RERA projects in Satara Tanda

2 projects under 2 MahaRERA registrations, registered 2021–2022. None has an extended completion date on record.

Locality
2RERA projects
2Registrations
0Completion still due2 past their completion date
—Median extension beyond promised date0% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20211
20221

Projects in Satara Tanda

2 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Hari Jyoti Park Part 2Parineeta Pramod KhairnarP5150003462820 Apr 202230 Jun 2023—Promised date passed0
Shri Hari HillsParineeta Pramod KhairnarP5150002924310 May 202131 Dec 2022—Promised date passed0

Other localities in Aurangabad

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Parineeta Pramod Khairnar2 projects
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology