1,161 MahaRERA projects in Thane are past their promised completion date, and MahaRERA shows no completion for them.

Most overdue first

Late: the latest completion date MahaRERA records (promised, or revised by an extension) has passed. Months late count from the first promised date. Page 5 of 24.

ProjectLocalityPromisedRevisedDelivery
Dreamland Co-op. Hsg. Soc. Ltd.Vaastusukh DevelopersNaupadaDec 2021Nov 20234 yrs 11 mo late
Falco RivershireShreeji EnterprisesAmbivali Tarf ChonDec 2021—4 yrs 11 mo late
Golden City ComplexShree J.p. BuildersMirabhayandar (M Corp.)Dec 2021Dec 20214 yrs 11 mo late
Guruprabha SankulVinay KoliKon (Ct)Dec 2021Sep 20254 yrs 11 mo late
Green Willows Phase IGreen LifespacesShendrun Bk.Dec 2021Dec 20214 yrs 11 mo late
Jeevan Asha HeightsNirmiti ConstructionsMirabhayandar (M Corp.)Dec 2021Dec 20214 yrs 11 mo late
Landscape Heritage Building No 2Landscape InfrastructureAmbarnath (R)Dec 2021Jun 20234 yrs 11 mo late
Maher CrestA Limitless ConstructionThane (M Corp.)Dec 2021Dec 20214 yrs 11 mo late
Malshej GreenGreen Space Real TechSaralgaonDec 2021Dec 20244 yrs 11 mo late
Man Itellipark - ItMerino Shelters Private LimitedNerulDec 2021Dec 20214 yrs 11 mo late
Mangal HeightsNakshatra DeveopersMajiwadeDec 2021Dec 20254 yrs 11 mo late
Mukul PalmsFaizunnisa Farooque SayedAmbarnath (R)Dec 2021Dec 20214 yrs 11 mo late
Nav RushikeshVighnaharta EnterprisesAmbarnath (R)Dec 2021Dec 20214 yrs 11 mo late
New Era CYogi Developers CorporationKalyanDec 2021Dec 20214 yrs 11 mo late
Namdev ViharNamdev ConstructionChikangharDec 2021Dec 20234 yrs 11 mo late
Om Shanti ResidencyOm Shanti Construction CompanyMandaDec 2021Dec 20244 yrs 11 mo late
Poonam SquareRohit Devendra GoyalMirabhayandar (M Corp.)Dec 2021Dec 20214 yrs 11 mo late
Shah SignatureShah Group Builders & Infraprojects LtdNavi Mumbai (M Corp.)Dec 2021Dec 20214 yrs 11 mo late
Shanti HouseShantistar BuildersMirabhayandar (M Corp.)Dec 2021Dec 20214 yrs 11 mo late
Shiv-GauriShivam DevelopersBadlapur (M Cl)Dec 2021—4 yrs 11 mo late
Shree Vignaharta Residency Building No B3, B4, B5 And B6Shree Vignaharta DeveloperDawaleDec 2021Dec 20234 yrs 11 mo late
Simran DeluxeSai BuildconUlhasnagar (M Corp.)Dec 2021Dec 20214 yrs 11 mo late
Simran GalaxyAnil Bhavandas PamnaniUlhasnagar (M Corp.)Dec 2021Dec 20214 yrs 11 mo late
Shashwat VaastuShashwat VaastuAsangaon (Ct)Dec 2021Dec 20214 yrs 11 mo late
Sunder Angan Phase IISunder Angan DevelopersMirabhayandar (M Corp.)Dec 2021Dec 20224 yrs 11 mo late
Tropical EliteSchema Enterprises Private LimitedThane (M Corp.)Dec 2021Dec 20224 yrs 11 mo late
Tulsi SamarthShree Krupa EnterprisesKalyanDec 2021Jun 20224 yrs 11 mo late
Vardhaman Nest HomesVardhaman Nest HomesThane (M Corp.)Dec 2021Dec 20214 yrs 11 mo late
Ved ResidencyOm CorporatinTitwalaDec 2021Dec 20214 yrs 11 mo late
Vighnaharta ArcadeVighnaharta EnterprisesBadlapurDec 2021Dec 20214 yrs 11 mo late
Seawoods HeightScarlet Builders & DeveloperNerulJan 2022Jan 20264 yrs 10 mo late
Simran LuxuriaJay Sunil DaryananiUlhasnagar (M Corp.)Jan 2022Jan 20224 yrs 10 mo late
HrishaYadav Bro''s ConstructionsAmbarnath (R)Jan 2022Jan 20224 yrs 10 mo late
Om Sai Sankul COm Sai UnitedMandaJan 2022Jan 20234 yrs 10 mo late
Shree PrastShree PrastPaliFeb 2022Feb 20234 yrs 9 mo late
Aarambha HeightsAarambha Vision Homes Private LimitedDombivliMar 2022Mar 20224 yrs 8 mo late
Ashapura PrideRadhika EnterprisesDombivliMar 2022Mar 20234 yrs 8 mo late
Devashree ParkRamesh SawantKolshetMar 2022Dec 20234 yrs 8 mo late
Haware ParadiseSuresh Kashinath HawareMuthavalMar 2022Mar 20224 yrs 8 mo late
Krishna DarshanShri Krishna RealtorsBadlapur (M Cl)Mar 2022Mar 20234 yrs 8 mo late
MilestonePacific CreationsDombivliMar 2022Mar 20224 yrs 8 mo late
Pavanputra ApartmentsPavanputra ApartmentsKalher (Ct)Mar 2022Mar 20264 yrs 8 mo late
Radha Vasant Vihar Wing - R1Shiv Sagar Developers & BuildersUlhasnagar (M Corp.)Mar 2022Mar 20224 yrs 8 mo late
Raj TorresRajesh Estates And Nirman Pvt LtdThane (M Corp.)Mar 2022Mar 20194 yrs 8 mo late
Seagreen SapphireSiddhivinayak HomesUlhasnagar (M Corp.)Mar 2022Mar 20234 yrs 8 mo late
Shree Gaondevi DhamShree Tisai DevelopersKalyanMar 2022Sep 20224 yrs 8 mo late
Sita HeightsNamdev Sakharam PatilKataiMar 2022Dec 20254 yrs 8 mo late
Tranquil ParadiseMirza Homes Private LimitedAiroliMar 2022Mar 20224 yrs 8 mo late
Trinity Galaxy R5Trinity DevelopersBadlapurMar 2022Mar 20224 yrs 8 mo late
Urban GrandMahaveer realityKalyanMar 2022Mar 20224 yrs 8 mo late

Delayed projects by district

SourcesMahaRERA registrations, extension certificates, project pages and document listsA project counts as completed when MahaRERA shows it so: its status, or a completion or occupancy certificate in its documents. Dates are MahaRERA's; Deedo does not know the day a project was handed over.Report a problemMethodology