RERA projects in Pimpalas
2 projects under 2 MahaRERA registrations, registered 2018–2018. 100% have a completion date extended beyond the one promised.
2RERA projects
2Registrations
0Completion still due2 past their completion date
19 monthsMedian extension beyond promised date100% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2018 | 2 |
Projects in Pimpalas
2 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Anantam - Phase IIOyster Living LLP | P51700017195 | 23 Jul 2018 | 30 Jun 2022 | 30 Jun 2023 | Extended 12 mo | 0 |
| Anantam - Phase IOyster Living LLP | P51700017123 | 16 Jul 2018 | 30 Jun 2022 | 31 Aug 2024 | Extended 26 mo | 0 |
Other localities in Bhiwandi
Most active promoters
By projects registered here, as named on MahaRERA.
- Oyster Living LLP2 projects
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology