Deedo IDDL-AUR-AURANGABAD6 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
6 in 10 registrations run late here
1,507 MahaRERA registrations in Aurangabad and the places within it
181 completed143 not yet due265 extended, not yet due621 past even the latest date297 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Aurangabad
1,480 projects registered with MahaRERA in this district and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Khinvansara AuraRavindra Champalal Khinvasara | Due Apr 2031, extended 4 mo | — | — |
| Shiv SanskrutiShiv Sanskruti Reality | Due Apr 2029, extended 4 mo | — | — |
| Neo OrbitPiyush Infratech Pvt.Ltd. | Due Dec 2030, extended 4 mo | — | — |
| Sai SwapnapurtiVikas Developers & Construction | Due Dec 2029, extended 4 mo | — | — |
| Shree Sai TowerRaosaheb Shripal Udagave | Due Aug 2030, extended 4 mo | — | — |
| Swaraj HeightsShree Samarth Infra | Due Apr 2032, extended 4 mo | — | — |
| VasundharaMorya Associates | Due Apr 2029, extended 4 mo | — | — |
| Parijat SkylineKishor Madanlal Lalwani | Due Aug 2028, extended 4 mo | — | — |
| Siddhivinayak Trade CenterMulti-Trek Infra LLP | Due Apr 2030, extended 4 mo | — | — |
| Malhar ApartmentMukund Govindrao Kulkarni | Due Apr 2029, extended 4 mo | — | — |
| Siddhi Ellora Business ParkAdvika Construction | Due Aug 2027 | — | — |
| Arch VistaVista Associates | Due Apr 2031, extended 4 mo | — | — |
| Vishwaraj HeightsAmardeep Builders And Developers | Due Apr 2031, extended 4 mo | — | — |
| Madhura AnganMadhura Estate | Due Apr 2032, extended 4 mo | — | — |
| Farha ValleyGlint Aster Homes LLP | Due Feb 2027, extended 4 mo | — | — |
| Rama ParkDattatraya Rambhau Bawaskar | Completed | — | — |
| Grover TowerVeena Jaikrishan Grover | Due Apr 2032, extended 4 mo | — | — |
| Swapna Srushti 1Nisha Associates | Due Jul 2028, extended 4 mo | — | — |
| Om Sai Ram ResidencyOm Sai Ramleela Buildcon LLP | Due Sep 2027, extended 4 mo | — | — |
| Samruddhi TowerSamruddhi Infra | Due Apr 2030, extended 4 mo | — | — |
| Venugopal ParkYashwant Mukund Kharote | Due Mar 2030 | — | — |
| Viquar VillamentsRoyal Builders | Due Mar 2028 | — | — |
| Jagdale ResidencyVaibhav Arun Jagdale | Due Dec 2028 | — | — |
| Sara NiwaraSara Infrastructures | Due Dec 2030 | — | — |
| Vighnaharta ResidencyAvinya Developers | Due Dec 2027 | — | — |
Localities in Aurangabad
- Aurangabad (M Corp.)513 projects
- Aurangabad192 projects
- Tisgaon93 projects
- Satara (Ct)61 projects
- Itkheda38 projects
- Pisadevi35 projects
- Devlai31 projects
- Garkheda31 projects
- Chikalthana25 projects
- Sawangi22 projects
- Shendra Kamangar21 projects
- Aurangabad (Cb)20 projects
All 80 localities
- Nakshatrawadi19
- Wadgaon Kolhati (Ct)19
- Golwadi17
- Sundarwadi15
- Hirapur14
- Kubhephal14
- Harsool12
- Gangapur Jahagir11
- Balapur9
- Gangapur7
- Shendraban7
- Wadgaon Kh.7
- Bidkin6
- Karmad6
- Paithan (M Cl)6
- Sillod (M Cl)6
- Ashrafpur5
- Gandheli5
- Fattepur4
- Kannad4
- Kannad4
- Shahanur Wadi4
- Gangapur3
- Georai3
- Paithan3
- Palshi3
- Shioor3
- Sulibhanjan3
- Apatgaon2
- Babhulgaon2
- Nanakwadi2
- Ohar2
- Satara Tanda2
- Sawangi2
- Sillod2
- Tuljapur2
- Vaijapur (M Cl)2
- Waluj Bk. (Ct)2
- Warud2
- Zalta2
- Aghur1
- Andheri1
- Bendewadi1
- Chartha1
- Farola1
- Gangapur (M Cl)1
- Georai Tanda1
- Ghanegaon1
- Jogeshwari1
- Jyoti Nagar1
- Kamlapur1
- Kanchanwadi1
- Karodi1
- Khultabad1
- Ladgaon1
- Nagar Tisgaon1
- Naigaon1
- Narayanpur Kh.1
- Nilajgaon1
- Others1
- Paithan Kheda1
- Pokhari1
- Pune (M Corp.)1
- Ranjangaon (S) (Ct)1
- Rotegaon1
- Shahajapur1
- Soygaon1
- Usmanpura1
Other districts
Most active promoters
- Sajansing Motilal Jarwal11 projects
- Simar Pride Ventures Llp10 projects
- Vikas Laxman Chaudhary10 projects
- Sajansing Motilal Jarwal9 projects
- Bhuvi Landmarks Llp8 projects
- Arch Developers7 projects
- Sara Infrastructures7 projects
- Jagrut Sara Associates6 projects
- Nabhraj Builders And Developers Pvt Ltd6 projects
- Sakshi Builders6 projects
Aurangabad, in questions
How many projects in Aurangabad run late?
6 in 10 MahaRERA registrations (886 of 1,507): their completion date was extended or has passed, data through 20 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Aurangabad by Deedo. Medians on fewer than 3 deeds are not shown.