 0 |
| Kisan ParkKalyanrao Kisanrao Autade | P51500018345 | 23 Oct 2018 | 30 Dec 2024 | 31 Dec 2026 | Extended 24 mo | 0 |
| Shree Krishna NagarVenubai Shahadev Tavle | P51500015253 | 8 Feb 2018 | 31 Dec 2019 | — | Promised date passed | 0 |
| Shrinath ParkShri Nath Vihar Constructions | P51500006059 | 14 Aug 2017 | 30 Dec 2021 | 29 Jun 2022 | Completed | 0 |
| Satyam ResidencyMahalaxmi builders and Developers | P51500004520 | 9 Aug 2017 | 31 Jul 2019 | 30 Jun 2022 | Extended 35 mo | 0 |
Other localities in Aurangabad
- Aurangabad (M Corp.)614 projects
- Tisgaon87 projects
- Satara (Ct)61 projects
- Devlai29 projects
- Shendra Kamangar21 projects
- Aurangabad (Cb)20 projects
- Wadgaon Kolhati (Ct)19 projects
- Sawangi16 projects
- Golwadi14 projects
- Kubhephal14 projects
- Sundarwadi14 projects
- Gangapur Jahagir11 projects
Most active promoters
By projects registered here, as named on MahaRERA.
- Sahyadri Builders & Developers2 projects
- Amol Fakirchand Kale1 project
- Bharat Janardhan Kale1 project
- Bhaskar Ramanath Kale Prop Shree Ram Developers1 project
- Gokuldham Residency1 project
- Hari Om Developers1 project
- Kalyanrao Kisanrao Autade1 project
- Kartik Builders1 project
- Laxman Kondia Kale1 project
- Madhura Estate1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology