Active

Tisgaon, Aurangabad 431102 |Promoter: Sahakar JV

Residential / Group HousingRERAP51500079944
7 Apr 2025Registered with MahaRERA
31 Dec 2025Promised completion
8Buildings
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Active
Buildings
8
Land area for this project
20,509 sq m (2,20,761 sq ft)
Permissible built-up area
32,833 sq m (3,53,411 sq ft)
Sanctioned built-up area
32,833 sq m (3,53,411 sq ft)
Recreational open space
4,647 sq m (50,023 sq ft)
Planning authority
Chhatrapati Sambhajinagar Municipal Corporation
Address
Gut no. 225/1 Part, Mauje Tisgaon, Gut no. 225/1, Mauje TisgaonPIN 431102
Designated bank account
Indian Bank
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 0.00000, 0.00000
PMAY U Tisgaon 225 A is at latitude 0.00000, longitude 0.00000.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Dec 2025

The latest completion date on record passed 10 months ago.

Registered
7 Apr 2025
Promised
31 Dec 2025

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P515000799447 Apr 202531 Dec 2025—Sahakar JVProject page

8 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
A11-A127—
A13-A147—
A15-A168—
A1-A28—
A3-A48—
A5-A68—
A7-A88—
A9-A108—

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 units registered

Parking

BuildingTypeTwo-wheelerFour-wheelerBusVisitorTotal
A11-A12Closed/Covered00000
A11-A12Open Space7200072
A13-A14Closed/Covered00000
A13-A14Open Space7200072
A15-A16Closed/Covered00000
A15-A16Open Space8200082
A1-A2Closed/Covered00000
A1-A2Open Space8200082
A3-A4Closed/Covered00000
A3-A4Open Space8200082
A5-A6Closed/Covered00000
A5-A6Open Space8200082
A7-A8Closed/Covered00000
A7-A8Open Space8200082
A9-A10Closed/Covered00000
A9-A10Open Space8200082

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

A11-A12

  • Excavation100%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth15%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

A13-A14

  • Excavation100%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

A15-A16

  • Excavation100%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

A1-A2

  • Excavation100%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

A3-A4

  • Excavation100%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

A5-A6

  • Excavation100%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

A7-A8

  • Excavation100%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth60%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

A9-A10

  • Excavation100%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyNot applicable
  • Sewerage (Chamber, Lines, Septic Tank , STP)Not applicable
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingNot applicable
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingNot applicable
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationNot applicable
  • Aggregate area of recreational Open SpaceAs per Proposed Plan0%
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

43 documents held by Deedo, 50 filings listed on MahaRERA's project page

Others

Registration certificate

Document library

  • Commencement Certificates / NA Order for plotted developmentCC Upload.pdf · uploaded 5 Mar 2025View
  • Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 5 Mar 2025View
  • Building Plan Approval / NA Order for plotted developmentBuilding Plan.pdf · uploaded 5 Mar 2025View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Upload.pdf · uploaded 7 Mar 2025View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Sahakar 225-1 Block A.PDF · uploaded 10 Mar 2025View
  • Commencement Certificates / NA Order for plotted developmentGmail - 76 08 SANTION BP POROPSAL 05032025 PMAY.pdf · uploaded 10 Mar 2025View
  • CERSAI details225 A.pdf · uploaded 10 Mar 2025View
  • Declaration about Commencement CertificateDecleration of Commencement Certificate.PDF · uploaded 12 Mar 2025View
  • Disclosure for secured/unsecured finance availed for the projectDisclosure for securedunsecured finance availed for the project.PDF · uploaded 12 Mar 2025View
  • CERSAI detailsCersai Declaration.PDF · uploaded 12 Mar 2025View
  • Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest Merged.pdf · uploaded 12 Mar 2025View
  • Disclosure of sold/ booked inventorySold Unsold Inventory 225 A.pdf · uploaded 12 Mar 2025View
  • Other – LegalAnnexure A.PDF · uploaded 12 Mar 2025View
  • Declaration about all RERA Designated Bank Accounts (Format A)Declaration about RERA Designated Bank Accounts for real estate projects.PDF · uploaded 12 Mar 2025View
  • Deviation Report with respect to Allotment letterDeviation Report with respect to Allotment letter.PDF · uploaded 12 Mar 2025View
  • Deviation Report with respect to model copy of AgreementDeviation Report with respect to model copy of Agreement.PDF · uploaded 12 Mar 2025View
  • Declaration in FORM BFORM B - Developer New Revised Upload.pdf · uploaded 12 Mar 2025View
  • a Details of encumbrances concerned to FinanceEmcumbrances.pdf · uploaded 13 Mar 2025View
  • b Details of encumbrances concerned to LegalEmcumbrances.pdf · uploaded 13 Mar 2025View
  • Copy of the legal title reportRERA SEARCH REPORT GUT NO 225 Tisgaon.pdf · uploaded 25 Mar 2025View
  • Other – LegalTisgaon 225-1 7-12_upload.pdf · uploaded 25 Mar 2025View
  • Other – LegalSHAKAR JV_upload.pdf · uploaded 25 Mar 2025View
  • Proforma of Allotment letterNEW ALLOTMENT LETTER.pdf · uploaded 25 Mar 2025View
  • Proforma of Agreement for saleAGREEMENT TO SALE.pdf · uploaded 25 Mar 2025View
  • Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)10 Opening of RERA Designated Bank Accounts_page.pdf · uploaded 25 Mar 2025View
  • Other – FinanceForm 3 Declaration Tisgaon 225 A.pdf · uploaded 25 Mar 2025View
  • Other – FinanceWorkorder Tisgaon 225-1.pdf · uploaded 25 Mar 2025View
  • Other – Technical6 Annexure A.PDF · uploaded 25 Mar 2025View
  • Other – TechnicalCC Declaration.pdf · uploaded 25 Mar 2025View
  • Other – TechnicalTisgaon 225 -1 Workorder.pdf · uploaded 25 Mar 2025View
  • Withdrawal Update Form 1Form 1 225 A.pdf · uploaded 24 Jul 2025View
  • Withdrawal Update Form 2Form 2 225 A.pdf · uploaded 24 Jul 2025View
  • Withdrawal Update Form 1Sahakar JV - Tisgaon Gut No 225-1 Block A - Form 1.pdf · uploaded 27 Oct 2025View
  • Withdrawal Update Form 2Sahakar JV - Tisgaon Gut No 225-1 Block A - Form 2.pdf · uploaded 27 Oct 2025View
  • Withdrawal Update Form 1Tisgaon Gut No 225 1 A Form 1.PDF · uploaded 20 Jan 2026View
  • Withdrawal Update Form 2Tisgaon Gut No 225 1 A Form 2.PDF · uploaded 20 Jan 2026View
  • Withdrawal Update Form 1Tisgaon 225 A SJ Form 1 Signed.PDF · uploaded 12 May 2026View
  • Withdrawal Update Form 2Tisgaon 225 A SJ Form 2 Signed.PDF · uploaded 12 May 2026View
  • Withdrawal Update Form 1Tisgaon Gut 225 Block A Form 1.pdf · uploaded 29 Jul 2026View
  • Withdrawal Update Form 2Tisgaon Gut 225 Block A Form 2.pdf · uploaded 29 Jul 2026View

Promoter documents

  • Declaration Form BFORM B - Developer New Revised Upload.pdf · uploaded 12 Mar 2025View
  • Legal Title reportRERA SEARCH REPORT GUT NO 225 Tisgaon.pdf · uploaded 25 Mar 2025View

Technical documents

  • Layout ApprovalLayout.pdfView
  • Building Plan ApprovalBuilding Plan.pdfView

Other legal documents

  • Other – LegalAnnexure A.PDFView
  • Other – LegalTisgaon 225-1 7-12_upload.pdfView
  • Other – LegalSHAKAR JV_upload.pdfView

Financial documents

  • Other – FinanceForm 3 Declaration Tisgaon 225 A.pdf · uploaded 25 Mar 2025View
  • Other – FinanceWorkorder Tisgaon 225-1.pdf · uploaded 25 Mar 2025View

Proforma allotment letter

  • Proforma allotment letterNEW ALLOTMENT LETTER.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Tisgaon, Aurangabad taluka

Survey, CTS, gat or plot numbers

Gut no. 225/1 Part

As published on MahaRERA's project page

Gut no. 225/1 Part, Mauje Tisgaon

Boundaries

North
60 Mtr Wide Road
South
Gut no 225 Part
East
12 Mtr Wide Road
West
Open Space

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAr. Swapnil Shroff—
Chartered accountantCA Yash Nagar—
Chartered accountantSonawane Sahane & Associates—
EngineerSurve Samarth Chandrakant—

Source: MahaRERA project page. Contact details are not shown.

Data through11 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology