Skip to content
Deedo home
Menu

RERA projects in Ranjnoli

8 projects under 9 MahaRERA registrations, registered 2017–2026. 11% have a completion date extended beyond the one promised.

Locality
8RERA projects
9Registrationssome projects hold several
7Completion still due2 past their completion date
24 monthsMedian extension beyond promised date11% of registrations extended
0Regulatory casesnone on MahaRERA's lists
7Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20171
20180
20191
20200
20210
20222
20231
20241
20252
20261

Projects in Ranjnoli

8 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Metro HeightsBhakti RealtorsPR133000260193816 Sep 202631 Dec 2028—Not yet due0
Silver AnantamSayam Enterprises LLPPM13300025017045 Dec 202531 Jul 2031—Not yet due0
Bhumi World SkyGebi LLPPC133000250063425 Aug 202512 Aug 2028—Not yet due0
Riddhi Siddhi ParkM/S Shree Ganesh DevelopersP517000491571 Feb 202330 Sep 2029—Not yet due0
Siyara IconShakti RealtyP5170003476328 Apr 202231 Dec 2028—Not yet due0
Mahindra Happinest Kalyan 2 ProjectMahindra Lifespace Developers limitedP51700032925, P517000769632 Feb 202231 Dec 2028—Not yet due0
Sagar HomesM/S Sagar DevelopersP5170002136224 Jun 201930 Dec 202329 Dec 2025Extended 24 mo0
Amantra Phase 2Tata Housing Development Company LimitedP5170000030815 Jul 201731 Mar 2018—Promised date passed0

Other localities in Bhiwandi

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Bhakti Realtors1 project
  2. Gebi LLP1 project
  3. Mahindra Lifespace Developers limited1 project
  4. M/S Sagar Developers1 project
  5. M/S Shree Ganesh Developers1 project
  6. Sayam Enterprises LLP1 project
  7. Shakti Realty1 project
  8. Tata Housing Development Company Limited1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology