Skip to content

Bhiwandi, Thane

Deedo IDDL-THN-BHIWANDI

7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects451
Registrations489some projects hold several
Completion still due277167 past their date
Median extension4 months55% of registrations extended
Regulatory cases34on 16 projects

7 in 10 registrations run late here

489 MahaRERA registrations in Bhiwandi and the places within it

3 completed88 not yet due189 extended, not yet due164 past even the latest date45 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Bhiwandi

451 projects registered with MahaRERA in this taluka and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Golden ParadiseAquib Nizamuddin AnsariDue Dec 2032——
Riz ResidencyAbuzaid Rais Ahmed ShaikhDue Dec 2032——
Aarav HeightR B Builders and DevelopersDue Aug 2030——
Upper Thane­ IRIS Wing HLodha Developers LimitedDue Jun 2032——
Ckp Builder And DeveloperCkp Builder And DeveloperDue Dec 2029——
All 451 projects →
Bhiwandi market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Macrotech Developers Limited17 projects
  2. Lodha Developers Limited14 projects
  3. Arihant Enterprises7 projects
  4. Shakti Realty6 projects
  5. Infini Developers5 projects
  6. Adrika Developers Private Limited4 projects
  7. Al Araaf Infra Private Limited4 projects
  8. Siyara Realty Private Limited4 projects
  9. Kgi Realty Private Limited3 projects
  10. Maya Developer3 projects

Bhiwandi, in questions

How many projects in Bhiwandi run late?

7 in 10 MahaRERA registrations (353 of 489): their completion date was extended or has passed, data through 29 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Bhiwandi by Deedo. Medians on fewer than 3 deeds are not shown.

Data through29 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology