RERA projects in Harsool

3 projects under 3 MahaRERA registrations, registered 2022–2026. None has an extended completion date on record.

3RERA projects
3Registrations
2Completion still due1 past their completion date
—Median extension beyond promised date0% of registrations extended
0Regulatory casesnone on MahaRERA's lists
3Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20221
20230
20240
20251
20261

Projects in Harsool

3 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Indrayani NandanwanIndrayani Builder and DevelopersPR104000260124920 Jul 202631 Mar 2031—Not yet due0
Sara NiwaraSara InfrastructuresP515000807431 Jul 202531 Dec 2030—Not yet due0
Pargaonkar Nagar - 01Sai Builders And DevelopersP515000457719 Jun 202231 Mar 2025—Promised date passed0

Other localities in Aurangabad

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Indrayani Builder and Developers1 project
  2. Sai Builders And Developers1 project
  3. Sara Infrastructures1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology