6 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects1,480in 80 localities
Registrations1,507some projects hold several
Completion still due421789 past their date
Median extension4 months31% of registrations extended
Regulatory cases122on 114 projects

6 in 10 registrations run late here

1,507 MahaRERA registrations in Aurangabad and the places within it

181 completed143 not yet due265 extended, not yet due621 past even the latest date297 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Aurangabad

1,480 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Khinvansara AuraRavindra Champalal KhinvasaraDue Apr 2031, extended 4 mo——
Shiv SanskrutiShiv Sanskruti RealityDue Apr 2029, extended 4 mo——
Neo OrbitPiyush Infratech Pvt.Ltd.Due Dec 2030, extended 4 mo——
Sai SwapnapurtiVikas Developers & ConstructionDue Dec 2029, extended 4 mo——
Shree Sai TowerRaosaheb Shripal UdagaveDue Aug 2030, extended 4 mo——
Swaraj HeightsShree Samarth InfraDue Apr 2032, extended 4 mo——
VasundharaMorya AssociatesDue Apr 2029, extended 4 mo——
Parijat SkylineKishor Madanlal LalwaniDue Aug 2028, extended 4 mo——
Siddhivinayak Trade CenterMulti-Trek Infra LLPDue Apr 2030, extended 4 mo——
Malhar ApartmentMukund Govindrao KulkarniDue Apr 2029, extended 4 mo——
Siddhi Ellora Business ParkAdvika ConstructionDue Aug 2027——
Arch VistaVista AssociatesDue Apr 2031, extended 4 mo——
Vishwaraj HeightsAmardeep Builders And DevelopersDue Apr 2031, extended 4 mo——
Madhura AnganMadhura EstateDue Apr 2032, extended 4 mo——
Farha ValleyGlint Aster Homes LLPDue Feb 2027, extended 4 mo——
Rama ParkDattatraya Rambhau BawaskarCompleted——
Grover TowerVeena Jaikrishan GroverDue Apr 2032, extended 4 mo——
Swapna Srushti 1Nisha AssociatesDue Jul 2028, extended 4 mo——
Om Sai Ram ResidencyOm Sai Ramleela Buildcon LLPDue Sep 2027, extended 4 mo——
Samruddhi TowerSamruddhi InfraDue Apr 2030, extended 4 mo——
Venugopal ParkYashwant Mukund KharoteDue Mar 2030——
Viquar VillamentsRoyal BuildersDue Mar 2028——
Jagdale ResidencyVaibhav Arun JagdaleDue Dec 2028——
Sara NiwaraSara InfrastructuresDue Dec 2030——
Vighnaharta ResidencyAvinya DevelopersDue Dec 2027——
Aurangabad market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Sajansing Motilal Jarwal11 projects
  2. Simar Pride Ventures Llp10 projects
  3. Vikas Laxman Chaudhary10 projects
  4. Sajansing Motilal Jarwal9 projects
  5. Bhuvi Landmarks Llp8 projects
  6. Arch Developers7 projects
  7. Sara Infrastructures7 projects
  8. Jagrut Sara Associates6 projects
  9. Nabhraj Builders And Developers Pvt Ltd6 projects
  10. Sakshi Builders6 projects

Aurangabad, in questions

How many projects in Aurangabad run late?

6 in 10 MahaRERA registrations (886 of 1,507): their completion date was extended or has passed, data through 20 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Aurangabad by Deedo. Medians on fewer than 3 deeds are not shown.

Data through20 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology