RERA projects in Kannad
4 projects under 4 MahaRERA registrations, registered 2020–2026. 50% have a completion date extended beyond the one promised.
Locality
4RERA projects
4Registrations
2Completion still due2 past their completion date
4 monthsMedian extension beyond promised date50% of registrations extended
0Regulatory casesnone on MahaRERA's lists
5Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2020 | 1 |
| 2021 | 0 |
| 2022 | 0 |
| 2023 | 1 |
| 2024 | 0 |
| 2025 | 1 |
| 2026 | 1 |
Projects in Kannad
4 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| MORYA PARK Ph-IIIMh Builders And Developers | PR1040002600975 | 29 Jun 2026 | 31 Dec 2031 | 30 Apr 2032 | Extended 4 mo | 0 |
| Diamond ComplexDiamond Developers | P51500079287 | 25 Feb 2025 | 12 Dec 2028 | 12 Apr 2029 | Extended 4 mo | 0 |
| Galaxy TowerGlobal Stone Builders And Developers | P51500049454 | 14 Feb 2023 | 11 Jan 2026 | 11 Jan 2026 | Promised date passed | 0 |
| Ram NagarBharat Rambhau Lokhande | P51500024451 | 13 Feb 2020 | 30 Mar 2022 | 30 Mar 2022 | Promised date passed | 0 |
Most active promoters
By projects registered here, as named on MahaRERA.
- Bharat Rambhau Lokhande1 project
- Diamond Developers1 project
- Global Stone Builders And Developers1 project
- Mh Builders And Developers1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology