RERA projects in Murbad

53 projects under 54 MahaRERA registrations, registered 2017–2026. 11% have a completion date extended beyond the one promised.

Taluka
53RERA projects
54Registrationssome projects hold several
23Completion still due21 past their completion date
36 monthsMedian extension beyond promised date11% of registrations extended
3Regulatory caseson 3 projects
8Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20174
20189
20190
20203
20215
20225
20238
20242
20257
20261

Projects in Murbad

53 projects registered with MahaRERA in this taluka and the places within it.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Om Sai Krupa ApartmentShivnirman DevelopersPR133000250244623 Feb 202630 Dec 2028—Not yet due0
Suparshavanath RealitySuparshavanath RealityPR133000250184423 Dec 202531 Dec 2029—Not yet due0
Shree Ganesh ApartmentVandana Dinesh KanteP5170008098019 Sep 202531 Mar 2028—Not yet due0
Heritage VillasMadhusudan Infrabuild Private LimitedPM133000250064725 Aug 202531 Dec 2029—Not yet due0
Shree Darshan HeightsShree Darshan ConstructionP5170008008223 Apr 202531 Dec 2029—Not yet due0
Skyrise VillaSky Rise Builders And DevelopersP5170007970820 Mar 202531 Dec 2027—Not yet due0
Vishwa ComplexVastushilp ConstructionP5170007970120 Mar 202530 Jun 2027—Not yet due0
Shree ApartmentDeepak Shivaji HinduraoP5170007936028 Feb 202516 Apr 2026—Promised date passed0
Sai Krishna HeightsOm Sai DevelopersP5170005521111 Mar 202431 Dec 2026—Not yet due0
Om Shree Sai VillaSangita Sharad SuryaravP5170005495321 Feb 202431 Dec 2026—Not yet due0
Crystal Retreat Phase 1Ajay & Sanjay MaheshwariP517000538381 Dec 202331 Dec 2030—Not yet due0
Satish ResidencyNitin Rajaram GharatP517000538421 Dec 202331 Dec 2025—Promised date passed0
Sai Krupa ApartmentBhimraj Ganpat MoreP5170005372828 Nov 202331 Dec 2026—Not yet due0
Madhusudan Retreat TerracesMadhusudan Leisure HomesP517000529285 Oct 202331 Dec 2026—Not yet due0
Sarosh ComplexSarosh Imran KohariP5170005147723 Jun 202331 Dec 2026—Not yet due0
Shiv ParadiseEagle Homes Builders And DevelopersP517000514088 Jun 202331 Mar 2026—Promised date passed0
Shree Siddhivinayak Park B1 And B2Satyashiv DevelopersP5170005006613 Mar 202331 Dec 2030—Not yet due0
Sai Siddhi ApartmentSai Siddhi DevelopersP5170004910430 Jan 202331 Dec 2024—Promised date passed0
Mohan HeightsMohan Atmaram SaseP5170004667129 Aug 202230 Jun 2026—Promised date passed0
Shree Prabhucharan Chs.ltdShree Prabhucharan Co-Op Housing SocietyP5170003503629 Apr 202231 Mar 2024—Promised date passed0
Shree Charan ApartmentShree Mangalmurti EnterprisesP5170003406424 Mar 202230 Apr 2024—Promised date passed0
Lake Emerald- Phase IN D EnterprisesP517000337798 Mar 202220 Apr 2027—Not yet due0
Swami Narendra ResidencyRaj Ratneshwari DevelopersP517000329192 Feb 202231 Dec 2026—Not yet due0
Techcons BaseraTechcons Constructional Engineering CoP5170003186122 Nov 202131 Dec 2026—Not yet due0
Madhusudan RetreatMadhusudan Leisure HomesP5170003097329 Sep 202131 Mar 2027—Not yet due1
Sarvatman Phase I A WingAnandwan ConstructionP5170003085920 Sep 202120 Jun 2026—Promised date passed0
Sai Balaji ComplexSai Balaji ComplexP5170003054430 Aug 202131 Jul 2024—Promised date passed0
Arjun HeightsNanda Arjun ShelkeP5170002904923 Apr 202131 Dec 2026—Not yet due1
Shree Mangalmurti Builders And DevelopersVasanti Kashinath ChaudhariP5170002710515 Nov 202030 Sep 2022—Promised date passed0
Shree Kakasheth Telavane SadanMauli ConstructionP517000243497 Feb 202030 Dec 2023—Promised date passed0
Morya GardenSumit DevelopersP517000237202 Jan 202030 Apr 202430 Apr 2027Extended 36 mo0
Diviana ParkAudumbar RealtorsP517000180063 Oct 201830 Oct 2039—Not yet due0
valencia enclavesiddhivinayak builders and developersP5170001777417 Sep 201830 Dec 2022—Promised date passed0
Sadguru DarshanOm Sadguru RealtorsP5170001713716 Jul 201829 May 2028—Not yet due0
Shree Siddhivinayak Park Wing A1 And A2Satyashiv DevelopersP517000167205 Jun 201830 Dec 2022—Promised date passed0
Malshej GreenGreen Space Real TechP517000158914 Apr 201830 Dec 202131 Dec 2024Extended 36 mo0
Shiv Shahi ComplexShalini Shivaji PawarP51700015735, P5170001701519 Mar 201830 Dec 202231 Mar 2030Extended 87 mo0
Vrindawan ResidencySankalp DevelopersP5170001568316 Mar 201828 Mar 2021—Promised date passed0
The Golden MileGracelands HabitatsP5170001532515 Feb 201830 Dec 2023—Promised date passed0
Swrnim ResidencyDys BuiltconP517000134767 Oct 201730 Dec 2021—Promised date passed0
Sahyadri Residency Phase IM/S Nirman DevelopersP5170001309914 Sep 201730 Dec 202230 Dec 2023Extended 12 mo0
Crystal HomesShreedham Construction Private LimitedP5170000728217 Aug 201730 Dec 2023—Promised date passed1
Karniks ExoticaKarniks ExoticaP517000039847 Aug 201730 Jan 2021—Promised date passed0
AmberP51700010503————0
GreenparkP51700013670————0
Green Park River ViewP51700013511————0
Palm GardensP51700021662————0
Sahyadri VillasP51700013836————0
Sai Sansar ResidencyP51700008197————0
Shine City ParkP51700007556————0
Shree Dattaguru ComplexP51700016318————0
Shree Samarth ParkP51700027802————0
Vrindavan GardenP51700008211————0

Other talukas in Thane

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Madhusudan Leisure Homes2 projects
  2. Satyashiv Developers2 projects
  3. Ajay & Sanjay Maheshwari1 project
  4. Anandwan Construction1 project
  5. Audumbar Realtors1 project
  6. Bhimraj Ganpat More1 project
  7. Deepak Shivaji Hindurao1 project
  8. Dys Builtcon1 project
  9. Eagle Homes Builders And Developers1 project
  10. Gracelands Habitats1 project
Data through8 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology