Fattepur, Aurangabad

Deedo IDDL-AUR-FATTEPUR

8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects4
Registrations4
Completion still due13 past their date
Median extension12 months75% of registrations extended
Regulatory cases0none on MahaRERA's lists

8 in 10 registrations run late here

4 MahaRERA registrations in Fattepur

1 completed1 extended, not yet due2 past even the latest date

Extended registrations moved their completion date by a median of 12 months.

Projects in Fattepur

4 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Prisha Square Phase-IINandkishor Bhimrao ChavanDue Apr 2031, extended 4 mo——
Prisha SquareNandkishor Bhimrao ChavanCompleted——
Simplicity Phase - IShreeram Traders and Developers2 yrs 8 mo late——
Simplicity G BuildingAscentventuresCompleted, extended 5 yrs 6 mo—40%
Fattepur market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Ascentventures1 project
  2. Nandkishor Bhimrao Chavan1 project
  3. Nandkishor Bhimrao Chavan1 project
  4. Shreeram Traders And Developers1 project

Fattepur, in questions

How many projects in Fattepur run late?

8 in 10 MahaRERA registrations (3 of 4): their completion date was extended or has passed, data through 21 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Fattepur by Deedo. Medians on fewer than 3 deeds are not shown.

Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology