7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects25
Registrations27some projects hold several
Completion still due1116 past their date
Median extension4 months30% of registrations extended
Regulatory cases0none on MahaRERA's lists

7 in 10 registrations run late here

27 MahaRERA registrations in Chikalthana

5 completed4 not yet due7 extended, not yet due11 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Chikalthana

25 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Ananda NilayamShreeja Builders And DevelopersDue Dec 2032——
Kasliwal NiwaraKasliwal NiwaraDue Dec 2032——
Shubhlabh HeritageBhaishree Realtors LLPDue May 2030, extended 4 mo——
Shri MahalaxmiVenubai Govind Dhotre Jijbai Govind Dhotre Deepak Babasaheb DhotreDue Jul 2029, extended 4 mo——
Sai ResidencyOm Sai DevelopersDue Apr 2032, extended 4 mo——
All 25 projects →
Chikalthana market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Simar Pride Ventures Llp8 projects
  2. Pride Ventures (I) Pvt Ltd3 projects
  3. Nabhraj Construction2 projects
  4. Abad Estate Aop1 project
  5. Akash Rajesh Butole And Rajesh Balabax Butole1 project
  6. Bhaishree Realtors Llp1 project
  7. Kasliwal Niwara1 project
  8. Om Sai Developers1 project
  9. Samarth infra1 project
  10. Sanjay Suganchand Kasliwal1 project

Chikalthana, in questions

How many projects in Chikalthana run late?

7 in 10 MahaRERA registrations (18 of 27): their completion date was extended or has passed, data through 21 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Chikalthana by Deedo. Medians on fewer than 3 deeds are not shown.

Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology