RERA projects in Fattepur

4 projects under 4 MahaRERA registrations, registered 2017–2026. 50% have a completion date extended beyond the one promised.

Locality
4RERA projects
4Registrations
1Completion still due3 past their completion date, 1 marked completed
39 monthsMedian extension beyond promised date50% of registrations extended
0Regulatory casesnone on MahaRERA's lists
3Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20171
20180
20190
20200
20210
20222
20230
20240
20250
20261

Projects in Fattepur

4 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Prisha Square Phase-IINandkishor Bhimrao ChavanPR10400026005991 Jun 202631 Dec 2030—Not yet due0
Prisha SquareNandkishor Bhimrao ChavanP5150004548424 May 202231 Mar 2024—Completed0
Simplicity Phase - IShreeram Traders and DevelopersP5150003480328 Apr 202231 Mar 202431 Mar 2025Extended 12 mo0
Simplicity G BuildingAscentventuresP5150000561517 Nov 201731 Dec 201730 Jun 2023Extended 66 mo0

Other localities in Aurangabad

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Nandkishor Bhimrao Chavan2 projects
  2. Ascentventures1 project
  3. Shreeram Traders and Developers1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology