RERA projects in Satara

1,182 projects under 1,195 MahaRERA registrations across 126 localities, registered 2017–2026. 12% have a completion date extended beyond the one promised.

District
1,182RERA projectsin 126 localities
1,195Registrationssome projects hold several
389Completion still due599 past their completion date
22 monthsMedian extension beyond promised date12% of registrations extended
80Regulatory caseson 80 projects
99Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
2017227
201891
201986
202078
202196
202294
2023102
202467
202586
202661

Projects in Satara

1,182 projects registered with MahaRERA in this district and the places within it.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Moon Light TowerRaj BuildersPR130000250274912 Mar 202631 Dec 2030—Not yet due0
Sukhodayam VillasM/s Ultra Urban Greene Realty LLPPP130000250270110 Mar 202631 Dec 2027—Not yet due0
99 AvenueReliable VenturePR13000025026155 Mar 202631 Dec 2031—Not yet due0
Aatish Central HubIra Earthcon Pvt LtdPM130000250241720 Feb 202630 Jun 2030—Not yet due0
Dwarka - Wing EShree Classic DevelopersPR130000250233912 Feb 202631 Dec 2030—Not yet due0
Aruved Town Phase2Aruved Builders & DevelopersPR130000250214421 Jan 202631 Dec 2030—Not yet due0
Aruved Town Phase 1Aruved Builders & DevelopersPR130000250212220 Jan 202631 Dec 2030—Not yet due0
Deepam ResidencyJanardhan Anantrao VibhutePR130000250211220 Jan 202630 Jun 2028—Not yet due0
ManoramaNaik Nimbalkar InfraPR130000250212620 Jan 202631 Dec 2028—Not yet due0
Kanyaratna Row HousesKanyaratna InfraPR130000250205912 Jan 202631 Dec 2030—Not yet due0
RugvedDurvankur Vastunirmiti Private LimitedPR130000250187726 Dec 202531 Dec 2029—Not yet due0
Hiragan ResidencySarada Landmark Private LimitedPR130000250182417 Dec 202531 Dec 2028—Not yet due0
PetalsDev PropertiesPR130000250179215 Dec 202531 Dec 2029—Not yet due0
Laxmi Shridhar ComplexPhadke Builders and DevelopersPR130000250176112 Dec 202531 Dec 2029—Not yet due0
The Royal AbodeRushikesh DevelopersPR130000250155124 Nov 202530 Apr 2030—Not yet due0
Shree Sai SerenityShree Sai BuildconPM130000250149017 Nov 202531 Dec 2031—Not yet due0
Nehadeep AvenueShriman Builders And DevelopersPR130000250147014 Nov 202531 Aug 2031—Not yet due0
Vyankatesh HeightsVyankatesh Builders SataraPR130000250141710 Nov 202531 Dec 2029—Not yet due0
Samruddhi VastuSamruddhi Builders & DevelopersPR13000025013977 Nov 202531 Dec 2030—Not yet due0
Sai UmeshShirke Constructions Pvt. Ltd.PR130000250135330 Oct 202531 Dec 2030—Not yet due0
Mayuresh ResidencyRahul Bhaskar ShalgarPR130000250132020 Oct 202531 Dec 2029—Not yet due0
Ambika ViharK K DevelopersP5270008101715 Oct 202531 May 2030—Not yet due0
Sanjog NiketanShree Niketan DevelopersPR130000250123315 Oct 202531 May 2028—Not yet due0
The Explorers Club and Country HouseInternational Wellness Residences Private LimitedPM13000025011529 Oct 202531 Dec 2028—Not yet due0
Guru AnganM/S Jadhav Korattil Promoters And DevelopersPR13010125010601 Oct 202531 Dec 2030—Not yet due0

Localities in Satara

By number of registered projects, as MahaRERA names them.

All 126 localities

Other districts

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Venkatesh Promoters And Builders6 projects
  2. Aditya Developers through Proprietor Kumar Balasaheb Chavan5 projects
  3. ASHWINI BUILDER'S & DEVELOPERS Pvt. Ltd.5 projects
  4. Rajan Namdeo Pore5 projects
  5. Shree Chaitanya Builders5 projects
  6. Swara Construction5 projects
  7. Model Developers And Builders4 projects
  8. M/S. Omkar Developers4 projects
  9. M Sons Builder And Developers4 projects
  10. Shinde Jadhav Builders And Developers4 projects
Data through11 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology