RERA projects in Jyoti Nagar

1 project under 1 MahaRERA registration, registered 2026–2026. 100% have a completion date extended beyond the one promised.

Locality
1RERA projects
1Registrations
1Completion still due0 past their completion date
4 monthsMedian extension beyond promised date100% of registrations extended
0Regulatory casesnone on MahaRERA's lists
2Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20261

Projects in Jyoti Nagar

1 project registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Nabhraj AjinkyaSwaraj InfrastructurePR10400025025924 Mar 202631 Dec 202830 Apr 2029Extended 4 mo0

Other localities in Aurangabad

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Swaraj Infrastructure1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology