RERA projects in Golwadi

14 projects under 15 MahaRERA registrations, registered 2017–2026. 20% have a completion date extended beyond the one promised.

Locality
14RERA projects
15Registrationssome projects hold several
7Completion still due8 past their completion date, 4 marked completed
4 monthsMedian extension beyond promised date20% of registrations extended
1Regulatory caseson 1 project
69Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20174
20181
20193
20200
20210
20220
20234
20241
20250
20262

Projects in Golwadi

14 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Aarav EnclaveRajendra Laxminarayan JaiswalPR104000260095329 Jun 202631 Mar 202831 Jul 2028Extended 4 mo0
Ssbd TowerSSBD Builders and Developers LLPPR10400026003748 May 202631 Dec 202730 Apr 2028Extended 4 mo0
Parvati HillsKisan Khanderao DhondareP5150005523914 Mar 202431 Mar 2030—Not yet due0
Ashtavinayak EnclaveRajendra Laxminarayan JaiswalP5150005148523 Jun 202331 Dec 202531 Dec 2025Promised date passed0
36 GreensA.m.patel Infra Pvt LtdP5150005063821 Apr 202330 Nov 202730 Nov 2027Not yet due1
Happy Homes Happy StreetShakti Lifespaces Pvt LtdP51500050368, P515000507875 Apr 202331 Dec 202631 Dec 2026Completed0
Babasaheb Gahenaji TambeBabasaheb Gahenaji TambeP5150002302314 Nov 201931 Jan 202031 Jan 2020Promised date passed0
Green WoodsChintamani InfrastructureP5150002237216 Sep 201930 Mar 202531 Dec 2027Extended 33 mo0
Tayal Siddhivinak Gangamai RecidencyTayals Siddhivinayak Gangamai ResidencyP5150001938929 Jan 201911 Jul 201911 Jul 2019Promised date passed0
Sai ResidencySai Shraddha Construction & DevelopersP5150001832123 Oct 201830 Dec 2020—Completed0
Shanti Nagar AopM/S. Shanti NagarP5150001470426 Dec 201731 Dec 2018—Completed0
Shree Krishna ResidencyKarwa Constructions And DevelopersP5150001387430 Oct 201730 Dec 202230 Dec 2022Promised date passed0
Tulsi GreenMulay FamilyP5150000605114 Aug 201731 Jul 2019—Completed0
Chaitanya PlazaChaitanya PlazaP515000028294 Aug 201731 Jul 202231 Jul 2022Promised date passed0

Other localities in Aurangabad

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Rajendra Laxminarayan Jaiswal2 projects
  2. A.m.patel Infra Pvt Ltd1 project
  3. Babasaheb Gahenaji Tambe1 project
  4. Chaitanya Plaza1 project
  5. Chintamani Infrastructure1 project
  6. Karwa Constructions And Developers1 project
  7. Kisan Khanderao Dhondare1 project
  8. M/S. Shanti Nagar1 project
  9. Mulay Family1 project
  10. Sai Shraddha Construction & Developers1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology