RERA projects in Ranjnoli
8 projects under 9 MahaRERA registrations, registered 2017–2026. 11% have a completion date extended beyond the one promised.
Locality
8RERA projects
9Registrationssome projects hold several
7Completion still due2 past their completion date
24 monthsMedian extension beyond promised date11% of registrations extended
0Regulatory casesnone on MahaRERA's lists
7Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 1 |
| 2018 | 0 |
| 2019 | 1 |
| 2020 | 0 |
| 2021 | 0 |
| 2022 | 2 |
| 2023 | 1 |
| 2024 | 1 |
| 2025 | 2 |
| 2026 | 1 |
Projects in Ranjnoli
8 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Metro HeightsBhakti Realtors | PR1330002601938 | 16 Sep 2026 | 31 Dec 2028 | — | Not yet due | 0 |
| Silver AnantamSayam Enterprises LLP | PM1330002501704 | 5 Dec 2025 | 31 Jul 2031 | — | Not yet due | 0 |
| Bhumi World SkyGebi LLP | PC1330002500634 | 25 Aug 2025 | 12 Aug 2028 | — | Not yet due | 0 |
| Riddhi Siddhi ParkM/S Shree Ganesh Developers | P51700049157 | 1 Feb 2023 | 30 Sep 2029 | — | Not yet due | 0 |
| Siyara IconShakti Realty | P51700034763 | 28 Apr 2022 | 31 Dec 2028 | — | Not yet due | 0 |
| Mahindra Happinest Kalyan 2 ProjectMahindra Lifespace Developers limited | P51700032925, P51700076963 | 2 Feb 2022 | 31 Dec 2028 | — | Not yet due | 0 |
| Sagar HomesM/S Sagar Developers | P51700021362 | 24 Jun 2019 | 30 Dec 2023 | 29 Dec 2025 | Extended 24 mo | 0 |
| Amantra Phase 2Tata Housing Development Company Limited | P51700000308 | 15 Jul 2017 | 31 Mar 2018 | — | Promised date passed | 0 |
Other localities in Bhiwandi
Most active promoters
By projects registered here, as named on MahaRERA.
- Bhakti Realtors1 project
- Gebi LLP1 project
- Mahindra Lifespace Developers limited1 project
- M/S Sagar Developers1 project
- M/S Shree Ganesh Developers1 project
- Sayam Enterprises LLP1 project
- Shakti Realty1 project
- Tata Housing Development Company Limited1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology