Delayed projects in Thane

1,161 MahaRERA projects in Thane are past their promised completion date, and MahaRERA shows no completion for them.

Most overdue first

Late: the latest completion date MahaRERA records (promised, or revised by an extension) has passed. Months late count from the first promised date. Page 6 of 24.

ProjectLocalityPromisedRevisedDelivery
Saish EnclaveDombivliApr 2022Apr 20224 yrs 7 mo late
Redevelopment Of Manas ChsArvij Builders And Developers Private LimitedThane (M Corp.)May 2022Oct 20234 yrs 6 mo late
Pride Of UttanBrickscity Developers Private LimitedMira Bhayandar (M Corp.)May 2022Dec 20254 yrs 6 mo late
Archit JewelArchit EnterprisesMumbraMay 2022Dec 20254 yrs 6 mo late
Raut BuildingBhavna C ChhedaThane (M Corp.)May 2022May 20224 yrs 6 mo late
PraptiPrapti EnterprisesAmbarnathJun 2022Jun 20224 yrs 5 mo late
ArizonaParas DevelopersThane (M Corp.)Jun 2022Jun 20224 yrs 5 mo late
Ashtivinayak ApartmentHare Krishna EnterprisesUlhasnagar (M Corp.)Jun 2022Jun 20224 yrs 5 mo late
Aadi Aarambh IINirman ConstructionAmbarnath (R)Jun 2022Jun 20224 yrs 5 mo late
Anantam - Phase IOyster Living LLPPimpalasJun 2022Aug 20244 yrs 5 mo late
Anantam - Phase IIOyster Living LLPPimpalasJun 2022Jun 20234 yrs 5 mo late
BHANUMATI TOWER wing APooja BuildconKatemanevaliJun 2022Jun 20224 yrs 5 mo late
BroadewayoneBroadwayThaneJun 2022Jun 20234 yrs 5 mo late
Charms Heights Phase-III B2-B3Charms DevelopersMandaJun 2022Dec 20254 yrs 5 mo late
Nanu ParkB G Patil And SonsKalyanJun 2022Jun 20244 yrs 5 mo late
Ram Ratan Complex - A Wing - RamDombivliJun 2022Jun 20224 yrs 5 mo late
Ram Ratan Complex - B Wing - LaxmanThaneJun 2022Jun 20224 yrs 5 mo late
Shivanjali HeightsShivanjali ConstructionBadlapur (M Cl)Jun 2022Jun 20234 yrs 5 mo late
Shree Sai Chaya ArcadeDombivliJun 2022Jun 20224 yrs 5 mo late
Shri Guruprasad ApartmentMangalya DeveloperBadlapurJun 2022Jun 20224 yrs 5 mo late
Siddiquee ComplexSiddiquee Construction Co.Thane (M Corp.)Jun 2022Jun 20254 yrs 5 mo late
Siddiquee EnclaveSiddiquee Infrastructure Co.Thane (M Corp.)Jun 2022Dec 20244 yrs 5 mo late
SwaminiShiv EnterprisesKulgaonJun 2022Jun 20224 yrs 5 mo late
Mahadev TowerNandkumar Mahadev PatilMira Bhayandar (M Corp.)Jul 2022Jul 20224 yrs 4 mo late
Tropical Lagoon - 5 - Di VitaSoham EstatesThane (M Corp.)Jul 2022Jul 20234 yrs 4 mo late
Tsp HeightsAshwamegh AssoicatesDombivliJul 2022Dec 20224 yrs 4 mo late
Chirag ConstructionAdivali DhokaliAug 2022Aug 20224 yrs 3 mo late
Trijal EnterprisesAdivali DhokaliAug 2022Aug 20224 yrs 3 mo late
Vikram Villa Co-Op Housing SocietyChaturthi DevelopersDombivliAug 2022Jan 20244 yrs 3 mo late
Lifestyle City Kalyan RivieraNirmal Lifestyle (Kalyan) Private LimitedVadavali Kh.Aug 2022Oct 20244 yrs 3 mo late
Lifestyle City Kalyan-Magnolia ANirmal Lifestyle (Kalyan) Private LimitedVadavali Kh.Aug 2022Aug 20224 yrs 3 mo late
Mahadev ResidencyRajkumar Tuljaram AswaniAsangaon (Ct)Aug 2022Aug 20224 yrs 3 mo late
Ekdant ResidencyEkdant ConstructionThane (M Corp.)Sep 2022Mar 20234 yrs 2 mo late
Keshav Height Building CNandkumar Balkrishna SalviThane (M Corp.)Sep 2022Jun 20244 yrs 2 mo late
Kohinoor LuxuriaShankar HotchandaniNetivaliSep 2022Sep 20224 yrs 2 mo late
Lodha Splendora - Platino - DMacrotech Developers LimitedThane (M Corp.)Sep 2022Sep 20224 yrs 2 mo late
Swastik HeightsAshok Suryanarayan SinghKalyanSep 2022Sep 20234 yrs 2 mo late
The Nageshwar ApartmentOmkar DevelopersBadlapurSep 2022Sep 20234 yrs 2 mo late
Bama Patil Shopping CentreKataiOct 2022Oct 20224 yrs 1 mo late
Sarita ApartmentShivansh Vaishnavi ConstractionUlhasnagar (M Corp.)Oct 2022Apr 20234 yrs 1 mo late
Shiv Sai ResidencySonarpadaOct 2022Oct 20224 yrs 1 mo late
SwaroopPruthviraj Balkrishna MhatreNavi Mumbai (M Corp.)Nov 2022Nov 20224 yrs late
Periwinkle Villa (Durgadham)Suresh Shalik MhatreNaupadaNov 2022Nov 20234 yrs late
Shree Builders And DevelopersNandivli Tarfe PanchnandNov 2022Nov 20224 yrs late
Expert Home Construction LLPKalyanDec 2022Dec 20223 yrs 11 mo late
Capmatrix SquareCapmatrix Buildcon LLPThane (M Corp.)Dec 2022Dec 20253 yrs 11 mo late
Harmony ResidencyMilestone ConstructionAmbarnath (R)Dec 2022Dec 20223 yrs 11 mo late
Salasar WoodsSalasar Estate Developers LLPBhayandarDec 2022Dec 20233 yrs 11 mo late
Susheela TowerDombivliDec 2022Dec 20223 yrs 11 mo late
The Vivek Flat Owners Chs LtdYash AshokaNaupadaDec 2022Dec 20253 yrs 11 mo late

Delayed projects by district

SourcesMahaRERA registrations, extension certificates, project pages and document listsA project counts as completed when MahaRERA shows it so: its status, or a completion or occupancy certificate in its documents. Dates are MahaRERA's; Deedo does not know the day a project was handed over.Report a problemMethodology